- South Dakota Department of Transportation - Bid Letting Information SDEBS Lettings Regional Lettings Bidding Information NEW Electronic Bidding Contractor Information Bid Letting Staff Error Message An error has occurred on the page you requested. Please contact the bid letting office at 605-773-3275 to report this error. Bid Letting Home Bid Letting Log In
- Pdf Text
- 1
DEPARTMENT OF TRANSPORTATION
NOTICE TO CONTRACTORS,
PROPOSAL, SPECIAL PROVISIONS,
CONTRACT AND CONTRACT BOND
FOR
VARIABLE SPEED LIMIT & ITS DEVICE
FEDERAL PROJECT NO. CR 0901(194)28
(PCN 05W7)
INTERSTATE 90
IN MEADE COUNTYDecember 9, 2026
DEPARTMENT OF
TRANSPORTATION
NOTICE TO ALL BIDDERS
TO REPORT BID RIGGING ACTIVITIES, CALL: 1-800-424-9071
THE U.S. DEPARTMENT OF TRANSPORTATION (DOT) OPERATES THE ABOVE TOLL-
FREE “HOTLINE” MONDAY THROUGH FRIDAY, 8:00 A.M. TO 5:00 P.M., EASTERN TIME.
ANYONE WITH KNOWLEDGE OF POSSIBLE BID RIGGING, BIDDER COLLUSION, OR
OTHER FRAUDULENT ACTIVITIES SHOULD USE THE “HOTLINE” TO REPORT SUCH
ACTIVITIES.
THE “HOTLINE” IS PART OF THE DOT’S CONTINUING EFFORT TO IDENTIFY AND
INVESTIGATE HIGHWAY CONSTRUCTION CONTRACT FRAUD AND ABUSE AND IS
OPERATED UNDER THE DIRECTION OF THE DOT INSPECTOR GENERAL.
ALL INFORMATION WILL BE TREATED CONFIDENTIALLY, AND CALLER ANONYMITY
WILL BE RESPECTED.
* * * *
PLANS, PROPOSALS AND ADDENDA
AFTER AWARD OF CONTRACT, THE LOW BIDDER WILL RECEIVE TEN (10)
COMPLIMENTARY SETS OF PLANS, PROPOSALS, PROJECT Q & A FORUM, AND
ADDENDA FOR FIELD AND OFFICE USE. AN ELECTRONIC COPY WILL ALSO BE
PROVIDED. ANY ADDITIONAL COPIES REQUIRED WILL BE THE RESPONSIBILITY OF THE
CONTRACTOR.
* * * *
Project Number: CR 0901(194)28 Revised 10/8/25
PCN 05W7
NOTICE TO CONTRACTORS
Bid proposals for this project will be prepared, transmitted, and received electronically by the
South Dakota Department of Transportation (SDDOT) via the South Dakota Electronic Bid
System until 10 A.M. Central time, on December 9, 2026, at which time the SDDOT will open
bids. All bids will be checked for qualifications with results posted on the SDDOT website. The
South Dakota Transportation Commission will consider all bids at a scheduled Commission
meeting.
The work for which proposals are hereby requested is to be completed within the following
requirement(s):
FIELD WORK COMPLETION: NOVEMBER 19, 2027
The project category is Category I
The project type is Structural
The geographic zone is Zone 2
THE DBE GOAL FOR THIS PROJECT IS: N/A
WORK TYPE FOR THIS PROJECT IS: WORK TYPE 10
Bidding package for the work may be obtained at:
http://apps.sd.gov/hc65bidletting/ebslettings1.aspx#no-back-button
The South Dakota Standard Specifications for Roads and Bridges, 10-7-26 Version, may be
obtained at https://dot.sd.gov/doing-business/contractors/standard-specifications/ .
The electronic bid proposal must be submitted by a valid bidder as designated by their
company’s https://apps.sd.gov/HC65C2C/EBS/BidAdminAuthorizationForm.pdf. A bidding
administrator will have privileges in the SDEBS to prepare bids, submit bids, and authorize
additional company employees to prepare and submit bids. Additionally, a bidding
administrator will be responsible for maintaining the list of authorized bidders for the company
and will have the ability to add employees, remove employees, and set-up bidder
identifications and passwords within the SDEBS. Bidding Administrator authorization will
remain in full force and effect until written notice of termination of this authorization is sent by
an Officer of the company and received by the Department.
A bidder identification and password, coupled with a company identification previously
assigned by the Department, will serve as authentication that an individual is a valid bidder for
the company.
