The San Francisco Public Utilities Commission (SFPUC) Power Enterprise is advancing the Spear Street Substation Project (Project) to support the continued reliability, resiliency, and capacity of San Francisco’s electrical transmission and distribution system, particularly in the downtown and waterfront areas. Please refer to Exhibit 1 for more detailed information regarding the updated project description. This Request for Interest (RFI) is referred to as RFI Number 002 (RFI No. 002) because it is a follow-up to the RFI sent in March 2026 (here after referred to as RFI No. 001).
This RFI is for informational purposes only. SFPUC does not guarantee the accuracy of any information contained herein. The information is general and preliminary in nature, subject to change, and will provide the basis for discussion and planning by SFPUC. No person, entity, or other party is entitled to rely on this RFI or the information contained herein for any purpose, including without limitation, submitting a bid or proposal, or entering into a contract related to the Project.
The Spear Street Substation Project is a critical component of the SFPUC Power Enterprise capital program and will be delivered using a Progressive Design-Build approach. To support industry engagement and ensure the market is well-positioned to successfully respond to this important solicitation, SFPUC has implemented a comprehensive outreach plan that includes:
(1) RFI No. 001 [March 2026, Complete]
(2) RFI No. 002 [this document]
(3) Meetings with Potential Primes Anticipated week of December 14, 2026
SFPUC values early market feedback during the Project development process. Respondents who submit responses are not obligated to propose if/when final procurement documents are released. Additionally, responses will remain anonymous and will not be shared with other participants, unless required by law. Responses may be subject to Public Records Act or Sunshine Ordinance requests, with potential withholding rights pursuant to San Francisco Administrative Code Section 67.24. SFPUC will endeavor to give the subject Respondent(s) reasonable notice of any such requests, to the extent possible, so that the Respondent(s) may seek court intervention prior to the production deadline.
SFPUC may seek to hold meetings or discussions with the Respondents to this RFI. In that event, SFPUC will issue further notice to all Respondents regarding the opportunity to meet and the guidelines for such meetings. If SFPUC provides this opportunity, it will be made available to all Respondents on equal terms.
We post new electrical opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most California work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: San Francisco Public Utilities Commission (solicitation 4633), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.