SANITARY SEWER REHABILITATION PROGRAM JOB ORDER CONTRACT
OPENGOV ID NO. JOC261
The City of Phoenix is seeking qualified contractors to do business on an on-call basis to provide Sanitary Sewer Rehabilitation Job Order Contracting (JOC) Services for rehabilitation of primarily 8-inch to 15-inch diameter sanitary sewer but may include larger pipe diameters within the City of Phoenix wastewater collection system as described below. Up to five contractors may be selected for this JOC.
A Small Business Enterprise goal has been waived for this project.
The City of Phoenix has approximately 5,000 miles of gravity sewer with small diameter pipe comprising 92% of the wastewater collection system. The purpose of this program is to maintain the reliability and integrity of the wastewater collections system by rehabilitating existing infrastructure. This program is mainly for 8-inch to 15-inch diameter clay pipe, but rehabilitation may include pipe diameters greater than 15 inches and other pipe materials. The primary method of sanitary sewer rehabilitation is cured-in-place pipe (CIPP) utilizing felt and resin lining process. Occasionally the work may include dig and replace in lieu of CIPP-lining of existing pipe. At a minimum, the Contractor will be expected to successfully perform the following construction services, including, but not limited to:
• Traffic control
• Sewer cleaning
• CCTV or digital scans of sewer pipe/manholes
• Bypass pumping
• Trenching for bypass piping
• Pavement restoration
• Spot repair
• PVC-liner repair
• Install cured-in-place pipe (CIPP) structural liner
• Cleanout replacement/removal
• Manhole rehabilitation, repair or replacement
• New manhole installation
• Odor control
• All other work as it relates to rehabilitation of sanitary sewer system
This will be for a 36-month duration or $30,000,000 per JOC, whichever occurs first. The JOC will include an option to renew, based on the Contractor’s satisfactory performance, the City’s need for additional services, and funding availability. The option to renew will be for an additional 24-month term or the balance of the maximum contract amount for a total contract amount not to exceed $50,000,000, including all JOC amendments. The City intends that each Job Order Agreement (JOA) issued under this JOC will not exceed $4,000,000 in construction costs, but in no event will any JOA exceed $4,000,000 subsequent to Council approval of the change in limits.
The Contractor is required to provide performance and payment bonds in the amount of each Job Order proposal prior to executing the Agreement.
During the term of the JOC, work is performed as a series of individual Job Orders. Each Job Order Agreement, initiated by the City, is defined cooperatively by the City and the Contractor. A scope, schedule, and price are agreed upon, and the Contractor is directed to proceed with the work. JOAs may include pre-construction services, construction work, project management and contract administration as comprised within the Contractor’s construction management plan.
The scope of work will vary with each JOA. Minor design services may be required for some JOAs, however, most will be designed through consultants under a separate contract with the City. City staff may design some projects.
For JOAs that may require design services, the Contractor shall seek the services of an Arizona registered professional architect and/or engineer to prepare plans for permitting. It is the responsibility of the Contractor to provide cost estimating, project scheduling for design, construction and/or maintenance, and obtain permits if needed from the appropriate City departments. The Contractor is also responsible for:
Knowledge of and compliance with current City of Phoenix adopted codes
All other work as it relates to this JOC, and
All work incidental to this JOC
Prior to preparing each Job Order Agreement, a scope of work conference may be scheduled to define design and construction services required of the Contractor.
The City of Phoenix will provide construction administration, inspection, and acceptance material testing for the JOAs.
Assumptions about JOAs:
All sites will be in the State of Arizona.
The Contractor will furnish all necessary tools and test equipment required for the performance of its work in accordance with the scope of work.
All customer-provided documentation is obtained within a reasonable time at project start.
All customer-required approvals are provided within a reasonable and mutually agreed upon time frame.
Any work required at each site outside of this scope of work will be performed in accordance with the adjustment process.