Contact information to schedule a preconstruction meeting prior to commencing with the work
on this project.
Mike Carlson
2300 Eglin St PO Box 1970
Rapid City, SD 57709-1970
Phone: 605/394-2244
PROPOSAL Revised 8/10/11
SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION, STATE OF SOUTH DAKOTA:
Ladies / Gentlemen:
The following proposal is made on behalf of the undersigned and no others. It is in all respects
fair and is made without collusion on the part of any other person, firm or corporation not
appearing in the signature to this proposal.
The undersigned certifies that she / he has carefully examined the plans listed herein, the
Specifications hereinbefore referred to, the Special Provisions and the form of contract, both of
which are attached hereto. The undersigned further certifies that she / he has personally
inspected the actual location of the work, together with the local sources of supply and that she /
he understands the conditions under which the work is to be performed, or, that if she / he has
not so inspected the actual location of the work, that she / he waives all right to plea any
misunderstanding regarding the location of the work or the conditions peculiar to the same.
On the basis of the plans, Specifications, Special Provisions and form of contract proposed for
use, the undersigned proposes to furnish all necessary machinery, tools, apparatus and other
means of construction, to do all the work and furnish all the materials in the manner specified, to
finish the entire project within the contract time specified and to accept as full compensation
therefore the amount of the summation of the products of the actual quantities, as finally
determined, multiplied by the unit prices bid.
The undersigned understands that the quantities as shown in the Bid Schedule are subject to
increase or decrease, and hereby proposes to perform all quantities of work, as increased or
decreased, in accordance with the provisions of the specifications, and subject to any applicable
special provisions, and at the unit prices bid.
The undersigned understands that the "Total or Gross Amount Bid" as immediately hereinbefore
set forth is not the final amount which will be paid if this proposal is accepted and the work done,
but that such amount is computed for the purpose of comparison of the bids submitted and the
determination of the amount of the performance bond.
The undersigned further proposes to perform all extra work that may be required on the basis
provided in the specifications, and to give such work personal attention in order to see that it is
economically performed.
The undersigned further proposes to both execute the contract agreement and to furnish a
satisfactory performance bond, in accordance with the terms of the specifications, within twenty
(20) calendar days after the date of Notice of Award from the South Dakota Department of
Transportation that this proposal has been accepted.
CERTIFICATION REGARDING LOBBYING
I certify, to the best of my knowledge and belief, that: No Federal appropriated funds have
been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or
attempting to influence an officer or employee of any agency, a member of Congress, an
officer or employee of Congress, or an employee of a member of Congress in connection with
the awarding of any Federal contract, the making of any Federal grant, the making of any
Federal loan, the entering into of any cooperative agreement, and the extension, continuation,
renewal, amendment, or modification of a Federal contract, grant, loan, or cooperative
agreement. If any funds other than Federal appropriated funds have been paid or will be paid
to any of the above mentioned parties, the undersigned shall complete and submit Standard
Form LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.
The undersigned shall require that the language of this certification be included in the award
documents for all subawards at all tiers (including subcontracts, subgrants, and contracts
under grants, loans, and cooperative agreements) and that all subrecipients shall certify and
disclose accordingly. This certification is a material representation of fact upon which reliance
was placed when this transaction was made or entered into. Submission of this certification is
a prerequisite for making or entering into this transaction imposed by section 1352, title 31,
U.S. Code. Any person who fails to file the required certification shall be subject to a civil
penalty or not less than $10,000 and not more than $100,000 for each such failure.
REV 11/2/26
INDEX OF SPECIAL PROVISIONS
PROJECT NUMBER(S): CR 0901(194)28 PCN: 05W7
TYPE OF WORK: VARIABLE SPEED LIMIT & ITS DEVICE
COUNTY: MEADE
The following clauses have been prepared subsequent to the Standard Specifications for Roads
and Bridges and refer only to the above described improvement, for which the following
Proposal is made.
The Contractor’s attention is directed to the need for securing from the Department of
Environment & Natural Resources, Foss Building, Pierre, South Dakota, permission to remove
water from public sources (lakes, rivers, streams, etc.). The Contractor should make his request
as early as possible after receiving his contract, and insofar as possible at least 30 days prior to
the date that the water is to be used.
Jonathan England is the official in charge of the Spearfish Career Center for Meade County.
THE FOLLOWING ITEMS ARE INCLUDED IN THIS PROPOSAL FORM:
Special Provision for Contract Time, dated 11/10/26.
