THIS POSTING IS FOR TINKER AFB - MAC BOA HOLDERS ONLY
UPDATE 03 - October 28th, 2026
This Solicitation has been cancelled.
An amendment has been posted to the attachments section to indicate the cancellation.
Thank you to all members who participated in this solicitation.
THIS POSTING IS FOR TINKER AFB - MAC BOA HOLDERS ONLY
UPDATE 02 - May 19th, 2026
The responses to RFI's have been posted.
The name of the document for the RFI responses is "WWYK240015 - RFI RESPONSES"
Proposals are due June 2nd, 2026 @ 1400 (2:00 pm)
Please send proposals to SSgt Isaac Demmers at isaac.demmers@us.af.mil
THIS POSTING IS FOR TINKER AFB - MAC BOA HOLDERS ONLY
UPDATE 01 - April 24th, 2026
The Site Visit Sign In Sheet has been posted and is labeled as: "WWYK240015 - Site Visit Sign In Sheet"
Request for Information (RFI's) are due MAY 1ST, 2026 @ 1300 (1:00pm)
RFI's must be sent to SSgt Isaac Demmers at isaac.demmers@us.af.mil
A DOD SAFE link will be sent out with "specs" and "as-builts" to all Prime Contractors. If you are a Prime Contractor and did not receive a DOD SAFE link, please reach out to SSgt Isaac Demmers at isaac.demmers@us.af.mil
As stated in the Statement of Work: "If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400"
If necessary, additional Specs are available from 72 ABW/CE - Engineering Support, located in B400
THIS POSTING IS FOR TINKER AFB - MAC BOA HOLDERS ONLY
Project Title: WWYK240015 - REHAB TANKS 62501E & 62501W
Project Solicitation Number : FA813726R0020
WWYK240015 - REHAB TANKS 62501E and 62501W - Tanks 62501E and 62501W are located in the Tinker AFB Industrial Waste Treatment Plant. The objective of this project is to replace the cathodic protection system for both tanks, and electrical for the raised platform. Strip and replace interior tanks and the piping to the 4 valves controlling infill and exit protective coating. Clean and recoat the exterior stairs, the raised platform and their structures.
Project specific documents are attached to this posting.
If you experience any difficulty at receiving or accessing the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission sent to your email. In the email, please provide email addresses for Prime Contractors points of contact ONLY, to have a DoD Safe link sent to. Do not include any sub-contractor email addresses.
THIS POSTING IS FOR TINKER AFB - MAC BOA HOLDERS ONLY
After review of the project specific documents, if you are a Tinker AFB - MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit. Your RSVP email must be received within 5 calendar days from the posting of this project. In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access. If anyone requires base access, you must forward with your RSVP, the Entry Access List (EAL) so that we can know how many personnel require base access.
After receipt of your RSVP and EAL if required, Initial Site Visit is set for Friday, 24 April, 2026 at 1000 (10:00 am). The meet up location for the site visit will be held at the parking lot of B62516 (IWTP entrance). Specific directions can be found in the document named: "Att12_240015-Drawings"
You must attend the initial Site Vist for the project, to be considered eligible to propose.
Please submit your RSVP to SSgt Isaac Demmers at "isaac.demmers@us.af.mil".
THIS POSTING IS FOR TINKER AFB - MAC BOA HOLDERS ONLY
The work consists of furnishing all materials, labor, plant, tools, transportation, equipment, testing services, quality control and incidentals required to replace the tanks' internal coatings, repair or replace the cathodic protection system, repair secondary containment seals, remove and properly dispose of construction waste material stored in the secondary containment, replace electrical for the raised platform, and clean and recoat exterior stairs, the raised platform and their structures. The work is phased so that only one tank is down at a time.
We post new concrete opportunities in Oklahoma as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"73145-9125""TINKER AFB""OK""USA""CP 405 739 4040""7858 5TH ST STE 1""Solicitation Amendment FA813726R00200001 SF 30.pdf"394885"file"".pdf""1""2026-10-29T13:27:52.889+00:00""d1236fced3114faeb0987a5d2452f61c""public""0""public""1936d582ea9140a29760a38f25138423""0"9"0""Solicitation Amendment - FA813726R00200001.pdf"720047"file"".pdf""1""2026-10-29T13:27:52.889+00:00""cc5058e936a64ccca587f0da05abaaf4""public""0""public""4ee2ddac115a4cf2969fb4f4d262dccc""0"8"0""WWYK240015 - RFI RESPONSES.pdf"431963"file"".pdf""1""2026-05-19T19:44:46.662+00:00""290661597cea483ba19e41a2498fc4ab""public""0""public""4b45d31b8427497d84b767ef9229c57f""0"7"0""WWYK240015 - Site Visit Sign In Sheet.jpg"86873"file"".jpg""1""2026-04-24T19:15:57.754+00:00""c46b3d85b19c44c4b4ed162c389a7f1a""public""0""public""aed5eea8f4b54f8684b22b54e56de208""0"6"0""Solicitation - FA813726R0020.pdf"716309"file"".pdf""1""2026-04-17T19:35:41.681+00:00""0c946dbb45764bc2810899b505c07511""public""0""public""f291f58368544674b405ba693553949f""0"5"0""Wage Determination - 1 Jan 26.pdf"175803"file"".pdf""1""2026-04-17T19:35:41.681+00:00""965dc458666343f79e95b83a9702a3f6""public""0""public""9aa6bed6c0454c77ac7421c4314fa62a""0"4"0""Att12_240015-Drawings.pdf"21461796"file"".pdf""1""2026-04-17T19:35:41.681+00:00""97a1a3f919b544ab84149db37b4fe45e""public""0""public""1025d23d887e4d5f908ca031d14ba0a6""0"3"0""Att10_240015_Statement of Work.final.pdf"293894"file"".pdf""1""2026-04-17T19:35:41.681+00:00""632501ac5dd0453eb50f37149567c5d8""public""0""public""583e934cb79f405ca4a0bf954b9b3f1c""0"2"0""Att11_240015_Submittal Register.pdf"189894"file"".pdf""1""2026-04-17T19:35:41.681+00:00""21454d13a33a44569fc84538674963aa""public""0""public""fec33ee7cb9e4ad08c5cdfe57f1d3c8a""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: SAM.gov (notice cddfc7acea544787b6b45049047bfc23), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.