Contract Number: C03156
Contract Name: NORTHFIELD-WILLIAMSTOWN STP SURF(76) & RANDOLPH STP
SURF(78)
VERMONT
AGENCY OF TRANSPORTATION
PROPOSAL
STANDARD SPECIFICATIONS FOR CONSTRUCTION
DATED 2024 SHALL APPLY TO THIS CONTRACT
SPECIAL PROVISIONS
SCHEDULE OF ITEMS
ELECTRONIC BID BOND to be submitted in the amount of 5% of the Contractor's bid.
BIDDING PROCEDURE
Bid Proposals will not be read unless accompanied by an electronic bid bond, and they may be rejected as
irregular if they are not in compliance with Agency specifications.
NOTE: All bid proposals shall be properly filled out and submitted electronically utilizing iCX Web
System services.
VTrans Mission and Vision
Through excellent customer service, provide for the safe and efficient movement of people and goods.
A safe, reliable, and multimodal transportation system that grows the economy, is affordable to use and
operate, and serves vulnerable populations.
Cover Page Proposal ____________________________________________________________ 1
Table of Contents _______________________________________________________________ 2
Project Special Provisions ________________________________________________________ 3
406-0004 BITUMINOUS CONCRETE PAVEMENT, THIN OVERLAY ___________________14
Required Contract Provisions for Federal Aid Construction Contracts FHWA 1273 June 2026 __ 30
USDOL Davis Bacon Wage Rates 2026 - Orange County _______________________________ 42
USDOL Davis Bacon Wage Rates 2026 - Washington County ____________________________ 46
Bidding Requirements and Conditions ______________________________________________ 50
DBE Policy Required Contract Requirements CR110 - 2026 _____________________________ 62
Attachment C - Standard State Contract and Grant Provisions Rev 2-13-26 _________________ 67
USDOT Standard Title VI Nondiscrim Assurances Appendix A and E _____________________ 77
Standard Federal EEO Construction Contract Specifications _____________________________ 80
Contractor EEO Certification Form - CA109 _________________________________________ 87
Vermont AOT Certificate of Compliance - CA271 _____________________________________ 88
Vermont AOT Minimum Labor and Truck Rates - CA101 _______________________________ 92
Commodity Index Prices CA170 - Spec Book 2024 ____________________________________ 93
Proposal Schedule of Pay Items ____________________________________________________ 94
Northfield-Williamstown STP SURF(76) & Randolph STP SURF(78) Advertised October 14, 2026
PIN Number(s): 21v228 & 21v219 Page 1
Special Provisions – Notices to Bidders
SPECIAL PROVISIONS
1. NOTICE TO BIDDERS – CONTRACT COMPLETION DATE. This Contract shall be completed
on or before October 15, 2027.
2. NOTICE TO BIDDERS – PROHIBITION OF RUSSIAN GOODS. The Contractor is hereby
notified that, pursuant to Vermont Executive Order No. 02-22, dated March 3rd, 2022, the
purchase of Russian-sourced goods and goods produced by Russian entities (defined as institutions
or companies that are headquartered in Russia or have their principal place of business in Russia)
is prohibited. The awarded Contractor must fill out and sign the Executive Order 02-22 Vendor
Certification as part of Contract awarding process.
3. NOTICE TO BIDDERS – WORK REQUIREMENTS. The Contractor is hereby notified that no
work shall be performed from mile marker (MM) 1.900 to mile marker (MM) 3.350 on VT Route
66 within the Town of Randolph between the hours of 7:15 a.m. to 8:15 a.m. and from 4:15 p.m.
to 5:15 p.m.
4. NOTICE TO BIDDERS – ELECTRONIC DOCUMENT MANAGEMENT. The Contractor is
hereby notified that the Contractor, their subcontractors, and suppliers shall create both a Doc
Express and an iCXWeb account. The Contractor shall use these applications for collection and
management of electronic documents. Doc Express can be accessed at the following link:
https://docexpress.com. iCXWeb can be accessed at the following link:
vtrans.exevision.com/icx/Index.aspx.
All costs associated with the use of Doc Express and iCXWeb will be considered incidental to
Item 635.1100, Mobilization/Demobilization. The State will manage the applications including
Contract setup upon Contract execution.
To create an account and for more information regarding the use of Doc Express see the
information at the following link:
https://outside.vermont.gov/agency/vtrans/external/docs/construction/Contracting/DocExpressOv
erviewforContractors.docx.
