This is a PRE-SOLICITATION NOTICE for the Webbers Falls Excitation System Replacements in Webbers Falls, Oklahoma. **TH****IS IS NOT A SOLICITATION FOR PROPOSALS AND NO CONTRACT WILL BE AWARDED FROM THIS SYNOPSIS. ** No reimbursement will be made for any costs associated with providing information in response to this pre-solicitation notice or any follow up postings.
The U.S. Army Corps of Engineers – Tulsa has been tasked to solicit for and award a contract for the Webbers Falls Excitation System Replacements, at Webbers Falls, Oklahoma. The proposed design-build project will be procured as an Unrestricted, firm-fixed price contract in accordance with Revolutionary FAR Overhaul (RFO) Part 15, Negotiated Procurement, using the Lowest Price Technically Acceptable approach. Tradeoffs will not be permitted.
Project Description:
This project includes the replacement of the excitation systems (including the Potential Transformers) for all units at Webbers Falls Powerhouse. The installation and commissioning of Unit 1 will be dependent on the availability of the unit, which is currently out of service due to issues with the speed gear. The Contractor will be responsible for designing and manufacturing the new excitation system equipment, delivering to the site, removing the existing equipment, installing the new equipment, and commissioning the new system. They will also perform model validation testing and reporting as listed above. The Hydroelectric Design Center (HDC) will provide submittal reviews, factory visit(s) to witness factory testing, and commissioning support to include determining draft settings for the excitation systems. The government will be responsible for landing all new cable (except for the AC cables from the bus tap to the Potential Transformers and the DC cables from the exciter to the brush rigging) to all external locations within the powerhouse, external to the new exciter and Potential Transformer cubicles.
The estimated magnitude of construction for this project is between $1,000,000 and $5,000,000.
The North American Industry Classification System code for this procurement 237990 (
Other Heavy and Civil Engineering Construction) which has a small business size standard of $45M.
The Product Service Code is: Z2KA (Repair or Alteration of Dams)
Estimated duration of construction of this project is 300 calendar days.
Anticipated solicitation issuance date is on or about 31 August 2026, and the estimated proposal due date will be on or about 01 October 2026.
The work involves replacing the excitation systems, including Potential Transformers, for all units at Webbers Falls Powerhouse. The contractor will design and manufacture the new excitation system equipment, deliver it to the site, remove existing equipment, install the new equipment, and commission the new system, including model validation testing and reporting. The Hydroelectric Design Center will provide submittal reviews, factory visit(s) to witness factory testing, and commissioning support including determining draft settings for the excitation systems. The government will land all new cable to external locations within the powerhouse, except for AC cables from the bus tap to the Potential Transformers and DC cables from the exciter to the brush rigging. Installation and commissioning of Unit 1 is dependent on the unit's availability, currently out of service due to speed gear issues.
We post new electrical opportunities in Oklahoma as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"74137-4290""TULSA""OK""USA""KO CONTRACTING DIVISION""2488 E 81ST STREET"Most Oklahoma work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: SAM.gov (notice 385c98be005c47aaa6977232e4490668), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.