Paulding County School Nutrition has issued a Request for Proposals seeking qualified vendors to provide and install a walk-in freezer/cooler and shelving at Northside Elementary School.
Attachment B
Northside Elementary Walk-In Cooler/ Freezer and Shelving Replacement
Respondents should note that all specifications list in this RFP are based on general
criteria that the Paulding County School Nutrition Program (SFA) feels is important for our
walk-in cooler/freezer/shelving providers. The SFA is open to reviewing all system proposals
for our walk-in cooler/freezer/shelving that may meet or exceed our needs. Our intent in
listing these specifications in the RFP is to give the Respondents a general idea of some of
the functions we would like to see. The SFA is looking to the Respondents to provide us with
as much information as possible about their particular product and how it can meet the
SFA needs. Any similarity in the specifications listed in this RFP document and any
manufacturer’s specifications is unintentional and should not be perceived as such.
Scope of Work
Paulding County School Nutrition has issued a Request for Proposals seeking
qualified vendors to provide and install a walk-in freezer/cooler and shelving at
Northside Elementary located at:
2223 Cartersville Hwy.
Dallas, GA 30132
This is a turnkey installation. Price must include demolition, full installation
including electrical by a licensed electrician and running refrigeration lines and
charging all refrigeration, any final trim needed for floor and ceiling. All debris must
be cleaned up and removed.
The scope of this solicitation encompasses the supply, delivery, and installation of a
walk-in cooler/freezer unit and shelving. Prospective contractors are expected to
furnish a turnkey solution that meets all applicable safety, quality, and performance
standards.
Supply, delivery and turnkey installation of an approximately 23' x 17' x 8' NSF-approved prefabricated walk-in cooler/freezer partitioned to fit the existing footprint, including 4-inch urethane panels, reinforced floor with non-slip rubber finish, two stainless-steel doors, LED lights, R-448A refrigeration with evaporators and condensers, Fermod-or-equal shelving, demolition, electrical by a licensed electrician, refrigeration piping and charging, pit preparation, trim, flashing and sealing, debris removal, testing to hold 0F or below in the freezer and 34F-38F in the cooler for five consecutive days, and a ten-year unit warranty.
We post new appliances opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Georgia work asks for the two below, and the solicitation documents are where it’s stated. Apply straight through for it — or prequalify once and skip the application on both.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-55813-NONST-2027-000000043), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.