To create an account and for more information regarding the use of iCXWeb see the information
at the following link: https://vtrans.vermont.gov/icx.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 2
5. NOTICE TO BIDDERS – ELECTRONIC TICKETING VTRANS PORTAL. The Contractor
is hereby notified that the Contractor, their subcontractors, and suppliers shall connect to the
VTrans Portal and use the application for distribution and management of electronic tickets (e-
tickets). VTrans Portal is a state cloud-based e-ticket database, including a web-based user
interface and a jobsite mobile e-ticket application. VTrans Portal will interface with the
Contractor’s supplier existing point of sales or e-ticketing platform and will allow VTrans to
manage bituminous material e-tickets.
All costs associated with the use of VTrans Portal will be considered incidental to the appropriate
Section 406 and Section 407 pay items. The Agency will manage the VTrans Portal application
including Contract setup upon Contract execution.
To create an account, connect to the VTrans Portal, and for more information regarding the use of
VTrans Portal see the information at the following link: https://www.haulhub.com/vermont-
agency-transport-22/
6. NOTICE TO BIDDERS – CONTACT WITH THE AGENCY. From the time of advertising until
the actual bid opening for this Contract, all prospective Contractors, subcontractors, and suppliers
shall direct all inquiries related to this Contract solely to the Agency's Contract Administration
Section at AOT.ConstructionContractingInquiry@vermont.gov.
The deadline for submitting inquiries related to this Contract is 4:30 p.m. Eastern Time on October
28, 2026. Inquiries received prior to this time will receive a response from the Agency. Inquiries
received after this time may receive a response at the Agency’s discretion.
7. NOTICE TO BIDDERS – OTHER SPECIFICATIONS AND CONTRACT REQUIREMENTS.
FHWA 1273 – Required Contract Provisions for Federal Aid Construction Contracts
USDOL Davis Bacon Wage Rates by County
Vermont Agency of Transportation Bidding Requirements and Conditions
Disadvantaged Business Enterprise (DBE) Policy Contract Requirements - CR-110
Attachment C - Standard State Provisions for Contracts and Grants
USDOT Standard Title VI Nondiscrimination Assurances Appendices A, E
Standard Federal Equal Employee Opportunity (EEO) Construction Contract Specifications CA26
Contractor Equal Employment Opportunity (EEO) Certification Form – CA109
Vermont Agency of Transportation Certificate of Compliance – CA271
Vermont Agency of Transportation Minimum Labor and Truck Rates – CA101
Commodity Index Prices – CA170
Schedule of Pay Items
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 3
8. NOTICE TO BIDDERS – NEW PREQUALIFICATION FORM. The Contractor is hereby
notified that the Agency is required by the U.S. Department of Transportation to develop and
maintain a list of information about all firms that bid on federally funded Contracts in accordance
with 49 C.F.R. § 26.11. The Agency has developed a new electronic form to collect this
information. The Contractor shall fill out this form as part of their project-specific prequalification
for every Contract that they bid on. A link to this form is provided in the prequalification form
available through iCX and the Agency’s website.
9. NOTICE TO BIDDERS – DAVIS-BACON. U.S. Department of Labor Davis-Bacon wage rates
are applicable to this Contract. Copies of the applicable rates are included in this proposal.
10. NOTICE TO BIDDERS – GENERAL SPECIAL PROVISIONS. The Contractor is hereby
notified that the most recent General Special Provisions in effect on the date of advertisement shall
apply to this Contract. The General Special Provisions may be found at the following address:
https://vtrans.vermont.gov/highway/construct-material/construct-services/pre-
contractspecifications/vermont/2024
11. NOTICE TO BIDDERS – STANDARD DRAWINGS. The Vermont Agency of Transportation
Standard Drawings listed on the Index of Sheets are not included in the plan set, but may be found
at the following address:
https://resources.vtrans.vermont.gov/resources/cadd/VAOTconSTD_Name.xml?_gl=1*6cpy62*
_ga*MTU5MTQ3NTcyNi4xNzIwMjM5NjI0*_ga_V9WQH77KLW*czE3NTI3NTYyMzQkbzE
3NCRnMSR0MTc1Mjc1NjkwMyRqNjAkbDAkaDA.
12. NOTICE TO BIDDERS – INFORMATIONAL DOCUMENTS. The Contractor is hereby notified
that the following informational documents for this Contract are available on iCXWeb and the
VTrans Bid Opportunities website. These documents are being provided during the bid solicitation
period for informational purposes only.
