CONTRACTS AND SPECIFICATIONS BUREAU
Proposal
Proposal ID: 94-9260-024 Letting Date: September 29, 2026
Call Order: 006
Proposal Work Type: BRIDGE REPAIR
DBE Goal: 0.0%
Contracting Authority: IOWA DEPARTMENT OF TRANSPORTATION
Proposal Guaranty: $6,250.00
This proposal includes the following project(s):
Project Number: STPN-926-0(024)--2J-94 County: WEBSTER
Project Work Type: BRIDGE REPAIR Route: IOWA 926
Location: 2nd Ave S over CN RR and Merriweather Dr 0.8 mi E of N Jct US 169
Road System: PRIMARY ROAD (on NHS)
Federal Aid - Wages: Non-Federal Aid - Predetermined Wages are not in Effect
Project Number: STPN-926-0(025)--2J-94 County: WEBSTER
Project Work Type: BRIDGE REPAIR Route: IOWA 926
Location: 2nd Ave S over Des Moines River 0.6 mi S of N Jct US 169
Road System: PRIMARY ROAD (on NHS)
Federal Aid - Wages: Non-Federal Aid - Predetermined Wages are not in Effect
Contracts and Specifications Bureau
9/1/2026 12:53 PM
Contract Time
Proposal ID: 94-9260-024 Call Order: 006 Letting Date: September 29, 2026
Site ID Site Details Liquidated
Damages
00 11/9/2026 COMPLETION DATE $1,000.00
.
(*) - Indicates Cost Plus Time Site. See Schedule of Items for Cost Per Unit
Contracts and Specifications Bureau
9/1/2026 12:53 PM
Proposal ID: 94-9260-024 Call Order: 006 Letting Date: September 29, 2026
Notes
Notes :
There are no notes for this proposal.
Contracts and Specifications Bureau
9/1/2026 12:53 PM
Proposal Specifications List
Proposal ID: 94-9260-024 Call Order: 006 Letting Date: September 29, 2026
Note Description
001.2023 *** STANDARD SPECIFICATIONS -- SERIES 2023 ***
The Iowa Department of Transportation STANDARD SPECIFICATIONS FOR
HIGHWAY AND BRIDGE CONSTRUCTION, SERIES 2023, plus applicable General
Supplemental Specifications, Developmental Specifications, Supplemental
Specifications AND Special Provisions shall apply to construction work on this contract.
DS-23032 DEVELOPMENTAL SPECIFICATIONS FOR ELECTRONIC TICKETING
DS-23086 DEVELOPMENTAL SPECIFICATIONS FOR CONSTRUCTION OR MAINTENANCE
WORK ON RAILROAD RIGHT-OF-WAY (CHICAGO, CENTRAL, & PACIFIC
RAILROAD COMPANY, CEDAR RIVER RAILROAD COMPANY, AND IOWA
NORTHERN RAILWAY CO)
GS-23006 GENERAL SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE
CONSTRUCTION
SP-230445 SPECIAL PROVISIONS FOR ENVIRONMENTAL PROTECTION
Webster County
STPN-926-0(024)--2J-94
STPN-926-0(025)--2J-94
Contracts and Specifications Bureau
9/1/2026 12:53 PM
Proposal Schedule of Items
Proposal ID: 94-9260-024 Call Order: 006 Letting Date: September 29, 2026
SECTION: 0001
DESIGN NO. 0427; REPAIRS TO A 654'-8 X 57'-0 CONTINUOUS WELDED PLATE GIRDER BRIDGE STPN-926-
0(024)--2J-94
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0010 2533-4980005
MOBILIZATION LUMP SUM LUMP SUM _________._____
0020 2595-0005120
RAILROAD PROTECTIVE LIABILITY
INSURANCE FOR CHICAGO,
CENTRAL & PACIFIC RR / CEDAR
RIVER RR / IOWA NORTHERN
RAILWAY
LUMP SUM LUMP SUM _________._____
0030 2599-9999009 238.000
('LINEAR FEET' ITEM) Timber Protective
Shield
LF _________._____ _________._____
Section: 0001 Total: _________._____
SECTION: 0002
ROADWAY ITEMS - STPN-926-0(024)--2J-94
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0040 2528-2518000 2.000
SAFETY CLOSURE EACH _________._____ _________._____
0050 2528-8445110
TRAFFIC CONTROL LUMP SUM LUMP SUM _________._____
0060 2528-9290050 6.000
PORTABLE DYNAMIC MESSAGE SIGN
(PDMS)
CDAY _________._____ _________._____
Section: 0002 Total: _________._____
Contracts and Specifications Bureau
9/1/2026 12:53 PM
Proposal Schedule of Items
Proposal ID: 94-9260-024 Call Order: 006 Letting Date: September 29, 2026
SECTION: 0003
DESIGN NO. 0527; REPAIRS TO A 90'-0 X 58'-0 MULTISPAN CONTINUOUS WELDED PLATE GIRDER BRIDGE
PLUS STPN-926-0(025)--2J-94
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0070 2533-4980005
MOBILIZATION LUMP SUM LUMP SUM _________._____
0080 2599-9999009 63.000
('LINEAR FEET' ITEM) Timber Protective
Shield
LF _________._____ _________._____
Section: 0003 Total: _________._____
