Kitsap County erosion control bonds.
Quote on review.

Kitsap County, Washington requires the project owner to post a performance bond for site stabilization before it issues a Site Development Activity Permit to clear, grade, fill or excavate one acre or more. The code gives two ways to size it; a surety specialist then returns your price, usually within one business day.

✓
Required by Kitsap County Code § 12.12.020 before a Site Development Activity Permit issues on one acre or more of land disturbance
✓
Sized at 150% of the engineer’s approved estimate (a $5,000 minimum bond), or a bond of $10,000 per disturbed acre with no estimate
✓
Priced on review — tell us the permit, the development and the disturbed acreage, and a specialist quotes it
Underwrittenthe county code sets the amount1 daytypical specialist replySoft pull onlynever a hard inquiry
Trusted by industry leaders
New York City Economic Development Corporation (NYCEDC)
Blumenfeld Development Group (BDG)
Capital Development Partners
McKinney Properties
Terra Capital
JLL (Jones Lang LaSalle)
Triple Five Group
The Georgetown Company
New York City Economic Development Corporation (NYCEDC)
Blumenfeld Development Group (BDG)
Capital Development Partners
McKinney Properties
Terra Capital
JLL (Jones Lang LaSalle)
Triple Five Group
The Georgetown Company
How it works

Built around your site development permit.

Kitsap County will not hold your pre-construction meeting or issue the Site Development Activity Permit until the erosion control bond is uploaded. Here is the whole process, from quote to permit:

TODAY · ONE APPLICATION

Send us the site

Apply online with your business details, the bond amount you are posting, the SDAP permit number, the name of the development, and the section and township-range of the parcel. The form ends with a credit consent that authorizes a soft pull only.

WITHIN 1 BUSINESS DAY

A surety specialist prices it

The code has already fixed how the bond is sized, so the review is about the project and the amount, not about re-estimating your work. A specialist confirms your exact premium and sends it back for approval.

ON APPROVAL

Pay, e-sign & upload to your SDAP

Once you accept the quote and pay, the executed bond arrives by email. Upload it to your permit in the county’s Online Permit Center as a Pre-Construction Document, then request the pre-construction meeting. The permit issues after that meeting. Check your acceptance letter for any county form it names, and send it to us if there is one.

About this bond

What it is and who needs it.

What the Kitsap County erosion control bond guarantees

Kitsap County regulates site development in its unincorporated areas through Title 12, Stormwater Drainage, of the Kitsap County Code. Section 12.12.010 requires that, before a Site Development Activity Permit (SDAP) issues and before any construction begins, the project owner record a performance covenant or post a performance surety for site stabilization and erosion and sedimentation control. Section 12.12.020 turns that choice into a firm rule for larger sites: for project sites with one or more acres of land-disturbing activity, a performance bond must be posted before the permit issues. Below one acre, § 12.12.030 lets the owner record a performance covenant against the land instead.

The bond guarantees Kitsap County that temporary erosion and sedimentation control and permanent site stabilization measures will perform as Title 12 requires. The owner sizes it one of two ways: 150% of the estimated cost of minor grading, temporary erosion and sedimentation control and permanent stabilization, from a cost estimate the project engineer submits for the director’s approval, with a $5,000 minimum bond; or a bond of $10,000 per acre of land-disturbing activity, with no engineer’s estimate required. If the director finds the site work violates Title 12, the county may use the bond to stabilize the site itself.

Two features matter more than the amount. The bond must run continuously until released by the county and cannot carry an expiration or cancellation date, so plan to keep it in force for the life of the permit. And it is released only after the work, including permanent stabilization, is done and the county gives final approval. It is a three-party arrangement: you (the principal), the surety, and Kitsap County (the obligee). It is not insurance for you — if the surety pays the county, you repay the surety. Projects constructed or owned by Kitsap County are exempt, and the cities of Bremerton, Port Orchard, Poulsbo and Bainbridge Island run their own codes.