(a) Traffic Management Plan (TMP) Checklist – Northfield-Williamstown STP SURF(76)
(b) Traffic Management Plan (TMP) Checklist – Randolph STP SURF(78)
13. NOTICE TO BIDDERS – SURFACE WATER WITHDRAWAL. The Contractor is hereby
notified that the Vermont state law, Act 135 of 2022, requires any person withdrawing surface
water (as defined in 10 V.S.A. § 1002 (20)) to register with and report the water withdrawal and
usage to the Vermont Department of Environmental Conservation beginning January 1, 2023.
Guidance can be found here: https://dec.vermont.gov/watershed/rivers/streamflow-protection/act-
135-surface-water-withdrawal-registration-and-reporting
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 4
14. NOTICE TO BIDDERS – ENVIRONMENTAL COMMITMENTS.
(a) Threatened, Endangered, and Rare Species. The Contractor shall ensure all personnel
working on the project site are made aware of the potential presence and protected status
of the northern long-eared bat and the tricolored bat. No suitable bat habitat is present
within the project limits and no Time-of-Year (TOY) restrictions are required.
The Contractor is hereby made aware of the potential for TOY restrictions related to
proposed Waste, Borrow and Staging areas. Cutting trees >3 inches in diameter outside
of the contract project limits shall require review under Section 105.25 Opening Off-Site
Activity Areas.
(b) Invasive Material. If invasive species are delineated on the Plans or found in the project
area and confirmed by the Engineer, the invasive species, and any soil excavated from
areas that contained the invasive species, will be termed invasive material.
The Contractor shall handle the invasive material in accordance with the VTrans State
Highway System Roadside Terrestrial Invasive Plants Best Management Practices
(BMPs). The Contractor shall stockpile the invasive material separately from other soil
stockpile areas. A ground barrier and perimeter containment system shall be in place
around the area intended for stockpiling the invasive material. Equipment shall be cleaned
of all soil and plant matter prior to arriving on site in accordance with Subsection 107.06.
The equipment used for excavation and transport of invasive material shall be cleaned of
all soil and plant matter before being used for work in other areas in accordance with the
BMPs.
To the extent possible, invasive material shall be reused on site. Invasive material shall
only be reused on site in areas where the presence of the invasive species were clearly
evident. If there is an excess of invasive material, it shall be wasted in accordance with the
BMPs.
The cost of excavating invasive material will be paid for under the appropriate Contract
excavation items. When invasive species are delineated on the Plans, the additional cost
for handling invasive material, following the BMPs, cleaning equipment, and wasting
excess invasive material will be incidental to all other Contract items. When invasive
species are not delineated on the Plans, and compensation is not otherwise provided for in
the Contract, the work of handling invasive material, following the BMPs, cleaning
equipment, and wasting excess invasive material will be considered extra work in
accordance with Subsection 104.03 and will be paid for in accordance with Subsection
109.06.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 5
15. NOTICE TO BIDDERS – UTILITIES – NORTHFIELD-WILLIAMSTOWN STP SURF(76).
Existing aerial facilities owned by Washington Electric Cooperative, Consolidated
Communications, and TDS Telecom will not require adjustment. The Contractor is cautioned to
protect these facilities from damage.
Existing underground facilities owned by Washington Electric Cooperative and Consolidated
Communications will not require adjustment. The Contractor is cautioned to protect these facilities
from damage.
Contacts for the above listed companies are as follows:
Washington Electric Co-op Brian Wilkin (802) 224-2319
Consolidated Communications Travis Andrews (802) 735-4874
TDS Telecom Aaron Diers (603) 848-7822
Employees or agents of the companies are to be allowed free and full access within the project
limits with the tools, materials, and equipment necessary to install, operate, maintain, place,
replace, relocate, and remove their facilities.
There will be no extra compensation paid to the Contractor for any inconvenience caused by
working around and with the companies, or their facilities. Should the Contractor desire additional
adjustments of the utility facilities for his/her convenience, proper arrangements shall be made in
conformance with Subsection 105.09.
There are areas of underground utilities that may require additional locating beyond normal Dig
Safe measures. The Contractor is advised that exploratory excavation to locate existing
underground facilities may be necessary to protect these facilities from damage. Where approved
by the Engineer, these utilities shall be located and/or exposed by methods such as air/vacuum
excavation and/or hand digging to determine their exact location. This exploratory work shall be
classified as Trench Excavation of Earth, Exploratory and payment shall be through Pay Item
204.2200, Trench Excavation of Earth, Exploratory (N.A.B.I.).
The Contractor shall notify aerial utility pole owner if excavation will be within 10 feet of an
existing pole or anchor. That pole owner may choose to be onsite for this activity. There will be
no excavation allowed within 5 feet of existing poles and anchoring.