SECTION: 0004
ROADWAY ITEMS - STPN-926-0(025)--2J-94
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0090 2528-2518000 4.000
SAFETY CLOSURE EACH _________._____ _________._____
0100 2528-8445110
TRAFFIC CONTROL LUMP SUM LUMP SUM _________._____
Section: 0004 Total: _________._____
Total Bid: _________._____
DS-23032
(New)
DEVELOPMENTAL SPECIFICATIONS
FOR
ELECTRONIC TICKETING
Effective Date
October 17, 2023
THE STANDARD SPECIFICATIONS, SERIES 2023, ARE AMENDED BY THE FOLLOWING
MODIFICATIONS AND ADDITIONS. THESE ARE DEVELOPMENTAL SPECIFICATIONS AND THEY
SHALL PREVAIL OVER THOSE PUBLISHED IN THE STANDARD SPECIFICATIONS.
23032.01 DESCRIPTION.
A. This work shall consist of providing electronic material tickets for all loads of flexible paving
mixture or ready mixed PCC delivered to the project. Electronic ticketing will only be required for
the primary material supplied to the project, i.e. flexible paving mixture for an HMA resurfacing
project or PCC for a PCC paving project. Electronic tickets for other materials supplied to a
project may be submitted at the Contractor’s option. The Contractor/supplier can use the plant
ticketing system of their choice to create the material ticket data.
B. Ticket data shall include the following:
1. After each truck is loaded, ticket data must be electronically captured, and ticket information
uploaded via web service / Application Programming Interface (API) to the agency.
2. Material ticket data will be submitted to https://iowa.dot-portal.io via an HTTPS POST as
JSON documents. Include the API key specific to each customer in each request as an HTTP
header.
3. Material supplier must test to confirm that ticketing data can be shared from the originating
system no less than 30 days prior to project start. Topic shall be discussed at the pre-
construction meeting.
4. Ticket data must be available immediately upon project start so there are no delays to
viewing tickets.
5. Provide the same data that is currently accessible and viewed by agency users previously on
printed tickets specific to state projects.
6. Transmit ticket data before the truck leaves the plant and transmit any updates to the ticket
data within 5 minutes of a change.
DS-23032, Page 2 of 3
23032.02 CONSTRUCTION DATA.
Contractor shall submit material ticket data in accordance with the plant manufacturer’s system
recommendations to provide the following.
A. Net weight (or volume for ready mix concrete) of material being transported (to nearest 0.01 ton
or cubic yard).
B. Running daily total of net weight of material (or volume for ready mix concrete) being transported
(to the nearest 0.01 ton or cubic yard).
C. Each material ticket shall contain the following:
1. General Ticket information (All Material).
a. Date.
b. Iowa DOT Project Number.
c. Name of Contractor
d. Name of material supplier.
e. Unique truck ID.
f. Plant/scale name (source).
g. Truck Status Times:
1) Loaded time (time batched) shall be available.
2) Provided other truck status times as available.
a) Ticketed.
b) Load time.
c) Left plant.
d) Arrive at project.
e) Begin unload.
f) Finish unload.
g) Leave project.
2. Portland Cement Concrete.
a. Loaded time (water/cement time).
b. Wet and dry batch weights (if computer generated).
c. Water:
1) In aggregate.
2) Total water.
3) Water/cement ratio.
4) Max water/cement ratio.
5) Allowable water to add.
d. Admixtures (including brand names if available):
1) Retarder and weights.
2) Water reducer and weights.
3) Air entrainment and weights.
4) Special performance admixtures and weights.
5) Concrete fibers.
e. Cementitious material(s) and weights.
f. CPI Name and certificate number.
3. Flexible Pavement Mixture.
a. Type of material.
b. Gross weight (if not automatic weighed).
c. Tare weight (if not automatic weighed).
d. Net weight.
e. Mix design number.
DS-23032, Page 3 of 3
23032.03 METHOD OF MEASUREMENT.
None.
23032.04 BASIS OF PAYMENT.
Payment for electronic ticketing will be incidental to the material being provided.
