The South Georgia Governmental Services Authority, d/b/a CNSNext ("SGGSA"), requests competitive sealed proposals from qualified contractors to construct fiber to the home outside plant in the Thomasville service area (OLT 12), as described in this Request for Proposals ("RFP"). This procurement is conducted by competitive sealed proposals under O.C.G.A. §§ 36-91-20 and 36-91-21(c). The work will be performed under a unit-price construction agreement. No federal funds are involved in this project.
EXHIBIT D
FORM OF AGREEMENT
UNIT PRICE CONSTRUCTION AGREEMENT
FIBER TO THE HOME OUTSIDE PLANT CONSTRUCTION
RFP NO. CNSNEXT-FTTH-2026-001
This Unit Price Construction Agreement ("Agreement") is made as of ________, 20
(the "Effective Date") between the South Georgia Governmental Services Authority, d/b/a
CNSNext, a body corporate and politic and political subdivision of the State of Georgia
created by Ga. L. 2001, p. 3560 ("Owner"), and ______________________________________________, a
_______________________________________ ("Contractor").
Owner issued Request for Proposals No. CNSNEXT-FTTH-2026-001 (the "RFP") for
the construction of fiber to the home outside plant. Owner's board determined in writing
that Contractor's proposal was the most advantageous to Owner under O.C.G.A. § 36-91-
21(c) and approved this Agreement on ________, 20. In consideration of the mutual
promises in this Agreement, Owner and Contractor agree as follows:
ARTICLE 1. CONTRACT DOCUMENTS AND DEFINITIONS
1.1 Contract Documents. The "Contract Documents" consist of the following, which are
incorporated by reference. If they conflict, they govern in this order of precedence:
(a) change orders and written amendments signed by both parties, the most
recent controlling;
(b) this Agreement;
(c) the Scope of Work, Technical Specifications, and Drawings (Exhibit A to the
RFP), as modified by addenda;
(d) the Unit Price Schedule (Contractor's completed Exhibit B, as accepted by
Owner) (the "Unit Price Schedule");
(e) The List of Owner-Furnished Materials (Exhibit C to the RFP);
(f) the RFP and its addenda; and
(g) Contractor's proposal, to the extent not inconsistent with the documents
listed above. Any exception in Contractor's proposal is excluded unless
Owner expressly accepted it in writing.
The project consists of constructing fiber to the home outside plant, including directional boring and placement of one to four 1.25-inch HDPE ducts; placement of non-traffic and traffic-rated handholes and pedestals; placement of fiber optic cable in conduit and aerial fiber optic cable lashed to strand, in counts from 12 to 288 fibers; installation of buried and aerial splice closures and outdoor fiber distribution terminals; installation of field-installable primary and secondary splitters and fusion splicing; testing (including OTDR and power meter testing) and documentation; as-built drawings and splice records; utility locates, traffic control, surface restoration, and cleanup; and coordination with pole owners and compliance with pole attachment and make-ready requirements.
We post new electrical opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-66952-NONST-2027-000000001), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.