Special Provision Regarding Railroad Insurance Requirements for RCP&E Railroad,
dated 11/12/26.
NOTE: The Contractor WILL NOT be granted permission to proceed with any work on
Railroad Right-of-Way until he has been notified by the Railroad that the insurance has
been approved and the insurances and certificates has been provided to the SDDOT
area office.
Special Provision Regarding Working on Railroad Property and Associated Contractor
Permits Needed for RCP&E Railroad, dated 11/12/26.
Special Provision for Contractor Staking, dated 11/6/26.
Special Provision for Fire Plan, dated 3/11/25.
Intelligent Transportation System Special Provision, dated 11/11/26.
Special Provision for Cylindrical Concrete Footings, dated 7/22/26.
List of Utilities.
Special Provision for Submission of Bid Proposals (SDEBS Lettings), dated 10/29/26. Special
Provision for Aggregates for Granular Bases and Surfacing, dated 10/26/26.
Special Provision for Acknowledgment and Certification Regarding Article 3, Section 12 of the
South Dakota Constitution, dated 8/24/23.
Fuel Adjustment Affidavit, DOT form 208 dated 11/25.
Standard Title VI Assurance, dated 3/1/16.
Special Provision for Equal Employment Opportunity Requirements for Highway Construction
Contracts, dated 10/7/26.
Special Provision for Contract Provisions for Federal-Aid Construction Contracts, Form
FHWA 1273 (Rev. June 25, 2026), dated 10/7/26.
Contract Provisions for Federal-Aid Construction Contracts, Form FHWA 1273 (Rev. 6/25/26).
Special Provision Regarding Minimum Wage on Federal-Aid Projects, dated 10/24/19.
Wage and Hour Division US Department of Labor Washington DC. - US Dept. of Labor Decision
Number SD20260001, dated 1/30/26.
Special Provision Regarding Stormwater Discharges to Waters of the State, dated 11/5/25.
General Permit Authorizing Stormwater Discharges Associated with Construction
Activities, dated 11/1/23.
https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/stormwater/StormWater
Construction.aspx
STATE OF SOUTH DAKOTA
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
CONTRACT TIME
PROJECT CR 0901(194)28, PCN 05W7
MEADE COUNTY
NOVEMBER 10, 2026
Sturgis Motorcycle Rally Restrictions
The Contractor will open all lanes to unimpeded traffic from July 31, 2027 to August 15,
2027 (inclusive) due to the Sturgis Motorcycle Rally. The Contractor will be allowed to
work through the Sturgis Motorcycle Rally provided there are no lane closures on I-90
and the Contractor only accesses the work sites from the interchange ramps and the
nearest intersecting road, unless written permission is granted by the Area Engineer.
The Department will make a disincentive assessment in the amount of $1,000 per
calendar day for the Contractor’s failure to comply with the Sturgis Motorcycle Rally
restrictions. A contract item for incentive/disincentive pay is included in the bid schedule
for the Department’s use in assessing disincentive. The Department will use a negative
quantity of days for assessing disincentives. The Department will not grant time
extensions for the Sturgis Motorcycle Rally restrictions for any reason.
Field Work Completion
The Contractor will complete the project by the November 19, 2027 field work
completion date.
The Contractor will complete all work on the project prior to the field work completion
requirement. If the Contractor does not complete all work by the field work completion
requirement, the Department will assess liquidated damages in accordance with Section
8.9. The Department will assess liquidated damages for each working day the work
(project) is late until the Contractor completes all field work. In the event the Contractor
does not complete all field work on time, the Department will count working days in
accordance with Section 8.7 B.
* * * * *
STATE OF SOUTH DAKOTA PAGE 1 OF 2
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION REGARDING
RAILROAD INSURANCE REQUIREMENTS FOR
RCP&E RAILROAD
IM 0901(194)28, PCN 05W7, MEADE COUNTY
VARIABLE SPEED LIMIT AND ITS DEVICES, STURGIS AREA, MEADE COUNTY, SD,
DOT 199689L, DOT 199691M, DOT 199683V, DOT 199698K
November 12, 2026
_______________________________________________________________________________________
Prior to commencing any work in the vicinity of the railroad property on this project, the successful
Contractor will provide and maintain in effect insurance covering all of the work and services to be
performed by the Contractor and each of its subcontractors in the coverage and minimum amounts as noted
below:
(1) Railroad Protective Liability: The RCP&E and the Genesee & Wyoming Inc. will be the Named
Insured for bodily injury and property damage of $2,000,000 per occurrence and $6,000,000 in the
aggregate.