Vermont Statutes Annotated, Title 30, Chapter 86 (“Dig Safe”) requires notice to Dig Safe before
starting excavation activities. The Contractor must telephone Dig Safe at 811 at least 72 hours
(excluding Saturdays, Sundays and legal holidays) before, but not more than 30 days before,
starting excavation activities at any location. In addition, before excavation and/or pavement
grinding in or on the state highway right-of-way, the Contractor must contact the Agency’s Traffic
Signal Superintendent, Dan Ertel, to obtain/verify the location of Agency’s underground utility
facilities or to confirm the absence of such facilities. Dan can be reached at (802) 343-2188.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 6
The Contractor is advised that many towns are not members of Dig Safe. It is the Contractor’s
responsibility to check with towns prior to excavation and shall protect and restore utilities
damaged within the project and as set forth in Subsection 107.12.
All Contractors, subcontractors or material suppliers involved in any project-related activity shall
comply with all applicable codes and regulations related to working around live electrical lines;
including, but not limited to maintaining the required minimum clear distance from an electrical
utility facility. The Contractor’s Competent Safety Officer shall be well versed in OSHA and
VOSHA regulations, and shall be capable of implementing a plan to conform to these regulations
during prosecution of work.
16. NOTICE TO BIDDERS – UTILITIES – RANDOLPH STP SURF(78). Existing aerial facilities
owned by Green Mountain Power Corporation, Comcast Communication, FirstLight Fiber, and
Consolidated Communications will not require adjustment. The Contractor is cautioned to protect
these facilities from damage.
Existing underground facilities owned by the Town of Randolph, Green Mountain Power
Corporation, Comcast Communication, and Consolidated Communications will not require
adjustment. The Contractor is cautioned to protect these facilities from damage.
It is not anticipated that rim adjustments will need to be made to the sewer manholes or the water
valves owned by the Town of Randolph.
Contacts for the above listed companies are as follows:
Green Mountain Power Corp Ian Treadway (802) 353-5079
Consolidated Communications Tucker Peterson (802) 735-7550
FirstLight Fiber Bill Gray (802) 373-4319
Comcast Communications Bruce Bowser (802) 316-9324
Town of Randolph Christopher Chambers (802) 728-9079
Employees or agents of the companies are to be allowed free and full access within the project
limits with the tools, materials, and equipment necessary to install, operate, maintain, place,
replace, relocate, and remove their facilities.
There will be no extra compensation paid to the Contractor for any inconvenience caused by
working around and with the companies, or their facilities. Should the Contractor desire additional
adjustments of the utility facilities for his/her convenience, proper arrangements shall be made in
conformance with Subsection 105.09.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 7
There are areas of underground utilities that may require additional locating beyond normal Dig
Safe measures. The Contractor is advised that exploratory excavation to locate existing
underground facilities may be necessary to protect these facilities from damage. Where approved
by the Engineer, these utilities shall be located and/or exposed by methods such as air/vacuum
excavation and/or hand digging to determine their exact location. This exploratory work shall be
classified as Trench Excavation of Earth, Exploratory and payment shall be through Pay Item
204.2200, Trench Excavation of Earth, Exploratory (N.A.B.I.).
The Contractor shall notify aerial utility pole owner if excavation will be within 10 feet of an
existing pole or anchor. That pole owner may choose to be onsite for this activity. There will be
no excavation allowed within 5 feet of existing poles and anchoring.
Vermont Statutes Annotated, Title 30, Chapter 86 (“Dig Safe”) requires notice to Dig Safe before
starting excavation activities. The Contractor must telephone Dig Safe at 811 at least 72 hours
(excluding Saturdays, Sundays and legal holidays) before, but not more than 30 days before,
starting excavation activities at any location. In addition, before excavation and/or pavement
grinding in or on the state highway right-of-way, the Contractor must contact the Agency’s Traffic
Signal Superintendent, Dan Ertel, to obtain/verify the location of Agency’s underground utility
facilities or to confirm the absence of such facilities. Dan can be reached at (802) 343-2188.
The Contractor is advised that many towns are not members of Dig Safe. It is the Contractor’s
responsibility to check with towns prior to excavation and shall protect and restore utilities
damaged within the project and as set forth in Subsection 107.12.
All Contractors, subcontractors or material suppliers involved in any project-related activity shall
comply with all applicable codes and regulations related to working around live electrical lines;
including, but not limited to maintaining the required minimum clear distance from an electrical
utility facility. The Contractor’s Competent Safety Officer shall be well versed in OSHA and
VOSHA regulations, and shall be capable of implementing a plan to conform to these regulations
during prosecution of work.