DS-23086
(Replaces DS-23047)
DEVELOPMENTAL SPECIFICATIONS
FOR
CONSTRUCTION OR MAINTENANCE WORK ON RAILROAD RIGHT-OF-WAY (CHICAGO,
CENTRAL, AND PACIFIC RAILROAD COMPANY, AND CEDAR RIVER RAILROAD COMPANY, AND
IOWA NORTHERN RAILWAY COMPANY)
Effective Date
July 21, 2026
THE STANDARD SPECIFICATIONS, SERIES 2023, ARE AMENDED BY THE FOLLOWING
MODIFICATIONS AND ADDITIONS. THESE ARE DEVELOPMENTAL SPECIFICATIONS AND THEY
PREVAIL OVER THOSE PUBLISHED IN THE STANDARD SPECIFICATIONS.
23086.01 DESCRIPTION.
This specification applies to projects on the Interstate, Primary, Secondary, and Local Road systems
involving construction or maintenance of roadways and structures on Chicago, Central, and Pacific
Railroad Company, and Cedar River Railroad Company, and Iowa Northern Railway Company
(collectively CCP) Right-of-way (ROW).
This specification describes the following:
• Requirements when work is within the ROW or properties of the CCP and adjacent to tracks, wire
lines, and other facilities.
• Coordination with CCP when work by the Contractor will be performed upon, over, or under the CCP
ROW, or may impact current or future CCP operations.
CCP representatives will be the persons identified by the CCP Chief Engineer to handle specific tasks
related to the project. The attachments specify the contact information for these individuals.
Prior to advertising the project for letting, Contracting Authority will negotiate and obtain an agreement
with the CCP for the work on CCP ROW. Contractor will also be required to enter into a Right of Entry
agreement with the CCP for the purpose of coordinating Contractor work and CCP train activities. A copy
of this agreement is attached as DS-23086, Attachment A.
Contractor shall provide physical barriers approved by CCP to protect track and ballast from damage and
contamination when the Contractor’s equipment is operating within 25 feet from nearest rail.
23086.02 REQUESTS FOR INFORMATION.
Requests for information involving work within any CCP ROW shall be in accordance with the procedures
listed in the contract documents. Requests shall be submitted to the Engineer. Engineer will forward the
request to the CCP as necessary.
23086.03 CONSTRUCTION AND AS-BUILT SUBMITTALS.
DS-23086, Page 2 of 20
A. Submittals are required for construction materials and procedures as outlined below. The
submittals shall include all review comments from the Engineer. Design submittals shall be
stamped and signed by a Professional Engineer registered in the State of Iowa.
B. The tables below provide CCP’s minimum submittal requirements for the construction items
noted. Submittal requirements are in addition to those specified elsewhere in the contract
documents. The minimum review times indicated below represent CCP’s requirements only.
Contractor shall allow additional time for the CCP’s review time as stated elsewhere in the
contract documents.
For this specification the following definitions shall apply:
• Overpass: when the roadway bridges over the railroad.
• Underpass: when the roadway crosses under the railroad.
C. Submittals will be made by the Engineer to the CCP. Items in Table DS-23086.04-1 shall be
submitted for both railroad overpass and underpass projects, as applicable. Items in Table DS-
23086.04-2 shall be submitted for underpass projects only.
Prior to or during construction of underpass structures, the CCP requires the review and approval
of drawings, reports, test data, and material data sheets to determine compliance with the
specifications. Product information for items noted in Table DS-23086.04-2 shall be submitted to
CCP through the Engineer for their review and approval. The signed submittal and the Engineer’s
review comments will be reviewed and approved by CCP.
Table DS-23086.04-1: Review Sets and Minimum Time for Review
Description Sets Required CCP’s Minimum
Review Time
Shoring design and details 2 4 weeks
Falsework design and details 2 4 weeks
Drainage design provisions 2 4 weeks
Erection diagrams and sequence 2 4 weeks
Demolition diagram and sequence 2 4 weeks
Table DS-23086.04-2: Sets Required
Description Sets Required Notes
Shop drawings 4 Steel and Concrete members
Bearings 4 For entire structures
Concrete Mix Designs 4 For entire structures
Rebar & Strand certifications 4 For superstructure only
28 day concrete strength 4 For superstructure only
Waterproofing material
certifications and installation
procedure
4 Waterproofing & protective
boards
Structural steel certifications 4
All fracture critical members &
other members requiring
improved notch toughness
Fabrication and Test reports 4
All fracture critical members &
other members requiring
improved notch toughness.
Welding Procedures and Welder
Certification 4 AWS requirements
DS-23086, Page 3 of 20
Description Sets Required Notes
Foundation Construction Reports 4
Pile driving, drilled shaft
construction, bearing pressure
test reports for spread
footings.
Compaction testing reports for
backfill at abutments 4
Must meet 95% maximum dry
density, Modified Proctor
ASTM D 1557.
