Update 10/8/2026: QA_10.8.2026.pdf posted to attachments.
Invitation for Bids (IFB) for construction project OR FLAP DOT CRGNSA 100(7), Historic Columbia River Highway State Trail, Mitchell Point Dr. to Ruthton Trailhead
The Invitation for Bids (IFB), Plans, Physical Data, and the Construction Contract Administration Document per FAR 36.211 are posted under attachments.
The work includes mobilization, construction survey and staking, contractor quality control and testing, soil erosion control, clearing and grubbing, removal of existing structures, roadway excavation, subexcavation, topsoil conservation, placement of geotextiles, foundation fill, riprap, roadway aggregate, asphalt concrete pavement (including temporary I-84 and TPAR sections), fog seal, tack coat, asphalt pavement milling, structural concrete, temporary support structures, concrete structure coating, precast structural concrete, pipe culverts, slotted drain pipe, large precast concrete arch culvert, manholes, inlets, underdrain systems, concrete curbs, detectable warning panels, guardrail systems (MGS), terminal systems, structure transition railing, concrete barrier, fence, bollards, stone masonry, markers, dump truck and excavator rental, manufactured topsoil placement, seeding, mulching, rolled erosion control product, sign systems, delineators, rumble strips, pavement markings, temporary traffic control devices (barricades, drums, portable changeable message signs, crash cushions, traffic signal system, portable traffic barrier), field office, fixtures, pedestrian railing, and stormwater management dry swale.
We post new general contractors opportunities in Oregon as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""US""98661""VANCOUVER""WA""USA""DOT FEDERAL HIGHWAY ADMIN""610 E FIFTH STREET""QA_10.8.2026.pdf"189535"file"".pdf""1""2026-10-08T17:02:26.961+00:00""094e4606bdbe4c0a8753e08fb6fbbfb1""public""0""public""6ae5b7e62359425385170d96b222e40a""0"30"0""IFB_69056726B000009_OR FLAP DOT CRGNSA 100(7).pdf"70017404"file"".pdf""1""2026-09-18T22:07:04.17+00:00""ee286ecc33b644c49fafb0ad8ac032fd""public""0""public""e88478bb5ee145e686bacc0f94d0023f""0"29"0""ora-dot-crgnsa100-7_plans.pdf"58178285"file"".pdf""1""2026-09-18T22:07:04.17+00:00""230e9cb521354098a94c25083fbd01f8""public""0""public""e51eba17986c48b3837b27a35efc085f""0"28"0""Physical Data.zip"71437215"file"".zip""1""2026-09-18T22:07:04.17+00:00""f40236399fc5428b938232c9681e33f6""public""0""public""126f3fb68c504eccb67232290bcdd139""0"27"0""WFLHD Construction Contract Administration_FY 23 V2.pdf"165441"file"".pdf""1""2026-09-18T22:07:04.17+00:00""4bd09e7234ef4aaab728c28883d37edd""public""0""public""2ac955505bd643bbbd43ad5c6e41fdb8""0"1"0""https://meet.google.com/wjh-bopr-vcg?authuser=0&hs=122""Link to Bid Opening"0"link""1""2026-09-18T22:07:04.17+00:00""08fb243e923f48e79c33b9d4d4e2a2f5""public""0""Link to Bid Opening""public""8037475f25934ca68fce00609289da30""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.