17. NOTICE TO BIDDERS – CONCURRENT CONSTRUCTION. The Contractor is made aware of
the following VTrans construction project(s) which are expected to be in progress within the area
of this project during its construction.
TABLE 1 – CONCURRENT CONSTRUCTION PROJECTS
Project Contractor Anticipated Contract
Completion Date
Randolph STP PC26(3) Pending Fall 2027
This list is not all-inclusive and it is possible there may be other VTrans, municipal, or private
construction projects within the area of this project during its construction.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 8
The Contractor shall coordinate construction schedules and traffic control with the work required
for these projects.
There will be no extra compensation paid to the Contractor for any inconvenience caused by
working around these or other projects.
18. NOTICE TO BIDDERS – SALVAGED MATERIALS. The Contractor is hereby notified that 500
tons of bituminous millings shall remain the property of the State.
All costs for loading and delivering these salvaged materials will be incidental to Contract Item
210.1200 Fine-Milling, Bituminous Pavement. The Contractor shall load 500 tons of bituminous
millings on to suitable transport and deliver to the I-89 NB closed Rest Area MM 34.3 Randolph,
VT 05060.
The Contractor shall contact Shannon Gilbert, District 4 General Manager, Tel.:(802)338-5083 a
minimum of two (2) weeks prior to beginning delivery to the designated location.
19. NOTICE TO BIDDERS – SPECIAL CONSTRUCTION REQUIREMENTS.
(a) The Contractor shall maintain a safe access to all ramps and U-turns at all times during the
construction of this project.
(b) During construction it will be necessary for the Contractor to maintain one-lane traffic for
extended periods of time. In no case shall the paved width for this one-lane traffic,
including shoulders, be reduced to less than 12 feet. This paved width shall remain free of
obstructions and obstacles at all times.
(c) The Contractor shall position Portable Changeable Message Signs at locations determined
by the Engineer properly warning motorists of the roadway conditions ahead. As directed
by the Engineer, these locations may change during construction as needs arise based on
daily work activities. The message to be displayed shall be submitted to the Engineer in
advance for approval. The displayed message should accurately reflect what motorists can
expect to encounter through the project area. The cost of providing the Portable Changeable
Message Signs shall be paid for under Contract item 641.1500 or 641.1700. The Contractor
shall also install and maintain appropriate construction signing warning the traveling public
of the expected roadway surface conditions.
(d) Prior to final acceptance of the project, all drop inlets and bridge joints within the project
limits shall be cleaned and all material within the drop inlets and bridge joints shall be
removed. All paved areas adjacent to curbs shall be swept and cleaned of all extraneous
material. Costs for this work will not be paid for directly, but will be considered incidental
to all Contract items.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 9
(e) There are special events throughout the year that may require close communication and
coordination between the Contractor and the municipality to reduce conflicts. The
municipality will advise the Engineer and Contractor of the specifics of each event and the
Engineer will direct the Contractor as to what actions, if any, will be necessary on the
Contractor’s part to minimize impacts to the event. Special events that may conflict with
Contractor operations are not limited to those which may be listed in this Notice to Bidders.
There will be no extra compensation paid to the Contractor for any inconvenience caused
by working around any listed or unlisted special events.
For more information about area special events, contact the following:
Northfield: Mary Smith
Town Manager
51 S. Main Street
Northfield, VT 05663
jschulz@northfield.vt.us
802-485-9822
Williamstown: Ryan Lockwood
Town Manager
2470 VT Route 14
Williamstown, VT 05679
twnmgr@williamstown.org
802-433-6671
Randolph: Tom Yennerell
Town Manager
7 Summer Street
Randolph, VT 05060
trevor@randolphvt.org
802-728-5818
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 10
TABLE 1 – SCHEDULE OF KNOWN EVENTS
Event Date
New World Festival Randolph August/September
2027
Norwich University Home Coming Weekend September 2027
Vermont State University – Randolph Campus
Commencement May 2027
Norwich University Commencement May 2027
20. NOTICE TO BIDDERS – AFAD. The Contractor is hereby notified that Automated Flagger
Assistance Devices (AFADs) are remotely operated devices that enable a certified flagger to be
positioned out of the lane of traffic and are used to control motorists through work zones.
AFADs shall only be used in situations where there is no more than one lane of approaching traffic
that needs to be controlled. Additionally, since AFADs are not traffic control signals, they shall
not be used to replace traffic signals or other continuously operating traffic control devices.
