The U.S. Army Corps of Engineers (USACE) at the Libby Dam Project (17877 Hwy 37, Libby, MT 59923) is modernizing its Main Unit Governors by replacing existing pressure switches with pressure transducers on five (5) units. The objective of this contract is to procure specialized governor control programming, Programmable Logic Controller (PLC) / Human Machine Interface (HMI) development, and commissioning support from the contractor to accommodate this hardware change. This is a turnkey requirement; the Contractor assumes full responsibility for understanding the existing system logic and delivering a fully functional, updated programming solution with no technical assistance from the Government.
Work shall be accomplished on a rolling outage basis as units become available, spanning from the Contract Award Date through August 30, 2027.
Work will occur across remote and on-site location, structured as follows:
Tasks 1 & 3 (Remote): Contractor's Facility.
Task 2 (On-Site Commissioning): Libby Dam Project, 17155 HWY 37, Libby, MT 59923-9703
Quoters must submit a Firm-Fixed-Price (FFP) quote for all contract line item numbers (CLINs). Incomplete quotes will be ineligible for award.
To be considered for award, interested parties must submit an email quote package directly adhering to the following rules:
E-mail Address: Quotes must be emailed to the Contract Specialist, Londres Medranda, at londres.medranda@usace.army.mil
SAM Registration: Offerors must have an active registration in the System for Award Management (SAM.gov) at the time of quote submission and maintain it through performance and final payment.
Inquiries & Questions: Questions must be sent via email to the Contract Specialist no later than five (5) working days prior to the quote due date. This ensures sufficient time for the Government to publish amendments on SAM.gov.
The Contractor shall provide all specialized engineering labor, travel, and remote support necessary to modify the pump logic for five (5) units at the Libby Generating Station. The work consists of in-house development and testing, on-site commissioning for the first unit, and remote commissioning support for the remaining four units. Specific tasks include: Task 1 - In-House PLC/HMI Development & Testing (up to 10 engineering hours); Task 2 - On-Site Commissioning for the first unit (including travel to/from Libby, MT and one full day of on-site support); Task 3 - Optional Remote Commissioning for Units 2-5 (up to 12 hours of remote engineering support). The Contractor shall provide updated PLC/HMI Logic (due 4 Weeks After Receipt of Order) and a Field Service Report upon completion of Task 2 travel.
We post new electrical opportunities in Montana as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"98134-2329""SEATTLE""WA""USA""KO CONTRACTING DIVISION""4735 EAST MARGINAL WAY SOUTH""Solicitation - W912DW27QA003 Governor Control Programming.pdf"3246868"file"".pdf""1""2026-10-20T21:07:11.117+00:00""44586f9636a64d4283d166b0afe210a4""public""0""public""dc328fd02d8949438815fb13bb8d71b5""0"1"0"Most Montana work asks for the two below, and the solicitation documents are where it’s stated. Apply straight through for it — or prequalify once and skip the application on both.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.