(2) Workers’ Compensation Insurance: As required under the South Dakota Workmen’s Compensation Law.
(3) Commercial General Liability: For public liability, personal injury and property damage, as well as
Contractual Liability in the amount of $2,000,000 per occurrence, with an aggregate of $6,000,000.
(4) Automobile Liability: For bodily injury and property damage of at least $1,000,000 combined single
limit or the equivalent covering any and all vehicles owned or hired and used in performing services.
The RCP&E and the Genesee & Wyoming Inc. will be named additional insured for items 2, 3 and 4
above.
CERTIFICATES OF INSURANCE
The successful Contractor will issue to the following railroad Certificates of Insurance evidencing the
issuance of insurance coverage as prescribed in 1, 2, 3 and 4 above; certify that the Railroad will be given
not less than 30 days written notice prior to any material change, substitution or cancellation prior to normal
expiration dates; and the exclusion for working on, over, or within fifty feet (50’) of any railroad track will
be waived on the certificates. Cancellation or expiration of any of said policies of insurance will not preclude
railroad from recovery thereunder for any liability arising under this contract. Certificates of Insurance
holder will be:
Rapid City, Pierre & Eastern Railroad, Inc.
c/o Genesee & Wyoming Inc.
20 West Avenue
Darien, CT 06820
Special Provision Regarding Railroad Insurance Requirements for RCP&E Railroad Page 2 of 2
IM 0901(194)28, PCN 05W7, Meade County
November 12, 2026
The Contractor will submit the Certificates of Insurance to the Railroad at the following address:
Katie McGuier
Transaction Associate – Real Estate
Genesee & Wyoming Railroad Services, Inc.
13901 Sutton Park Dr., S., Suite 270
Jacksonville, FL 32224
Any questions or clarifications of Railroad’s insurance requirements may be directed to Katie McGuier, at
telephone number 904-900-6276, e-mail katie.mcguier@gwrr.com or to Cassidy Schnabel with the DOT at
605-773-5230, e-mail cassidy.schnabel@state.sd.us.
Additional insurance information can be found on the railroad’s web site using the following link:
https://www.gwrr.com/real_estate/insurance_requirements
The Contractor will also send a copy of all certificates and insurances to Mike Carlson, Rapid Area
Engineer, South Dakota Department of Transportation, PO Box 1970, Rapid City, SD 57709-1970, or
email mike.carlson@state.sd.us.
The successful Contractor will not be granted permission to proceed with any work on, over, or near
railroad property (at a minimum of 50 feet from centerline of any track) until the Contractor has been
notified by the Railroad that the required insurances have been approved and documentation of
approval has been provided to the Area Engineer.
All costs associated with these insurance requirements, including increasing policy limits, when required,
will be incidental to the bid item RAILROAD PROTECTIVE INSURANCE.
It is mutually understood and agreed that the purchase of insurance will not in any way limit the liability of
the Contractor to the Railroad.
Failure to obtain the required insurances and approvals prior to working on, over, or near Railroad
property will result in suspension of all work until required insurances are obtained and approved.
# # # # # # #
PAGE 1 OF 3
STATE OF SOUTH DAKOTA
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION REGARDING WORKING ON RAILROAD PROPERTY AND ASSOCIATED
CONTRACTOR PERMITS NEEDED FOR
RCP&E RAILROAD
IM 0901(194)28, PCN 05W7, MEADE COUNTY
VARIABLE SPEED LIMIT AND ITS DEVICES, STURGIS AREA, MEADE COUNTY, SD,
DOT 199689L, DOT 199691M, DOT 199683V, DOT 199698K
November 12, 2026
_______________________________________________________________________________________
(1) REQUIREMENTS OF THE CONTRACTOR IN RELATION TO THE PROTECTION OF THE RAILROAD
PROPERTY AND OPERATIONS FROM HAZARD DUE TO CONSTRUCTION OPERATIONS.
The Contractor is to contact Jeff Blachford, AVP Western Region Engineering, Genesee & Wyoming Railroad,
cell phone # 605-430-3284 at least five working days in advance whenever it is to enter the Railroad property.
However, a thirty-day notice is required before beginning of project to coordinate work. Manager may
designate others to represent the Railroad.