These devices may be used as a safety enhancement to flaggers on an hour-for-hour basis. AFADs
shall meet the following requirements:
(a) All AFAD applications shall meet the requirements of the applicable sections of the current
edition of the Manual on Uniform Traffic Control Devices (MUTCD).
(b) All AFAD applications shall be in accordance with NCHRP Report 350 or the MASH for
the applicable test level and device weight. Documentation of the crashworthiness of the
device shall be submitted to the Engineer for approval prior to use on the project.
(c) AFAD applications shall always be controlled by a flagger who has been trained in the
operation of the AFAD and who meets the requirements of Section 630. The flagger shall
not flag traffic and operate an AFAD at the same time.
(d) Should an AFAD malfunction or otherwise not function as intended they shall be replaced
by another AFAD or flagger(s) or work shall cease and the roadway shall be opened to
unrestricted traffic flow immediately.
(e) Each AFAD will be considered equivalent to one flagger and will be measured and paid
for on an hourly basis under Item 630.1500 Flaggers. One hour of AFAD use shall be paid
for as one hour of flagging.
Northfield-Williamstown STP SURF(76) Advertised October 14, 2026
& Randolph STP SURF(78) Page 11
(f) Flaggers will only be measured for payment when actually performing flagging duties.
Flaggers controlling AFADs but not actually flagging will not be measured for payment,
but will be considered incidental to the Contract lump sum price for Item 641.1000 Traffic
Control, or Item 641.1100 Traffic Control, All-Inclusive, as applicable.
(g) The use of AFADs may be suspended at the discretion of the Engineer.
21. NOTICE TO BIDDERS – FUEL PRICE ADJUSTMENT. In addition to the items specified in
Section 690, the Special Specification items listed in Table 1 will also be eligible for Fuel Price
Adjustment under Section 690.
TABLE 1 – SPECIAL SPECIFICATION ITEMS SUBJECT TO FUEL PRICE ADJUSTMENT
Special Specification Pay Items Subject to Adjustment: Using the Tabulated Fuel Usage
Factor and Threshold Quantity for:
Item No. Item Name Work Category
406.0410002 Bituminous Concrete Pavement, Thin Overlay Bituminous Concrete Pavement
22. NOTICE TO BIDDERS – SUBSECTION 101.02. Subsection 101.02 is hereby modified
by revising the definition of “Contract” to add the phrase “General Special Provisions”
immediately following the phrase “Standard Specifications”.
23. NOTICE TO BIDDERS – SUBSECTION 716.02. Subsection 716.02(a) is hereby modified by
deleting the fifth paragraph in its entirety and replacing it with the following:
Mix designs shall include an ignition oven asphalt binder correction factor, determined in
accordance with AASHTO T 308, for the oven used in quality control testing. Upon Agency
request, at the time that the mix design is submitted, the Contractor shall provide sufficient
aggregate and asphalt binder to allow the Agency to determine an ignition oven asphalt
binder correction factor.
24. NOTICE TO BIDDERS – SUBSECTION 728.02. When material is supplied in accordance with
Subsection 728.02(b) or Subsection 728.02(e), material in accordance with AASHTO M 180-18
or AASHTO M 180-23 may be substituted in place of material meeting AASHTO M 180-25.
Special Provisions Part II – Special Specifications
SECTION 406-0004 – BITUMINOUS CONCRETE PAVEMENT, THIN OVERLAY
406-0004.01 DESCRIPTION. This work shall consist of constructing a thin overlay (TO) bituminous
concrete pavement on a prepared foundation in accordance with these specifications and in conformance
with the lines, grades, thicknesses, and typical cross-sections shown on the Plans or established by the
Engineer.
406-0004.02 MATERIALS. Materials shall meet the requirements of the following subsections:
Performance-Graded Asphalt Binder .........................................................................702.01
Warm-Mix Asphalt Technologies..............................................................................702.03
Anti-Strip Additives ...................................................................................................702.04
Aggregate for Bituminous Concrete Mixtures ...........................................................704.10
Recycled Asphalt Pavement ......................................................................................704.22(a)
General Bituminous Concrete Mixture Design Requirements ..................................716.02(a)
Bituminous Mixing Plant and Laboratory .................................................................716.03
Preparing and Mixing Bituminous Concrete Mixtures ..............................................716.04
(a) Performance-Graded Asphalt Binder. Performance-graded asphalt binder shall meet the
requirements of Subsection 702.01(d) for PG 58E-34, unless otherwise specified on the Plans.
