Brunswick-Glynn County Joint Water & Sewer Commission is requesting Proposals for the design and construction of the following Project: Progressive Design Build Services for the North Mainland Water Pollution Control Facility Construction and Commissioning.
Proposals for the construction of the Project will be received at 1703 Gloucester Street, Brunswick, Georgia 31520, until Thursday, October 29, 2026, at 12:00 NOON EST.
To meet its future wastewater treatment needs, the BGJWSC plans to add a new water pollution control facility (North Mainland WPCF) on undeveloped property near Exit 42 along Interstate 95 in Glynn County, Georgia to provide additional treatment capacity to meet current and future system demands.
Due to rapid residential growth in the area and the potential for industrial development in the proposed sewershed, the selected Design-Builder will be required to plan for future expansions and include key infrastructure in the design and construction of the new WPCF to allow future treatment capacity to be easily added.
The Project will meet the BGJWSC's objectives of ensuring adequate treatment capacity and complying with regulations and water quality goals. Potential project components include: construction of a new Water Pollution Control Facility on the BGJWSC's property, offsite effluent discharge piping extension to the receiving water, extension of approximately 2,000 linear feet of gravity sewer to the proposed plant site, and connection of existing upstream force mains to the gravity sewer system that feeds the plant site.
The Project will include the planning, evaluation, design, construction, commissioning, and startup necessary to place the Project in full operation according to contract requirements.
The Project is to be designed and constructed using the progressive design-build delivery method.
ADVERTISEMENT
REQUEST FOR PROPOSALS
BRUNSWICK-GLYNN COUNTY JOINT WATER & SEWER COMMISSION
1703 Gloucester Street
Brunswick, Georgia 31520
RFP NO 27-002 PROGRESSIVE DESIGN- BUILD SERVICES FOR
NORTH MAINLAND WATER POLLUTION CONTROL FACILITY
CONSTRUCTION AND COMMISSIONING
Brunswick-Glynn County Joint Water & Sewer Commission is requesting Proposals for the
design and construction of the following Project: Progressive Design Build Services for the
North Mainland Water Pollution Control Facility Construction and Commissioning.
Proposals for the construction of the Project will be received at 1703 Gloucester Street,
Brunswick, Georgia 31520, until Thursday, October 29, 2026, at 12:00 NOON EST.
To meet its future wastewater treatment needs, the BGJWSC plans to add a new water pollution
control facility (North Mainland WPCF) on undeveloped property near Exit 42 along Interstate
95 in Glynn County, Georgia to provide additional treatment capacity to meet current and future
system demands.
Due to rapid residential growth in the area and the potential for industrial development in the
proposed sewershed, the selected Design-Builder will be required to plan for future expansions
and include key infrastructure in the design and construction of the new WPCF to allow future
treatment capacity to be easily added.
The Project will meet the BGJWSC’s objectives of ensuring adequate treatment capacity and
complying with regulations and water quality goals.
The project includes planning, evaluation, design, construction, commissioning, and startup of a new Water Pollution Control Facility on BGJWSC property near Exit 42 along Interstate 95 in Glynn County, Georgia. Potential components include construction of the WPCF, offsite effluent discharge piping extension, extension of approximately 2,000 linear feet of gravity sewer to the plant site, and connection of existing upstream force mains to the gravity sewer system. The work is divided into phases: Phase 1A (prepare Initial Design Report to ~15% design), Phase 1B (prepare design to 60% and a Phase 2 Proposal including a Guaranteed Maximum Price), and Phase 2 (complete design, construction, performance testing, startup commissioning, and operator training). The Design-Builder must plan for future expansions and include key infrastructure to allow future treatment capacity to be easily added.
We post new general contractors opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Georgia work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-66315-NONST-2027-000000024), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.