Construction activity that is within 25 feet laterally of center of any track and/or at any distance vertically from
top of rail of said track within 50 feet laterally of center of track will require flagging and/or a protective train
order, issued by the Railroad, for each train passing through or affected by said construction. The Contractor’s
work schedule will be coordinated with the State’s and Railroad’s Representative prior to notifying the
Railroad of required flagging dates.
Contractor will not be within 25 feet laterally and/or at any distance vertically of center of track when trains are
present. Contractor's work or activity will not interfere with or endanger Railroad operations or cause damage to
Railroad property.
Railroad flag protection may be required at any time the Railroad Representative believes that it is necessary to
safeguard Railroad’s operations and property.
The Railroad is to submit the billing for protective train orders and/or flagging directly to the Cassidy Schnabel,
Highway-Rail Safety Engineer, cassidy.schanbel@state.sd.us . Flagging will be paid for by the SD DOT
Department.
The Contractor is to Indemnify and Hold Harmless the Railroad for any personal injuries or property damage
arising out of this project to the extent as applicable by law.
(2) REQUIREMENTS FOR CONTRACTOR WORKING ON RAILROAD PROPERTY.
a. Absolutely no piling of construction materials or any other material, including dirt, sand, etc within 25
feet of center of track or on property of the Railroad not covered by Construction Easement or
Contractor's Permit/Lease.
b. No construction will be allowed within 25 feet of center of any track unless authorized by the Railroad
Representative and shown on Plan approved by the Railroad. This includes any excavation, bore pits,
slope encroachment and driving of sheet piles.
c. No change will be made to "Construction Plans" without approval by all parties involved. Approved
revised plan will be furnished to all parties prior to implementation of changes.
Special Provision Regarding Railroad Insurance Requirements for RCP&E Railroad Page 2 of 3
IM 0901(194)28, PCN 05W7, Meade County
November 12, 2026
d. No vehicles or machines will remain unattended within 25 feet from center of track.
e. Crossing of any Railroad track must be done at approved locations and must be full depth timbers,
rubber, etc. Any equipment with steel wheels, lugs, or tracks must not cross steel rails without aid of
rubber tires or other approved protection. Hauling across public crossings will be within legal load
limits.
f. All temporary construction crossings must be covered by a “Private Roadway & Crossing Agreement”
and will be paid for by the Contractor. All temporary crossings must be barricaded when not in use.
Crossing installation is to be coordinated with Railroad. Requests for temporary construction crossings
are to be directed to the Railroad at 605-430-3284.
g. Contractor will incur all costs for any track work made necessary due to his construction operations,
including but not limited to costs for temporary construction crossings and/or repair of damaged track or
any and all crossings.
h. Flagging protection may be required when equipment crosses, or Contractor is working within 25 feet
from center of track and/or at any distance vertically from top of rail of said track within 50 feet laterally
of the center of track. Flagging is a Federal requirement per 49CFR214.
i. Contractor must furnish details on how he will perform work that will affect existing drainage and/or
possible fouling of track ballast as well as removal of overhead bridges/structure.
j. Contractor's approved insurance must be in effect prior to entry onto Railroad property and during entire
project.
k. All permits, and Agreements must be in effect, payments made, and insurance policies received prior to
entering Railroad property.
l. Important - Disregard of any of these items will result in Contractor being shut down for a minimum of
48 hours on Railroad property while infraction is investigated. Based on the findings of the
investigation, it will be determined if the Contractor will be allowed to work on Railroad property in the
future.
m. Railroad may use a 3rd party vendor for some projects. The flagging may be paid through the project or
directly by the Contractor. If paid directly, the following should be kept in mind:
1. Contractor shall execute the flagging agreement with vendor.
2. Flagging must be requested 1 or 2 weeks ahead work.
3. Previously scheduled flagging must be cancelled 24 hours in advance, or a full day will be
charged.