(b) Additives. Anti-strip additives shall be used in thin overlay mixtures and shall be dosed to abate
stripping in accordance with Subsection 702.04. In addition, the anti-strip additive shall be capable
of reducing the compaction temperature, or a separate warm-mix asphalt (WMA) technology
meeting the requirements of Subsection 702.03 shall be included.
(c) Thin Overlay Mixtures. Thin overlay mixtures shall meet the following requirements:
(1) Design Ranges and Values. The gradation of the coarse aggregate, fine aggregate, and
recycled asphalt materials (if used) shall be such that, when combined, the composite
aggregate will meet the gradation requirements of Table 406-0004.02A. The process of
blending the coarse aggregate, fine aggregate, and recycled asphalt materials (if used) shall
be accomplished using separate bins. Blending in the stockpile will not be permitted.
The JMF target value for each sieve shall be within the ranges specified in Table 406-
0004.02A, and the JMF target value for other mixture properties shall meet the
requirements specified in Table 406-0004.02B.
Special Provisions Part II – Special Specifications
TABLE 406-0004.02A – GRADATION DESIGN RANGES
Sieve Designation
Percentage by Mass (Weight)
Passing Square Mesh Sieves
(Minimum – Maximum)
1/2 inch (12.5 mm) 100
3/8 inch (9.5 mm) 95 – 100
No. 4 (4.75 mm) 60 – 95
No. 8 (2.36 mm) 47 – 65
No. 16 (1.18 mm) --
No. 30 (0.600 mm) --
No. 50 (0.300 mm) --
No. 100 (0.150 mm) --
No. 200 (0.075 mm) 2 – 7
TABLE 406-0004.02B – OTHER MIXTURE PROPERTY DESIGN RANGES AND VALUES
Property Value or Requirement
Nominal maximum aggregate sieve size 3/8 inch (9.50 mm)
Percent Gmm at Nmax 99% max.
Design gyrations (Ndesign) 50
Voids in mineral aggregate 16.0% min.
Air voids 3.50%
Dust proportion (dry sieve) 0.50 – 1.00
Hamburg wheel tracker test (HWTT),
average rut depth 1 Report
HWTT, stripping inflection point (SIP) 1 Report
1 Specimen fabrication, conditioning, and procedures shall be in
accordance with the Agency’s Bituminous Concrete Quality
Manual.
(2) Use of Recycled Asphalt Materials. The Contractor may choose to use recycled asphalt
pavement (RAP) in thin lift bituminous concrete pavement mixtures. The amount of RAP
used shall not exceed 20% of the total weight of aggregate in the mixture, including the
RAP.
The use of recycled asphalt shingles (RAS) is prohibited.
Special Provisions Part II – Special Specifications
a. When any amount of RAP is used, an analysis of the RAP material, including the
extracted aggregate gradation, coarse aggregate specific gravity, fine aggregate
specific gravity, and asphalt content shall be provided in the mix design.
b. Any change in the amount or combination of recycled materials shall require a new
mix design unless otherwise approved by the Agency.
c. Should the characteristics of any proposed recycled material be such that an
acceptable mixture cannot be produced or maintained, the recycled material will
not be allowed for use on the Contract.
(3) Thin Overlay Mixture Design Process. AASHTO R 35 will be the method used to develop
a mix that will meet the specified design criteria in accordance with AASHTO M 323, unless
otherwise noted.
The mixture shall be designed using the following methodology:
a. Select materials (aggregate, asphalt binder, additives).
b. Select design aggregate structure.
c. Select design asphalt binder content.
d. Select additives content.
e. Evaluate mixture moisture sensitivity and rutting susceptibility using the Hamburg
wheel tracker test (HWTT).
f. Determine mixture cracking tolerance index (CT-Index) using the indirect tensile
cracking test.
g. Evaluate the anti-strip additive and mixture compatibility using ASTM D3625.
(4) Thin Overlay Job Mix Formula. The JMF for each mixture shall contain all of the following
information:
a. A single percentage of aggregate passing each sieve identified in Table 406-
0004.02A.
b. When applicable, a single percentage of RAP in the mixture.
c. A single percentage of asphalt binder to be added to the aggregate.
Special Provisions Part II – Special Specifications
d. A single percentage for every additive in the mixture. Each additive shall be
identified by name and purpose (e.g. anti-strip, WMA technology).
e. A single percentage for air voids.
f. A single percentage for voids in mineral aggregate.
g. The values of Ninitial, Ndesign, and Nmax.
h. The mixing temperature.
i. The design compaction temperature.
