The City of Marble Falls is soliciting competitive bids from qualified contractors for the renovation and expansion of the existing public restroom facility at Westside Park in Marble Falls, Texas.
The scope of work includes selective demolition of existing building components; removal and replacement of the existing roof structure; renovation of the existing men's and women's restrooms; construction of additional single-user, family-style restrooms; and associated structural, architectural, mechanical, electrical, plumbing, and site improvements.
Improvements include new masonry construction, stone veneer, standing-seam metal roofing, covered walkways, restroom fixtures and partitions, interior and exterior finishes, lighting, ventilation, climate control for the new restrooms, accessibl
Type of work: General Construction
Pre-bid meeting: November 3, 2026 at 1:30 PM (Chicago) — Westside Community Hall & Virtual — Meeting ID: 272 609 712 872 853 5 Passcode: BH7BK9GX
Bid opening: November 17, 2026 at 1:30 PM (Chicago) — Microsoft Teams — Meeting ID: 274 403 716 370 418 4 Passcode: x563gb7b
Questions due: November 13, 2026 at 12:00 PM (Chicago)
Questions asked: 4
The project is located within an active public park. The selected contractor shall coordinate construction activities, site access, material deliveries, staging, and temporary closures with the City of Marble Falls Parks and Recreation Department. Contractors are encouraged to familiarize themselves with existing site conditions prior to submitting a bid. All questions regarding the project shall be submitted through CivCast prior to the published question deadline. Responses and any resulting addenda will be distributed through CivCast. Bidders are responsible for reviewing all issued addenda prior to submitting their bids. The City of Marble Falls reserves the right to reject any or all bids and to waive informalities as permitted by applicable law and the solicitation documents.
Construction plans and technical specifications are provided for the Westside Park Restroom Renovation and Expansion project. Bidders are responsible for reviewing the complete construction documents, including all architectural, structural, mechanical, electrical, plumbing, and applicable site plans and specifications. The project includes a deductive alternate as identified in the construction drawings. Bidders shall review and account for the alternate in their bid submissions. All dimensions, existing conditions, and utility locations shall be verified by the contractor prior to construction. Any discrepancies or conflicts within the construction documents shall be submitted for clarification prior to bidding. All official clarifications, revisions, and addenda will be issued through CivCast.
Bid documents (download requires a free CivCast account):
The scope of work includes selective demolition of existing building components; removal and replacement of the existing roof structure; renovation of the existing men's and women's restrooms; construction of additional single-user, family-style restrooms; and associated structural, architectural, mechanical, electrical, plumbing, and site improvements. Improvements include new masonry construction, stone veneer, standing-seam metal roofing, covered walkways, restroom fixtures and partitions, interior and exterior finishes, lighting, ventilation, climate control for the new restrooms.
We post new bathroom opportunities in Texas as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"<p>The bid instructions have been uploaded. </p>""ad9a9909-5ace-4dfa-8882-9782f99d35f2""2026-11-02T18:22:43.679Z"false"<p>The Pre-Bid Meeting and Bid Opening Links have been posted. </p>""af8a1515-9692-41bc-8b18-0b6c05cdba20""2026-10-27T21:21:59.335Z"false"<p>The links for the meetings have by uploaded in the listing. </p>""6b111227-bc6e-4b2e-b814-50b37981d275""2026-10-29T19:03:52.873Z"false"<p>The instructions for bidders have been uploaded to the posting. </p>""7767a61a-9d06-4fe8-87c7-00db99f796f2""2026-11-02T18:23:18.519Z"false"<p>Question Response</p><ol><li><ol><li>Foundation subgrade: Sheet S100 Note SE-4 requires 4'-0" of select fill, while the Holt geotechnical report (File 07-20126) recommends 8". Which governs, and if it’s the geotech report, will a revised S100 sealed by the Structural Engineer be issued by addendum?</li></ol></li></ol><p><strong><u>Response</u></strong>: Revised S100 to reflect the Geotech.</p><p><strong><u>Sheet S100 revised in Addendum 01</u></strong></p><p> </p><ol><li><ol><li>Electrical service: E-102 keyed note 1 calls for a new 120/208V, 400A service, but Panel LA on E601 is 120/240V, 1-phase, 200A. Please confirm the service voltage, phase, and amperage.