4. Only full 8-hour days of flagging will be scheduled; partial days will not be considered.
Special Provision Regarding Railroad Insurance Requirements for RCP&E Railroad Page 3 of 3
IM 0901(194)28, PCN 05W7, Meade County
November 12, 2026
(3) RIGHT OF ENTRY FOR THE CONTRACTOR ON RAILROAD PROPERTY
Right of Entry will not be granted by either the Railroad Representative or State until the Contractor has
completed the following:
a. Contractor has provided the Railroad Protective Liability Insurance Policy to the Railroad and furnished
a certificate of said insurance to the State and Contractor has been notified by the Railroad that said
insurance is approved by the Railroad.
b. The ROE application is valid for only 60 days once executed. If the work is not completed within
the 60 days, an extension request must be submitted two weeks prior to the expiration date to
realestateapplications@gwrr.com with the File ID # in the subject line. There is a $500 extension
fee for each additional 30 days over the initial 60 days. Late requests will require a new agreement
and associated fees of $1,750.
c. Contractor has furnished a certificate of insurance for Commercial General Liability, Worker’s
Compensation Insurance, and Automobile Liability to the Railroad and State.
d. Contractor has acquired the Right of Entry License Agreement between the Contractor and the
Railroad. The State will submit the Right of Entry application on behalf of the Contractor prior to bid
opening. The Railroad will grant the State conditional approval to begin advertising for bids and
provide the State with the permit forms, which the state will include within the contract award
documents. The Contractor shall complete and submit the permit forms to the Railroad for
execution. The Contractor will be responsible for the permit fee, which will be $1,750. The
contractor is authorized to include in the bid an amount necessary to cover the permit fee applicable to
this project. The executed agreement will be returned to the Contractor. The Contractor must adhere
and comply with the terms and conditions of the Right of Entry Agreement and carry a copy of the
agreement at all times while on the railroads’ property.
e. Contractor has completed satisfactory arrangements with Railroad Representative for progress of work
without danger to train operations, without unnecessary interruption to train movements and for flagging
protection as necessary.
# # # # # # # # # # # # # #
14525101.docx 1
STATE OF SOUTH DAKOTA
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
CONTRACTOR STAKING
PROJECT CR 0901(194)28, PCN 05W7
MEADE COUNTY
NOVEMBER 6, 2026
Delete Section 5.8 of the specifications and insert the following:
SECTION 5.8
CONSTRUCTION STAKES, LINES AND GRADES
CONTRACTOR GRADE STAKING
A. DESCRIPTION
The Contractor will perform all construction staking. The staking work includes, but
is not limited to, establishing or re-establishing the project centerline; establishing
control points and benchmarks as needed; setting additional benchmarks as
needed; taking original and final cross sections of all Contractor secured borrow
sources and State designated borrow sources; taking cross sections of all topsoil
stockpiles; and staking right-of-way, easements, and fence.
The Contractor will perform all construction layout and reference staking necessary
for the accurate control and completion of all grading, paving, drainage, median
crossovers, signing, pavement marking, permanent benchmarks, detours, fence,
and all other appurtenances required for the complete construction and
acceptance of the work. The layout will include, but is not limited to, staking
easement line, staking clearing line, and performing the miscellaneous staking as
described in the plans and in this specification.
Horizontal and vertical control has been established as shown on the plans. Each
horizontal and vertical control point will be preserved or reset out of the work limits
and available during and after construction is complete. Prior to the Department’s
final acceptance of the project, the Contractor will replace or reset any control that
is disturbed during the construction of the project. The Contractor will provide the
Department a list of the in-place control points, including coordinates and
elevations relevant to the project control, at the end of the project.
14525101.docx 2
The Contractor will perform the staking work in accordance with the Department’s
Survey Manual, except as modified by this specification.
B. MATERIALS
The Contractor will furnish all staking materials of adequate quality for the purpose
intended including all stakes, stake chasers, paint, field note books, and all other
materials and equipment necessary to perform the required work.
C. CONSTRUCTION REQUIREMENTS
1. General: The Contractor will perform all staking work under the supervision of
a qualified surveyor or engineer who is experienced and competent in road and
bridge construction surveying and staking. The surveyor or engineer will be
available to review work, resolve problems, and make decisions in a timely
manner. A crew chief, competent to perform all required surveying duties, will
supervise the staking in the absence of the surveyor or engineer from the
project. The Contractor will submit the qualifications and work experience
history of the surveyor or engineer who will supervise the construction survey
work to the Engineer for review at least 14 calendar days prior to beginning the
staking work.
The Contractor will also submit the proposed starting date of the staking and
the anticipated surveying work schedule.
The Contractor will furnish, set, and properly reference all stakes, references,
lines, grades, and batter boards required. Minimum reference notations will be
for type, location, and alignment (when there are multiple alignments in the
same area). The Contractor will perform the survey and staking work in a
manner consistent with standard engineering practices and approved by the
Engineer.
The Contractor is solely responsible for the accuracy of the survey and staking
work. The Contractor will notify the Engineer of any errors and discrepancies
found in previous surveys, plans, specifications, or special provisions prior to
proceeding with the survey work.
