Extending existing pipe culverts to clear zone and removing guardrail on Kathleen Rd. located 1.1 miles south of IL 152.
Item: 140
Contract: 99774
Region/District: 5 / 9
DBE goal: Pending%
VBP goal: Pending%
Federal Project: 7J3I(406)
Key Routes: FAS 1824
Marked Routes: KATHLEEN ROAD
Sections: 24-00155-00-SP
State Jobs: C-99-017-26
Contract specifics:
The work includes earth excavation (80 cu yd), furnished excavation (115 cu yd), trench backfill (81 cu yd), stone riprap class A4 (69 sq yd), filter fabric (69 sq yd), aggregate base course type B 12" (152 sq yd), bituminous materials prime coat (341 lb) and tack coat (35 lb), hot-mix asphalt binder course IL-19.0 N50 (18 ton) and surface course IL-9.5 mix C N50 (11 ton), pavement removal (122 sq yd), pipe culvert removal (103 ft), metal flared end sections 48" (4 each), pipe culverts class C type 1 48" (141 ft), guardrail removal (256 ft), mobilization (1 lump sum), seeding class 2 special (0.5 acre), and traffic control and protection standard BLR 21 (1 lump sum).
We post new fencing opportunities in Illinois as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Illinois work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Illinois Department of Transportation (solicitation 99774), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.