</li></ol></li></ol><p><strong><u>Response</u></strong>: A new electrical service is required on site to accommodate the restroom building renovations. The site design is not complete. So a new 400 amp service is required for the entire park (under park package) and then a 200 amp service is required for the restroom building (under building package).</p><p><strong><u>Sheets E102 & 102A revised in Addendum 01</u></strong></p><p> </p><ol><li><ol><li>Existing roof structure: Spec 02 41 19 calls for removing the existing roof framing, but D1.1 note 11 and S202 say the structure remains. Is the existing roof framing being fully removed and replaced?</li></ol></li></ol><p><strong><u>Response</u></strong>: Existing roof structure to remain. See revised spec section 02 41 19.</p><p><strong><u>Specification Section 02 41 19 revised in Addendum 01</u></strong></p><p> </p><ol><li><ol><li>Plumbing drawings: Sheets P101, P102, and P201 are titled “Northside Community Park, City of Boerne” and reference existing piping and a floor drain. Do these sheets apply to this project, or will corrected plumbing drawings be issued?</li></ol></li></ol><p><strong><u>Response</u></strong>: Title Block has been revised. See attached.</p><p><strong><u>Sheets P101, 102 & 201 revised in Addendum 01</u></strong></p><p></p><p> </p><ol><li><ol><li>Resinous flooring: Spec 09 67 23 specifies Sherwin-Williams Hybri-Flex EC, while spec 09 91 00 specifies Dur-A-Flex. Which manufacturer is the basis of design?</li></ol></li></ol><p><strong><u>Response</u></strong>: Both refer to the same flooring system. Section 09 67 23 provides more detail information.</p><p><strong><u>No revisions in Addendum 01: Clarification Only</u></strong></p><p> </p><ol><li><ol><li>Metal roof panel: Spec 07 41 10 calls for 0.0159" panels to match the existing seam, while A7.0 calls for MBCI 22 ga BattenLok HS. Which panel gauge and profile governs?</li></ol></li></ol><p><strong><u>Response</u></strong>: MBCI 22ga BattenLok HS is to be used.</p><p><strong><u>Specification Section 07 41 10 revised in Addendum 01</u></strong></p><p> </p><ol><li><ol><li>Ductless split systems: The M6.2 schedule lists Mitsubishi, but the model numbers (KNMAB071A and KUMXA301A) and the M6.1 diagrams are LG. Which manufacturer is the basis of design?</li></ol></li></ol><p><strong><u>Response</u></strong>: LG is the basis of design</p><p><strong><u>Sheet M6.2 revised in Addendum 01</u></strong></p><p> </p><ol><li><ol><li>Deductive alternate: Structural sheets S200A–S202A are labeled “Add Alt. 1,” while the bid form shows a deductive alternate. Please confirm it is a deduct, and whether the bid form’s “Total of All Estimated Prices” line is the Base Bid plus or minus the Deduct. The second line item on the bid form is a <u>deductive</u> alternate. The “Total of All Estimated Prices” line is the Base Bid minus the Deduct.</li></ol></li></ol><p><strong><u>Response</u></strong>: The second line item on the bid form is a <u>deductive</u> alternate. The “Total of All Estimated Prices” line is the Base Bid minus the Deduct.</p><p> </p><ol><li><ol><li>Access control: Hardware sets 1.0–3.0 list card readers and power supplies “by Security Contractor.” Is that contractor hired by the City, with the GC limited to electrified hardware, conduit, and rough-in?</li></ol></li></ol><p><strong><u>Response</u></strong>: Access controls to be installed by city IT contractor. Selected General Contractor is responsible for coordination, conduit, power, wire paths, penetration repair, and the purchase and installation of doors and frames.</p><p><strong><u>Sheet A3.2 revised in Addendum 01</u></strong></p><p></p><p> </p><ol><li><ol><li>Code edition: The mechanical notes on M1.1 and M1.2 reference the 2021 IMC and IECC, while G1.1 lists the 2024 codes. Please confirm the 2024 codes govern.</li></ol></li></ol><p><strong><u>Response</u></strong>: 2024 codes govern</p><p><strong><u>Sheets M1.1 & M1.2 revised in Addendum 01</u></strong></p><p> </p><ol><li><ol><li>Owner and project address: The bid bond lists the Owner at 800 3rd Street, the ITB at 1808 2nd Street, and the bid form gives the project address as 1704 2nd Street. Please confirm the addresses to use on the bid bond. Use the Owner’s address of 1808 2nd Street, Marble Falls, Texas 78654 on the bid bond.</li></ol></li></ol><p><strong><u>Response</u></strong>: Use the Owner’s address of 1808 2nd Street, Marble Falls, Texas 78654 on the bid bond.</p>""da9535c4-63ba-4a53-a543-59e1ac05e338""2026-11-02T17:57:49.112Z"falseRead from this solicitation’s notice text — each row shows the sentence it came from. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: CivCast (project 6adf90090223036d2926afa7), retrieved via CivCast, the bid board Texas civil engineers advertise on. View the official posting, and always confirm requirements and deadlines with the issuing agency.