The Contractor will be responsible for the supervision of the construction
staking personnel. The Contractor will correct any deficient survey or staking
work that results in construction errors at no additional cost to the Department.
The Contractor will keep field notes in conventional handwritten notebooks or
in a computerized form acceptable to the Engineer in a clear, orderly, and neat
manner. The notebooks will become the property of the Department upon
completion of the project. The notebooks will provide enough information such
14525101.docx 3
that quantity measurements are verifiable by the Department. Field notes are
subject to inspection by the Engineer at any time.
The Contractor is required to submit any remaining required quantity
calculations and notes to the Engineer no later than 60 calendar days after
completion of the survey and staking work.
The Department will set reference control points. The Contractor is responsible
for the preservation of ties and references to all control points necessary for the
accurate re-establishment of all base lines and centerlines shown in the plans,
whether established by the Contractor or found on or adjacent to the project.
The Department will also establish benchmark elevations. It is the responsibility
of the Contractor to verify the accuracy of the benchmark elevations prior to
use on the project.
The Contractor will furnish stakes of sufficient length to provide a solid set in
the ground. Stakes set not meeting these requirements will be reset at the
Contractors expense. The Contractor will replace stakes damaged, destroyed,
illegible, or made unusable at no additional expense to the Department.
The Engineer may check the accuracy and control of the Contractor's survey
and staking work at any time. The checks performed by the Engineer will not
relieve the Contractor of the responsibility for the accuracy of the survey layout
or the construction work. If the random checks show the grade is out of
tolerance, the Engineer may require the Contractor to set additional stakes, at
the discretion of the Engineer, at no additional cost to the Department. If the
Engineer orders additional stakes, the Contractor will perform the additional
staking until the Contractor can show the staking operations achieve the
specified grade tolerances.
Prior to any project staking, the Contractor will run a level circuit to check the
plan benchmarks the full length of the project.
2. Construction Staking: Construction staking will consist of all staking for
miscellaneous stakes in accordance with the following:
a. Miscellaneous Staking: Miscellaneous staking includes the following
work:
1) Easement line for items including, but not limited to, setting temporary
fence, utility relocation, and landowner reference and property use;
2) Clearing line for items identified by the clearing contract unit item
when provided in the plans;
3) Approach road staking and all tie-in checks. The Contractor will submit
profiles and elevations of all approach roads and other tie-ins
14525101.docx 4
throughout the project to the Engineer at least 3 business days prior to
staking;
4) Topsoil measurement and computation of quantities;
5) Special ditch staking;
6) Staking of signs, delineators, pavement markings, rumble strips/stripes,
guardrail, curb & gutter, light poles, conduit, mailboxes, junction boxes,
and related items (Staking is for all aspects, i.e. detours, temporary and
permanent);
7) Right-of-way staking including fence post panels;
8) Pipe and storm sewer staking including drop inlets, manholes, cattle
passes, and related items. If additional pipe, storm sewer, drop inlets,
manholes, or cattle passes are required which are not shown on the
plans, the staking will be paid for at the contract unit price per hour for
Engineer Directed Surveying/Staking;
9) Mark limits of removal items (trees, foundations, curb & gutter,
sidewalk, etc.);
10) Detours, roadway diversions, and crossovers. (This work includes all
design and staking notes required to design and stake the detour,
roadway diversion, or crossover in accordance with the plan
requirements. The Contractor will submit the completed design
including profile and alignment and staking notes to the Engineer at
least 3 business days prior to staking.);
11) Final and original cross sections of Contractor and State furnished
borrow pits and computations. The Contractor will perform earthwork
computations by the average end area method, surface-to-surface
method, or alternate computation method approved by the Engineer;
12) Resetting horizontal and vertical control, if disturbed;
13) Approach slab and sleeper slab staking;
14) Staking of sidewalks and curb ramps; and,
15) Staking of steps and wheel chair ramps.
The Contractor will perform the pipe staking so the pipe will fit the field
conditions. The plans show only approximate pipe locations and grades.
The Contractor will not install pipe prior to gaining the Engineer’s approval
of minor location and grade adjustments necessary for proper staking of the
pipe.
The Contractor will stake the slope catch points to determine the inlet and
outlet locations, set reference stakes for the inlet and outlet locations, and
stake ditches and special inlet and outlet grades to ensure proper drainage.