D. As-Built Records will be submitted to the CCP by the Contracting Authority within 1 year of
completion of the structures. These records shall consist of the following items:
1. Overpass Projects.
• Electronic files of all structure design drawings with as-constructed modifications shown
in Auto-Cad Civil 3D or Acrobat .PDF format.
• Hard copies of all structure design drawings with as-constructed modifications shown.
2. Underpass Projects.
• Electronic files of all structure design drawings with as-constructed modifications shown,
in Auto-Cad Civil 3D or Acrobat .PDF format.
• Hard copies of all structure design drawings with as-constructed modifications shown.
• Final approved copies of shop drawings for concrete and steel members.
• Foundation Construction Reports
• Compaction testing reports for backfill at abutments
23086.04 SITE INSPECTIONS BY THE CCP.
Site inspections may be performed by the CCP at any point during construction, including but not limited
to the following:
• Preconstruction meetings
• Pile driving, drilling of caissons or drilled shafts
• Reinforcement & concrete placement for railroad bridge substructure or superstructure
• Erection of precast concrete or steel bridge superstructure
• Placement of waterproofing (prior to placing ballast on bridge deck)
• Completion of the bridge structure
A detailed construction schedule, including the proposed temporary horizontal and vertical clearances
and construction sequence for all work to be performed, shall be provided to the Engineer for submittal to
the CCP for review and approval prior to commencement of work. This schedule shall also include the
anticipated dates when the above listed events will occur. This schedule shall be updated for the above
listed events as necessary, but at least monthly so that site visits may be scheduled.
23086.05 CCP REPRESENTATIVES.
CCP representatives will be provided at the expense of the Contractor to protect CCP facilities, property,
and movements of its trains or engines. CCP may, at the Contractor’s sole cost, risk and expense, furnish
whatever protective services it considers necessary, including, but not limited to, flagger(s), inspector(s),
and stand-by personnel.
In general, CCP will furnish such personnel or other protective services as follows:
• Flagging protection will be required during any operation involving direct and potential interference
with CCP's tracks or traffic. This may include but is not limited to fouling of railroad operating
clearances, reasonable proximity of accidental hazard to railroad traffic, work within 25 feet
horizontally of the nearest centerline, any work over any railroad track, or in any other condition that
CCP deems protective services necessary, which may include work on or off CCP’s property more
than 25 feet from the nearest centerline of a railroad track, such as any equipment extension
DS-23086, Page 4 of 20
(including but not limited to a crane boom) that will reach or has the potential to reach within 25 feet of
any track.
• For any excavation below elevation of track subgrade if, in the opinion of CCP, track or other CCP
facilities may be subject to settlement or movement.
• During any clearing, grubbing, excavation, or grading, or other construction activity in proximity to
CCP facilities, which, in the opinion of CCP, may endanger CCP facilities or operations.
• During the Contractor’s operations when, in the opinion of CCP, CCP facilities, including, but not
limited to, tracks, buildings, signals, wire lines, or pipe lines, may be endangered.
• The Contractor shall arrange with the CCP to provide the adequate number of flag persons to
accomplish the work.
Contractor shall be required to pay CCP in advance for the cost of personnel or other protective services.
Prepayment will be based on Contractor’s estimated time for needing protective services, and if that
prepayment will be exhausted prior to the expiration of the contractor’s need for protective services,
additional prepayment funds will be needed to cover the new projected completion of the project.
In the event CCP is unable to furnish flagging protection, inspection services, or standby personnel at the
desired time or on the desired date(s), Contractor shall not perform the said operation or work until such
time and date(s) that appropriate CCP services can be made available. CCP shall not be liable for any
delay or increased costs incurred by Contractor owing to CCP's inability or failure to have appropriate
CCP services available at the time or on the date requested.
23086.06 INSURANCE.
Before the contract is awarded, Contractor shall submit to the Department a certificate of insurance
evidencing the coverage. The certificate shall identify the insurance company firm name and address,
Contractor firm name, policy period, type of policy, limits of coverage, and scope of work covered
(including project number). Policies shall provide no less than 30 calendar days prior written notice to
Contracting Authority and Railroad of cancellation or material change in policies. Following award of the
Contract, the Contractor shall submit a certificate of insurance evidencing the foregoing coverage to the
Railroad and Contracting Authority (if other than the Department), and a certified, true, and complete copy
of policy or policies to the Contracting Authority and Railroad. Upon request from either the Contracting
Authority or Railroad, a certified duplicate original of any required certificate or policy shall be furnished at
no cost to the Contracting Authority or Railroad.
