The City of Los Angeles is procuring construction of a cantilevered bulkhead retaining structure at 2735 Whittier Boulevard in the Boyle Heights neighborhood of Los Angeles, CA.
Only five prequalified contractors may bid as Prime Contractor: Calex Engineering, Clarke Contracting, Jilk Heavy Construction, Inc., Mike Prlich & Sons, Inc., and Mladen Buntich Construction Company.
The project will mitigate a public safety threat from encroaching debris by constructing a 10.5-foot-tall, 16-linear-foot bulkhead with three CIDH piles and cast-in-place concrete retaining walls, plus sidewalk removal and reconstruction.
Key dates: posted 2026-09-24, due 2026-10-21.
Procurement method: Competitive Sealed Bid.
Issuing agency: Engineering Bureau, Public Works.
Requirement: Only the following five Contractors can bid on this project as a Prime Contractor: • Calex Engineering • Clarke Contracting • Jilk Heavy Construction, Inc. • Mike Prlich & Sons, Inc. • Mladen Buntich Construction Company
Method
Competitive Sealed Bid
These takeaways are AI-generated and may be incomplete or wrong. Always verify every detail against the official documents before you bid.
Want to know if you can be bonded for this project? Get prequalified.One free application, soft pull — sized to your work.
Know you can be bonded before you spend a week on the bid
No scramble for a bond at the deadline — it becomes a request form
Construct a cantilevered bulkhead retaining structure approximately 10.5 feet tall and spanning 16 linear feet.
Install three cast-in-drilled-hole (CIDH) piles with cast-in-place reinforced concrete retaining walls between them.
Construct a grade beam along the bottom of the bulkhead.
Remove and reconstruct a portion of the sidewalk in front of the bulkhead.
Posted Scope of Work
■ Only the following five Contractors can bid on this project as a Prime Contractor:
• Calex Engineering
• Clarke Contracting
• Jilk Heavy Construction, Inc.
• Mike Prlich & Sons, Inc.
• Mladen Buntich Construction Company
♦ The project site is located at 2735 Whittier Boulevard in the Boyle Heights neighborhood of Los Angeles, specifically at the southern end of an alley east of the address. The existing slope condition at this location poses a significant threat to public safety due to encroaching debris.
♦ This project will mitigate the threat to public safety and protect the public right-of-way by constructing a new cantilevered bulkhead retaining structure. The proposed bulkhead will be approximately 10.5 feet tall and span 16 linear feet. It will consist of three cast-in-drilled-hole (CIDH) piles with cast-in-place reinforced concrete retaining walls placed between them. A grade beam will be constructed along the bottom of the bulkhead. The structure will extend approximately 6 inches below the sidewalk grade in front of the bulkhead. A portion of the sidewalk will also be removed and reconstructed.
♦ See bid package for full scope & details
♦ Bid package only on RAMP- if you're one of the prequalified contractors, download it to be a planholder
♦ For Bid Results visit http://engineering.lacity.gov/contractors/
Scope, read from the documentsAI-generated
The project will construct a new cantilevered bulkhead retaining structure approximately 10.5 feet tall and spanning 16 linear feet. It will consist of three cast-in-drilled-hole (CIDH) piles with cast-in-place reinforced concrete retaining walls placed between them. A grade beam will be constructed along the bottom of the bulkhead. The structure will extend approximately 6 inches below the sidewalk grade in front of the bulkhead. A portion of the sidewalk will also be removed and reconstructed.
More concrete bids in California, weekly.
We post new concrete opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Questions & answers
AI-generated
Who can bid as a Prime Contractor on this project?
Only the following five Contractors can bid on this project as a Prime Contractor: Calex Engineering, Clarke Contracting, Jilk Heavy Construction, Inc., Mike Prlich & Sons, Inc., and Mladen Buntich Construction Company.
Where is the project site located?
The project site is located at 2735 Whittier Boulevard in the Boyle Heights neighborhood of Los Angeles, specifically at the southern end of an alley east of the address.
What is the due date for bids?
The due date is 2026-10-21.
Full source recordEvery field City of Los Angeles RAMP published, untouched
■ Only the following five Contractors can bid on this project as a Prime Contractor:
• Calex Engineering
• Clarke Contracting
• Jilk Heavy Construction, Inc.
• Mike Prlich & Sons, Inc.
• Mladen Buntich Construction Company
♦ The project site is located at 2735 Whittier Boulevard in the Boyle Heights neighborhood of Los Angeles, specifically at the southern end of an alley east of the address. The existing slope condition at this location poses a significant threat to public safety due to encroaching debris.
♦ This project will mitigate the threat to public safety and protect the public right-of-way by constructing a new cantilevered bulkhead retaining structure. The proposed bulkhead will be approximately 10.5 feet tall and span 16 linear feet. It will consist of three cast-in-drilled-hole (CIDH) piles with cast-in-place reinforced concrete retaining walls placed between them. A grade beam will be constructed along the bottom of the bulkhead. The structure will extend approximately 6 inches below the sidewalk grade in front of the bulkhead. A portion of the sidewalk will also be removed and reconstructed.
♦ See bid package for full scope & details
♦ Bid package only on RAMP- if you're one of the prequalified contractors, download it to be a planholder
♦ For Bid Results visit http://engineering.lacity.gov/contractors/
Surety · through Light RFPprequal free · bid bond free · p&p 3%
Need a bond for this one? Get prequalified once.
Most California work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
Prequalified contractors know they can be bonded before they write the bid — and skip the application on every one of these. The bond becomes a request form and a copy of the RFP, not a scramble at the deadline.Prequalify For Bonding →What’s a good guy letter?
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Not finding it?Describe the work in your own words and we’ll search the whole site.Search with AI →
Source: City of Los Angeles RAMP (bid 232053), retrieved via the City of Los Angeles. View the official posting, and always confirm requirements and deadlines with the issuing agency.