Construction of three-span steel wide flange beam bridge carrying CH 17 over LaHarpe Creek in Hancock County. Work also includes HMA approach roadways, aggregate shoulders, guardrail and other required work.
Item: 103
Contract: 93862
Region/District: 4 / 6
DBE goal: Pending%
VBP goal: Pending%
Federal Project: UL5K(408)
Key Routes: FAS 426
Marked Routes: CH 17
Sections: 22-00143-00-BR
State Jobs: C-96-007-26
Contract specifics:
Construction of a three-span steel wide flange beam bridge. Work also includes HMA approach roadways, aggregate shoulders, guardrail, tree removal, earth excavation, channel excavation, furnished excavation, geotechnical fabric for ground stabilization, seeding, fertilization, mulching, erosion control, stone riprap, filter fabric, subbase granular material, aggregate base course, bituminous materials, hot-mix asphalt binder and surface courses, pavement connector for bridge approach slab, pavement removal, aggregate shoulders, removal of existing structures, structure excavation, cofferdam excavation and cofferdams, concrete structures and superstructure, bridge deck grooving, protective coat, concrete approach slab, furnishing and erecting structural steel, stud shear connectors, epoxy coated reinforcement bars, steel railing, furnishing and driving steel piles, test piles, pile shoes, name plates, anchor bolts, granular backfill, geocomposite wall drain, concrete headwalls, pipe underdrains, steel plate beam guardrail, traffic barrier terminals, guardrail removal, mobilization, terminal markers, guardrail reflectors, bar terminators, fence removal, traffic control and protection, construction layout, and trainees.
We post new structural work opportunities in Illinois as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Illinois work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Illinois Department of Transportation (solicitation 93862), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.