Contractor shall not enter upon or over CCP’s ROW until the Engineer and CCP have been furnished the
insurance policies, binders, certificates, and endorsements required by the contract documents and the
Right of Entry Agreement (Attachment A) has been executed by the Contractor and CCP. Insurance shall
be kept in full force and effect during the performance of work and thereafter until the Contractor removes
all tools, equipment, and material from CCP’s property and cleans the premises in a manner reasonably
satisfactory to CCP.
In addition to providing to CCP the insurance binders, endorsements, and certificates described below,
Contractor shall also provide the subcontractor insurance endorsements described in Article DS-
23086.08; ASSIGNMENT, SUBCONTRACTING, AND INSURANCE ENDORSEMENTS.
Contractor shall provide the following kinds of insurance:
A. Railroad Protective Insurance.
The Contractor shall provide for and on behalf of the CCP, Railroad Protective Insurance as
stated in the Code of Federal Regulations, Title 23, Part 646, and any revisions thereto issued by
the Federal Highway Administration for damages due to bodily injury or death of persons, and
injury to or destruction of property resulting from the operations of the Contractor, subcontractors,
or their agents, officers, or employees on this project.
Railroad Protective Liability Insurance is required for work involving elimination of hazards of
railroad highway crossings and other highway work wholly or partly within Railroad ROW. This
DS-23086, Page 5 of 20
insurance shall name either one of the Chicago, Central & Pacific Railroad Company, or the
Cedar River Railroad Company, or the Iowa Northern Railway Company, as determined by
project location, as the Insured with coverage of at least $5,000,000.00 per occurrence and
$10,000,000.00 in the aggregate. The policy shall be issued on a standard ISO form CG 00 35 10
93 and include the following:
• Endorsed to include the Pollution Exclusion Amendment (ISO form CG 28 31 10 93) and on
ISO form CG 28 31 10 93.
• Endorsed to include the Limited Seepage and Pollution Endorsement.
• Endorsed to include Evacuation Expense Coverage Endorsement.
• No other endorsements restricting coverage may be added.
• The original policy shall be provided to the Engineer and Railway prior to performing work.
Contractor shall use the website listed below to acquire Railroad train movement information for
the purpose of obtaining Railroad Protective Liability Insurance:
https://safetydata.fra.dot.gov/OfficeofSafety/PublicSite/Crossing/Crossing.aspx
The US DOT Crossing Inventory Number will be located in the project plans. Zero trains per day
will be displayed on the crossing inventory report for locations with grade separated crossings or
at-grade crossings when there is less than one train per day. In these situations generating a
map to find alternative crossing locations may be used to provide the number of trains per day
and speed nearest the project location.
B. Commercial General Liability Insurance.
Commercial General Liability (CGL) (occurrence based) with a limit of not less than
$5,000,000.00 each occurrence and an aggregate limit of not less than $10,000,000.00. CGL
insurance shall be written on ISO occurrence form CG 00 01 12 04 (or a substitute form providing
equivalent coverage).
Policy shall also contain the following endorsement, which shall be stated on the certificate of
insurance:
• Contractual Liability Railroads ISO form CG 24 17 10 01 (or a substitute form providing
equivalent coverage) showing either one of “Chicago Central & Pacific Railroad Company”, or
“Cedar River Railroad Company Property”, or “Iowa Northern Railway Company”, as the case
may be, as the Designated Job Site.
• Designated Construction Project(s) General Aggregate Limit ISO Form CG 25 03 03 97 (or a
substitute form providing equivalent coverage) showing the project on the form schedule.
C. Business Automobile Coverage Insurance.
Business auto coverage written on ISO form CA 00 01 (or a substitute form providing equivalent
liability coverage) with a combined single limit of not less $5,000,000.00 for each accident.
Policy shall contain the following endorsements, which shall be stated on the certificate of
insurance:
• Coverage For Certain Operations In Connection With Railroads ISO form CA 20 70 10 01 (or
a substitute form providing equivalent coverage) showing either one of “Chicago Central and
Pacific Railroad Company”, and “Cedar River Railroad Company Property”, or “Iowa Northern
Railway Company” as the Designated Job Site.
• Motor Carrier Act Endorsement - Hazardous materials clean up (MCS-90), if required by law.
D. Workers Compensation and Employers Liability Insurance.
Coverage shall include, but not limited to:
• Contractor's statutory liability under the workers' compensation laws of the State of Iowa.
• Employers' Liability (Part B) with limits of at least $500,000.00 each accident, $500,000.00
disease policy limit, $500,000.00 each employee.
DS-23086, Page 6 of 20
If Contractor is self-insured, evidence of the State of Iowa’s approval and excess workers
compensation coverage shall be provided. Coverage shall include liability arising out of the U. S.
Longshoremen's and Harbor Workers' Act, the Jones Act, and the Outer Continental Shelf Land
Act, if applicable.