(5) Control Limits. Each mix design shall establish an upper and lower control limit (as
applicable) for every JMF parameter to determine when action should be taken or production
should be suspended.
406-0004.03 AGENCY MATERIAL EVALUATION. Thin overlay mixtures will be sampled and tested
on a statistically random basis for evaluation in accordance with the specified requirements and the
material quality will be evaluated based on the results of these tests to determine a mixture pay adjustment
from air voids and asphalt binder content. The PWL based quality determination used to establish the pay
adjustment will not be used for acceptance or rejection, which shall be based on visual inspection or
verification sampling as described below.
The actual mixture produced shall not vary from the job mix formula target values by more than the
production tolerances specified in Table 406-0004.03A. For the purposes of verification sampling, the
tolerances given in Table 406-0004.03A will be considered the specification limits for an individual
sample. Continued production outside these ranges will be grounds to halt production and rescind the mix
design.
Material may be sampled at either the production facility or on the project site and may be tested at either
the production facility’s qualified lab or at the Agency’s Materials Testing and Certification Section
Central Laboratory.
Special Provisions Part II – Special Specifications
TABLE 406-0004.03A – MIXTURE PRODUCTION TOLERANCES
Material Property Lower Mixture
Tolerance
Upper Mixture
Tolerance
Coarse aggregate, percent passing the No. 4 (4.75 mm)
or larger sieves (dry sieve) JMF – 6% JMF + 6%
Fine aggregate, percent passing the No. 8 (2.36 mm)
sieve through the No. 100 (0.150 mm) sieve (dry sieve) JMF – 4% JMF + 4%
Fines, percent passing the No. 200 (0.075 mm) sieve
(dry sieve) JMF – 1% JMF + 1%
Mixture temperature 1 JMF – 20°F JMF + 20°F
Air voids JMF – 1.0% JMF + 1.0%
Dust proportion 0.50 1.00
Voids in mineral aggregate JMF – 1.0% JMF + 1.0%
Asphalt binder content JMF – 0.4% JMF + 0.4%
1 The mixture temperatures shall not exceed 355°F.
(a) Lots and Sublots. The entire quantity of a single mix design of thin overly mixture will constitute
a lot. Sublots shall be a maximum of 500 tons. Samples will be taken once per sublot.
At the Engineer’s discretion, low production activities, defined as a daily production of 300 tons
or less, that would otherwise be evaluated as part of the lot may be excluded from the PWL lot for
the purposes of pay factor calculation.
(b) Evaluation Method. The percent within limits (PWL) method will be used to determine the quality
of the material produced based on the quality characteristics specified in Subsection 406-
0004.03(c). The LSL shall be the lower mixture tolerance and the USL shall be the upper mixture
tolerance specified in Table 406-0004.03A. Detailed documentation on the PWL method is
available in the Agency’s Bituminous Concrete Quality Manual.
(c) Quality Characteristics. The quality of the mixture will be evaluated based on the air voids and
asphalt binder content. Asphalt binder content will be measured in a calibrated ignition oven in
accordance with AASHTO T 308.
(d) Pay Factor. A composite weighted pay factor combining the PWL of each quality characteristic
will be calculated to account for the overall quality of the lot. If mix design JMF changes cause
there to be multiple lots, a separate pay factor will be calculated for each lot.
Special Provisions Part II – Special Specifications
(e) Removal of Defective Material by the Contractor. With the approval of the Engineer, the
Contractor may elect to remove any defective material and replace it with new material at no
expense to the Agency. Any such new material will be sampled, tested, and evaluated for quality.
(f) Rounding and Reporting of Values. Results from all calculations shall be rounded and reported as
follows. All pay factors will be reported to 0.0001 and all pay adjustments to 0.01. For intermediate
calculations used to obtain pay factors and pay adjustments values shall retain the maximum
available precision.
When rounding, if the first digit to the right of the number to be rounded is greater than or equal
to 5, then the number will be rounded away from zero to the next number with larger magnitude.
If the digit to the right of the number to be rounded is less than 5, then the number will remain the
same.
406-0004.04 CONTRACTOR QUALITY CONTROL. The Contractor shall be responsible for
maintaining control of the mix production process. The mix production methods and technologies
shall generally be at the Contractor’s discretion, but will be limited to proven, Agency and industry
accepted practice. Upon approval of the Engineer and at no additional cost to the Agency, the Contractor
may use innovative equipment or techniques not included in the specifications to produce or monitor the
production or placement of the mixture.
(a) Control of Mixture. The plant shall be operated so that no intentional deviations are made from
the approved job mix formul