The staking of manholes and drop inlets will be included in pipe and storm
sewer staking. The Contractor will stake precast cattle passes similar to
drainage pipes.
The horizontal tolerance for the pipe and storm sewer staking is 0.05 foot
and the vertical tolerance is 0.03 foot.
14525101.docx 5
The Contractor will keep pipe staking notes on a DOT Form 214.
3. Engineer Directed Surveying/Staking: The use of the engineer directed
surveying/staking contract item is intended for surveying/staking not included
in the plan notes and this special provision. The Contractor may use a survey
crew to perform additional survey/staking work caused or required by the
Department. The Engineer will use a written order to authorize the hourly
engineer directed surveying/staking item and describe the surveying/staking
work required of the Contractor.
D. METHOD OF MEASUREMENT
Refer to the Table of Contractor Staking in the plans for more detail on how
quantities were calculated.
1. Construction Staking: The Department will not measure construction staking.
2. Engineer Directed Surveying/Staking: The Department will measure
engineer directed surveying/staking to the nearest 0.1 hour with the following
restrictions:
The use of engineer directed surveying/staking will be for the work ordered by
the Engineer. The measured quantity will be the actual time the survey crew is
working on the project, physically performing the field survey/staking work and
office time dedicated to the work specific to engineer directed
surveying/staking. The Department will not include travel time for the survey
crew in the measurement.
The Contractor will provide the Engineer documentation, such as an invoice,
showing the actual days/hours worked.
E. BASIS OF PAYMENT
Payment for all of the survey items will be considered full compensation for
furnishing all necessary personnel, vehicles, surveying equipment, supplies,
materials, recording fees, transportation, and incidentals to accurately and
satisfactory complete the work.
The Department reserves the right to omit any of these bid items without providing
compensation to the contractor if the Department deems the bid prices are
unreasonable.
1. Construction Staking: The Department will pay construction staking at the
lump sum price. The Department will make partial payment as follows:
14525101.docx 6
a. Upon submission of the name, experience, and qualifications of the
surveyor or engineer who will supervise the staking, the proposed starting
date, and the staking schedule, the Department will pay the Contractor 25
percent of the plan quantity for the construction staking.
b. The Department will make intermediate payments based on the amount of
the staking work completed.
c. The Department will make full payment at the plan quantity for construction
staking upon completion of all surveying and staking and when the
Contractor has furnished all field notebooks and records to the Engineer.
The Department will not adjust the contract unit price or plan quantity for
construction staking due to overruns or under runs in the other contract items.
2. Engineer Directed Surveying/Staking: The Department will pay engineer
directed surveying/staking on an hourly basis as per the Price Schedule for
Miscellaneous Items. The value listed in the Price Schedule for Miscellaneous
Items includes salaries, travel time, equipment, staking supplies, payroll
additive, and all incidental expenses related to providing the survey crew.
* * * * *
Prepared by:
Signed by:
Sign ed by:
JASON
VIRTUE
STATE OF SOUTH DAKOTA
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
FIRE PLAN
March 11, 2025
Digilally signed by JASON
VIRTUE
Date : 2025.03.25
08: 13:0 1 -06'00'
Ja son Virtue, Forest Fire Manage ment Officer
SHAWN
COCHRAN
Digitally signed by
SHAWN COCHRAN
Date: 2025.03.25
08:22: 12 -06'00'
Shawn Coch ra n, Black Hills NF Forest Superviso r
Revi sed M arch 11, 20 25
3/25/25
Date
3/25/25
Dat e
.3- ze,-ZS
Date
Revised March 11, 2025 2
TABLE OF CONTENTS
I. Responsibilities....................................................................................................................... 3
A. Contractor ........................................................................................................................ 3
B. Forest Service District Ranger or Delegated Fire Staff ..................................................... 3
II. Tools and Equipment ............................................................................................................. 4
A. Required Tools.................................................................................................................. 4
B. Available Equipment ........................................................................................................ 4
III. Personnel ............................................................................................................................. 4
IV. General Provisions .............................................................................................................. 4
A. Fire Prevention ................................................................................................................. 4
B. Fire Suppression ............................................................................................................... 6
C. Payment ........................................................................................................................... 7
D. Black Hills Fire Protection District .................................................................................... 7
1. PROHIBITIONS:.............................................................................................................. 7
2. EXEMPTIONS:..........................................................
- Enriched
- Yes
- Pdf Pages
- 164
- Work Desc
- Variable Speed Limit & ITS Device
- Work Type
- Work Type 10