Policy shall contain the following endorsement, which shall be stated on the certificate of
insurance:
Alternate Employer endorsement ISO form WC 00 03 01 A (or a substitute form providing
equivalent coverage) showing CCP in the schedule as the alternate employer (or a substitute
form providing equivalent coverage).
E. Umbrella Insurance.
If Contractor utilizes umbrella policies, these policies shall “follow form” and afford no less
coverage than the primary policy. Excess coverage is not allowed.
F. Pollution Liability Insurance.
Pollution liability coverage shall be written on ISO form Pollution Liability Coverage Form
Designated Sites CG 00 39 12 04 (or a substitute form providing equivalent liability coverage),
with limits of at least $1,000,000.00 per occurrence and an aggregate limit of $2,000,000.00.
If scope of work as defined in this contract includes the disposal of any hazardous or non-
hazardous materials from the job site, Contractor shall furnish to CCP evidence of pollution legal
liability insurance maintained by the disposal site operator for losses arising from the insured
facility accepting the materials, with coverage in minimum amounts of $1,000,000.00 per loss,
and an annual aggregate of $2,000,000.00.
G. Policy(ies) required above (except worker’s compensation and employers liability) shall include
“all operating subsidiaries of North American Railways, Inc.” as “Additional Insured” using ISO
Additional Insured Endorsements CG 20 26, and CA 20 48 (or substitute forms providing
equivalent coverage). The coverage provided to “all operating subsidiaries of North American
Railways, Inc.” as additional insured shall, to the extent provided under ISO Additional Insured
Endorsement CG 20 26, and CA 20 48 provide coverage for the CCP’s negligence whether sole
or partial, active or passive, and shall not be limited by Contractor's liability under the indemnity
provisions contained in the specifications.
H. Punitive damages exclusion, if any, shall be deleted (and the deletion indicated on the certificate
of insurance), unless the law governing prohibits all punitive damages that might arise in
connection with this contract.
I. Contractor waives all rights of recovery, and its insurers also waive all rights of subrogation of
damages against Railroad and its agents, officers, directors, and employees. This waiver shall be
stated on the certificate of insurance.
J. The address to be shown for “Chicago, Central & Pacific Railroad Company and its Parents”, or
“Cedar River Railroad Company and its Parents”, or “Iowa Northern Railway Company and its
Parents” on all policies and certificates shall be:
Attn: Diane Lewis
17641 S Ashland Ave
Homewood Il, 60430
715.332-3557 (office)
Diane.Lewis@cn.ca
DS-23086, Page 7 of 20
K. Insurance policies shall be written by a reputable insurance company acceptable to the CCP or
with a current Best's Insurance Guide Rating of A- and Class VII or better, and authorized to do
business in the State of Iowa.
L. The fact that insurance is obtained by the Contractor or by the CCP on behalf of the Contractor
shall not be deemed to release or diminish the liability of the Contractor, including, without
limitation, liability under the indemnity provisions of this contract. Damages recoverable by the
CCP from the Contractor or any third party shall not be limited by the amount of the required
insurance coverage.
23086.07 ASSIGNMENT, SUBCONTRACTING, AND INSURANCE ENDORSEMENTS.
Contractor shall not assign or subcontract the provisions of this specification, or any interest therein,
without the written consent of the Engineer. Contractor shall be responsible for the acts and omissions of
all subcontractors. Before Contractor commences any work, they shall, except to the extent prohibited by
law; (1) require each subcontractor to include the Contractor and “all operating subsidiaries of North
American Railways, Inc.” as "Additional Insureds" in the subcontractor's Commercial General Liability
policy and Business Automobile policies with respect to all liabilities arising out of the subcontractor's
performance of work on behalf of the Contractor by endorsing these policies with ISO Additional Insured
Endorsements CG 20 26, and CA 20 48 (or substitute forms providing equivalent coverage; (2) require
each subcontractor to endorse their Commercial General Liability Policy with "Contractual Liability
Railroads" ISO Form CG 24 17 10 01 (or a substitute form providing equivalent coverage) for the job site;
and (3) require each subcontractor to endorse their Business Automobile Policy with "Coverage For
Certain Operations In Connection With Railroads" ISO Form CA 20 70 10 01 (or a substitute form
providing equivalent coverage) for the job site.
23086.08 ADDITIONAL SAFETY REQUIREMENTS.
Personnel employed by the Contractor or subcontractors shall complete the course “CN Contractor
Security/Safety Course”, and be registered prior to working on CCP property, except that such personnel
are not required to execute the Right of Entry form for contractors, it being understood that all contractors
or subcontractors shall instead execute the Right of Entry Agreement attached to this specification. The
CCP orientation course is available at: www.contractororientation.com. This course shall be completed
annually.