Each JOA Schedule of Values must be submitted in MAG or CSI format or it will not be accepted.
Use of UNIFIER, an Application Service Provider (ASP) web-based project management database, may be required during this JOC. The following information provides a guideline for utilization. Any questions related to the requirements of UNIFIER should be directed to the Project Manager.
The Contractor will be required to maintain all project records in electronic format.
The City provides an ASP web-based project management database which the Contractor will be required to utilize in the fulfillment of the JOC requirements.
The Contractor shall provide a computerized networked office platform with broadband internet connectivity.
UNIFIER training will be provided through the City of Phoenix to firms under this JOC.
A pre-submittal meeting will be held at 1:00 pm, Phoenix time on Monday, November 9, 2026, at 200 W. Washington St. City Hall, 8th Floor, Conference Room AND via Teams. At this meeting, City staff will discuss the scope of work, general project requirements, and respond to questions from the attendees. It is strongly recommended that interested firms attend the pre-submittal meeting. Inquiries regarding the project scope outside of this pre-submittal meeting must be directed to the Contracts Specialist.
Pre-Submittal Meeting Teams Information:
Join: https://teams.microsoft.com/meet/2236122701102976?p=TnZ9jJARV3HRar5tYQ
Meeting ID: 223 612 270 110 297 6
Passcode: Jq3qX9kb
Firms will be selected through a qualifications-based selection process based on the criteria below. Subcriteria are listed in order of importance in relation to project services. City of Phoenix project experience is not required.
Description of project
Role of the person
Project’s construction cost
Construction dates
Project Owner
List any proposed subcontractors, including key staff names and the experience and qualifications of these individuals.
Scoring Method:
Points Based
Weight (Points):
250 (24.5% of Total)
4. Approach to Performing the Required Services
Describe the firm’s project management approach including its perspective and experience on partnering, quality control, project scheduling, claims, dispute resolution, changes in the scope of work, and construction safety.
Describe software systems and processes used for planning, project engineering and scheduling, estimating, and managing construction.
Provide a proposed subcontractor selection plan. The selection plan must select subcontractors based on qualifications alone or on a combination of qualifications and price and shall not select subcontractors based on price alone. Describe how you intend to implement this subcontractor selection plan. Discuss the benefit that your subcontractor selection plan provides to the project.
Scoring Method:
Points Based
Weight (Points):
350 (34.3% of Total)
5. Reference Checks
Use the form provided in the Attachments section to obtain at least three references. It is preferred no more than one be a City of Phoenix project. If your firm has not completed prior projects with other agencies, you will not be penalized. It is recommended there be references outside the City of Phoenix.
*These points are in addition to the 1,000 points for the SOQ.
Scoring Method:
Points Based
Weight (Points):
21 (2.1% of Total)
6. Submittal Requirements
6.1. JOC
Electronic Submittal Process: Firms interested in this project must submit a Statement of Qualifications (SOQ) electronically through the City's Procurement Portal at https://procurement.opengov.com/portal/phoenix.
Submittal requirements are as follows:
Vendor Information: All firms must be registered in the City’s Vendor Management System prior to submitting a proposal. The vendor number should be included on the cover of the SOQ. Information on how to register with the City is available at:
https://www.phoenix.gov/financesite/Pages/EProc-help.aspx
If your firm is already registered with the City of Phoenix’s Procurement system, visit https://procurement.opengov.com/portal/phoenix to login and access the electronic solicitation.
Submittals:
Experience Modification Rate (EMR) – provide current rating; the awarded company will be asked to provide verification upon contract execution.
Submit only one SOQ electronically, in .PDF format only, addressing all evaluation criteria. No hard copies will be accepted.
Clearly display the firm legal name, vendor number, project title, and project number on the cover of the SOQ.
A maximum of 10 pages is permitted to address all content in the SOQ submittal. (Maximum page limit includes evaluation criteria and all additional content. It does not include information sheet.)
Submit electronically the Statement of Qualifications by 12:00 pm, Phoenix time, on Monday, November 30, 2026.
Page size must meet requirements of 8½” x 11”.
Font size must not be less than 10 point.
Content count:
Each side of a page containing evaluation criteria and additional content will be counted toward the maximum page limit noted above.
Pages that have project photos, charts and/or graphs will be counted towards the maximum page limit noted above.
Front and back covers, information sheet, Table of Contents pages, and divider (tab) pages will NOT be counted toward the maximum page limit noted above, unless they include evaluation criteria and additional content that could be considered by the selection panel.
Information Sheet: Provide an information sheet that includes project title, OpenGov ID number, legal firm name (not a trade name), address, phone number, vendor number, and the name, title, email address and signature of your contact person for the project. Do not include any additional information.
Evaluation Criteria: Address the SOQ evaluation criteria.
Bonding Statement: As a separate PDF attachment, include a statement of the firm’s bonding capacity from a Surety Company (A- or better for the prior four quarters). This bond statement will not be counted towards the maximum number of pages.
Additional Content: Resumes and other information may be included (content shall be included within the permitted maximum page limit).
Note: All pages exceeding the specified maximum page limit will be removed from the submittal and not considered in evaluating a submitted SOQ.
Please be advised that the following will be grounds for disqualification, and will be strictly enforced:
Submitting a Statement of Qualifications for a different project.
Violating the “Contact with City Employees” policy contained in this RFQ.
Failure to provide additional documents due a time of submittal.
Failure to provide bonding statement.
8. Selection Process and Schedule
8.1. JOC
The successful firm will be selected through a qualifications-based selection process. Interested firms will submit a Statement of Qualifications (SOQ). A Selection Panel will evaluate each SOQ according to the criteria set forth in Statement of Qualifications Evaluation Criteria above. The City will select a firm based on the SOQs received; no formal interviews will be conducted.] The City may conduct a due diligence review on the firm receiving the highest evaluation.
The City expects to create a final list of at least five firms for this project. The City will enter into negotiations with the selected firm and execute a contract upon completion of negotiation of contract terms for City Council approval.
The following tentative schedule has been prepared for this project. The Pre-submittal meeting is not mandatory.
Pre-submittal Meeting 1:00 pm on Monday, November 9, 2026
SOQs Due 12:00 pm on Monday, November 30, 2026
Selection Notification January 2027
JOC Workshop February 2027
If the City is unsuccessful in negotiating a contract with the best-qualified firm, the City may then negotiate with the next most qualified firm until a contract is executed, or the City may decide to terminate the selection process. Once a contract is executed with the successful firm, the procurement is complete.
The firms selected for this project will be notified directly by the City. Notification to all o
Attached documents:
• SANITARY_SEWER_REHABILITATION_PROGRAM_JOB_ORDER_CONTRACT.pdf
• A - CONTRACTOR_REFERENCE_CHECK
• B - SBE JOC Clause Language
• C - SBE JOC-Contractor's Statement of Utilization Form
• D - SBE-Letter of Intent Form and Instructions
The contractor will perform sanitary sewer rehabilitation using cured-in-place pipe (CIPP) with felt and resin lining, and occasionally dig and replace. Services include traffic control, sewer cleaning, CCTV/digital scans, bypass pumping, trenching, pavement restoration, spot repair, PVC-liner repair, CIPP structural liner installation, cleanout replacement/removal, manhole rehabilitation/repair/replacement, new manhole installation, odor control, and all related work. The contractor must also provide cost estimating, project scheduling, obtain permits, and may need to engage an Arizona registered professional architect or engineer for design services. The contractor will use the City's UNIFIER web-based project management database and maintain all project records in electronic format.
We post new plumbing opportunities in Arizona as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s notice text — each row shows the sentence it came from. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: City of Phoenix (project JOC261), retrieved via the City of Phoenix OpenGov procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.