CCP has exempted from this requirement those it classifies as “Delivery Persons” from this training, such
as UPS, FedEx, trucking companies, etc. who merely access the property to supply materials or
equipment.
Contractor shall require its employees to be suitably dressed to perform their duties safely. Contractor
shall require workers to wear personal protective equipment as specified by CCP rules and regulations.
Personal protective equipment will be of safe design and construction for the work to be performed and
shall be maintained in a sanitary and reliable condition. Protective equipment shall include, but not be
limited to the following PPE listed below that meet the U.S. ANSI standards (American National
Standards Institute):
• Eye and face protection ANSI Z 96.1
• Head protection ANSI Z 89.1
• Foot protection ANSI Z 41.1
• High Visibility apparel ANSI / ISEA Z 107
Additional eye protection shall be provided to meet specific job situations such as welding, grinding,
burning, etc.; and hearing protection which affords enough attenuation to give protection from noise levels
that will be occurring on the job site. Only waist length shirts with sleeves and trousers covering the entire
leg shall be worn. Flare-legged trouser bottoms shall be tied to prevent catching.
CCP requires that the Contractor provide their personnel with the proper training, and that Contractor’s
personnel are provided with 1) a sticker to be affixed visibly on their hard hat and 2) a qualification card
so that CCP employees know that Contractor’s personnel are familiar with CCP safety practices and proof
DS-23086, Page 8 of 20
of having successfully completed the “CN Contractor Security/Safety Course” course. If a Contractor’s
employee does not have the sticker and qualification card, that Contractor employee will not be allowed
on CCP property.
Heavy equipment operating within CCP ROW shall be equipped with audible back-up warning devices. If
in the opinion of the CCP the Contractor’s equipment is unsafe for use on CCP’s ROW, Contractor shall
remove such equipment from CCP ROW.
Contractor shall promptly notify CCP of any U.S. OSHA or FRA reportable injuries occurring to any
employee that arises during the work performed on the work site within CCP ROW or for CCP.
If at any time the Engineer or CCP is of the opinion that any work of the Contractor is being or is about to
be done or prosecuted without due regard and precaution for safety and security, or in violation of any
applicable safety rule, the Engineer may suspend work until proper protective measures are adopted and
provided to the satisfaction of the CCP. In addition, if CCP has a reasonable, good faith belief that the
Contractor is engaging, or is about to engage, in any activity that poses a substantial risk of causing great
bodily injury or death to any person, or significant property damage, CCP may suspend the work of the
Contractor and shall as soon as possible thereafter contact the Engineer to review the circumstances of
the work stoppage. CCP shall thereafter abide by the decision of the Engineer as to the necessity of the
work stoppage.
23086.09 SAFETY MEASURES-PROTECTION OF OPERATIONS.
Contractor shall perform work in a safe manner and in conformity with the following standards:
A. Explosives.
Contractor shall not discharge any explosives on or in the vicinity of the CCP's property without
the prior consent of the CCP, which shall not be given if, in the sole discretion of the CCP, such
discharge would be dangerous or would interfere with the CCP's property or facilities. For the
purposes hereof, the "vicinity of the CCP's property" shall be deemed to be any place on the
CCP's property or in such close proximity to the CCP's property that the discharge of explosives
could cause injury to the CCP's employees or other persons, or cause damage to or interference
with the facilities or operations on the CCP's property. CCP reserves the right to impose
limitations on the transportation, handling, storage, security, and use of explosives as the CCP, in
the CCP's sole discretion, may deem to be necessary, desirable, or appropriate. In addition to
any limitations as may be specifically imposed:
1. Contractor shall provide no less than 48 hours written notice, excluding weekends and
holidays, before discharging any explosives.
2. Any explosives loaded in holes, placed or otherwise readied for discharge, shall be
discharged the same day during daylight hours, and at mutually acceptable times.
3. Contractor, at its own expense, shall take all precautionary measures and construct all
temporary shelters necessary to guard against danger of damage, destruction, or
interference arising out of or connected with any blasting or any transportation, handling,
storage, security, or use of explosives.
B. Obstructions to View.
Except as otherwise provided herein, Contractor shall not cause or permit the view along the
tracks of the CCP to be obstructed, nor place any combustible material on the crossing area, nor
erect any structures thereon except as allowed by the contract documents.
C. Excavation.
Contractor shall not excavate from existing slopes nor construct new slopes which are excessive
and may create hazards of slides or falling rock, impair, or endanger the clearance between
existing or new slopes and the tracks of the CCP. Contractor shall not perform work that may
disturb stability of any area or adversely affect CCP's tracks or facilities. Contractor, at its own
DS-23086, Page 9 of 20
expense, shall install and maintain adequate shoring and cribbing for all excavation or trenching
performed by them in connection with construction, maintenance, or other work. Shoring and
cribbing shall be constructed and maintained with materials and in a manner approved by CCP to
withstand all stresses likely to be encountered, including any stresses resulting from vibrations
caused by CCP's operations in the vicinity.
D. Drainage.
Contractor, at its expense, shall provide and maintain suitable facilities for draining the highway
and its appurtenances, and shall not suffer or permit drainage water to flow or collect upon
property of CCP that may adversely affect any of CCP’s operations, equipment or any third
parties with permitted facilities on CCP’s ROW. Contractor, at its own expense, shall provide
adequate passageway for the waters of any streams, bodies of water, and drainage facilities
(either natural or artificial, and including water from CCP's culverts and drainage facilities), so that
said waters may not, because of any facilities or work of Contractor, be impeded, obstructed,
diverted or caused to back up, overflow or damage the property of the CCP or any part thereof, or
property of others. Contractor shall not obstruct or interfere with existing ditches or drainage
facilities.
E. Clearances.
Contractor shall provide a minimum vertical clearance of 22.0 feet above top of rails and a
minimum lateral clearance of 12.5 feet from centerline of track nearest temporary construction
falsework. No materials, supplies, or equipment will be stored within 25 feet from centerline of any
railroad track, measured at right angles thereto.
Proposed changes to specified minimum clearances shall be submitted in writing to CCP, through
the Engineer, at least 30 calendar days in advance of the work. No work shall commence until
Engineer receives concurrence, in writing, from CCP that approval is given and that
arrangements have been made for flagging service, as may be necessary. CCP will have 15
calendar days to respond to the request.
F. Demolition of Existing Structures.
Contractor shall submit demolition plans to the Engineer for review and approval. Engineer will
forward such plans to CCP as identified in the project agreement for CCP to review and approve.
Demolition performed over or near CCP track will require proper protective shielding or other
measures (as identified on the plans) as maybe required by CCP, and Contractor shall be
required provide signed plans, signed by a Professional Engineer licensed in the State of Iowa,
and schedule for review and approval by CCP. Such protective shielding or measures shall be
designed for immediate removal by Contractor whenever instructed to do so by CCP. Demolition
shall not be undertaken until CCP has advised Engineer of its approval of the plans and
schedule, and Contractor has received the Engineer’s and CCP’s written approval of such
demolition plans and schedule. All such reviews and approvals or rejections will be completed by
the Engineer and CCP within 45 calendar days of receipt from Contractor.
23086.10 WALKWAYS.
Along the outer side of each exterior track of multiple operated track, and on each side of single operated
track, an unobstructed continuous space suitable for CCP’s use in walking along trains, extending to a
line not less than 12 feet from centerline of track, shall be maintained. Temporary impediments to
walkways and track drainage encroachments or obstructions allowed during work hours while CCP’s
flagging service is provided shall be removed before the close of each work day. Walkways with railings
shall be constructed by Contractor over open excavations when in close proximity of track, and railings
shall not be closer than 8.5 feet horizontally from center line of tangent track or 9.5 feet horizontally from
centerline of curved track.
DS-23086, Page 10 of 20
23086.11 EXCAVATIONS IN CLOSE PROXIMITY TO CCP FACILITIES.
Contractor shall take special precaution in connection with excavating and shoring. Excavations for
construction of footings, piers, columns, walls, or other facilities that require shoring shall comply with the
following requirements: OSHA, AREMA, and CCP “Guidelines for Temporary Shoring”.
Contractor shall contact CCP for facility locates at least 5 working days prior to commencing work at
telephone number 734.783.4533 during normal business hours (7:00 a.m. to 3:00 p.m. C.S.T., Monday
through Friday, except holidays. Contractor shall pay CCP in advance for the cost of CCP locates. Cost
for a cable locate is currently $350.00. If a telecommunications system is buried anywhere on or near
CCP property, Contractor shall coordinate with CCP and the telecommunication company to arrange for
relocation or other protection of the system prior to beginning any work on or ne
- Package Files
- Name
- 29SEP006\Plan\94-9260-024\94-9260-024_C.pdf
- Bytes
- 45198741
- Name
- 29SEP006\Plan\94-9260-025\94-9260-025_C.pdf
- Bytes
- 54784532
- Name
- 29SEP006\Prop\DS-23032.pdf
- Bytes
- 47943
- Name
- 29SEP006\Prop\DS-23086.pdf
- Bytes
- 908951
- Name
- 29SEP006\Prop\estprop006.pdf
- Bytes
- 197221
- Name
- 29SEP006\Prop\SP-230445.pdf
- Bytes
- 136448
- Package Pages
- 29
- Categorized By
- llm
- Package Scope Docs
- 3
- Package Manifest Only
- No