Kitsap County Code § 12.12.020Kitsap County Code § 12.12.020 (Performance bond for site stabilization), in Chapter 12.12, Covenants, Sureties and Liability Insurance, of Title 12, Stormwater Drainage, provides that for project sites with one or more acres of land-disturbing activity a performance bond shall be posted before a site development activity permit issues, to guarantee Kitsap County that temporary erosion and sedimentation control and permanent site stabilization measures will perform in accordance with the title. The amount is either 150 percent of the estimated cost of minor grading, temporary erosion and sedimentation control and permanent site stabilization, from a project engineer’s estimate approved by the director or designee, with a $5,000 minimum bond, or $10,000 per acre of land-disturbing activity with no engineer’s estimate. If the director finds the site work in violation of the title, the county may use the bond to provide temporary and permanent site stabilization. All performance bonds run continuously until released by the county and are not subject to an expiration or cancellation date. Section 12.12.010 requires the owner to record a covenant or post a surety before the permit issues and construction begins, exempts projects constructed or owned by Kitsap County, and releases this surety when a final-plat performance bond is accepted that covers stabilization with the other incomplete work. Section 12.12.030 allows a recorded performance covenant in lieu of the bond on sites under one acre. The subdivision performance bond in § 12.12.040 and the two-year maintenance bond in § 12.12.060 are separate obligations.

You need this bond if you’re

✓
A developer or project owner clearing, grading or filling one acre or more in unincorporated Kitsap County under a Site Development Activity Permit
✓
A subdivision developer who needs site stabilization secured before plat construction begins — until a final-plat performance bond replaces it
✓
A commercial or industrial builder whose site work disturbs an acre or more and triggers the county stormwater minimum requirements
✓
A site or excavation contractor posting the bond for the owner so the pre-construction meeting and permit are not held up
After you buy

Claims, renewal, filing, and what sets the price.

If a claim is made

A claim comes from the party the bond protects, the obligee named on the form, when the duty the bond guarantees is not met.

The surety investigates and pays a valid claim, up to the bond amount. You then repay the surety: a surety bond is a guarantee of your performance, not insurance for you.

Renewal and term

Term and renewal are set in the underwriter's quote.

Keep the bond in force for as long as the obligation behind it runs.

How to file it

Pay, e-sign & upload to your SDAP. Once you accept the quote and pay, the executed bond arrives by email. Upload it to your permit in the county’s Online Permit Center as a Pre-Construction Document, then request the pre-construction meeting. The permit issues after that meeting. Check your acceptance letter for any county form it names, and send it to us if there is one.

What sets the price

This bond is underwritten: the premium is quoted from the bond amount and your financial picture, so there is no flat price to show.

One application, one specialist review.

These are the actual issuing fields — your business details, the bond amount, the SDAP permit number, the development name, and the section and township-range. The form ends with a credit consent that authorizes a soft pull only. Submit once and a surety specialist returns your exact price, typically within one business day. Free until your bond is issued.

Start the application →
FAQ

Common questions.

What is a Washington erosion control bond for Kitsap County?It is the performance bond for site stabilization that Kitsap County Code § 12.12.020 requires before the county issues a Site Development Activity Permit on a site with one or more acres of land-disturbing activity. It guarantees Kitsap County that your temporary erosion and sedimentation controls and permanent site stabilization will perform as the stormwater code requires. If the director finds the site in violation, the county can use the bond to stabilize the site itself.
Who sets the bond amount?The county code does, and you choose between its two methods. Either the bond is 150% of the estimated cost of minor grading, temporary erosion and sedimentation control and permanent stabilization, from your project engineer’s estimate as approved by the director, with a $5,000 minimum bond; or it is a bond of $10,000 per acre of land-disturbing activity, with no engineer’s estimate needed. On a site under one acre you can usually record a performance covenant instead of buying a bond.
How much does it cost?This bond is not on our carrier’s published rate sheet, and the penal sum is different on every site, so we quote it on review instead of showing a number checkout might not match. Submit the application with your bond amount, permit number and development details, and a surety specialist confirms your exact premium, typically within one business day. The bond amount is the surety’s maximum liability to the county, not something you pay.
Will I need collateral?Often not on an ordinary site. Because this bond cannot carry an expiration or cancellation date and stays in force until the county releases it, underwriting on a large or long-running project may ask for more information or, occasionally, collateral — and we tell you before you commit to anything. The application includes a credit consent, but it authorizes a soft credit pull only — a soft inquiry that never affects your score. No hard inquiry ever runs on this bond.
When is the bond released?Only when the county releases it. The code says the bond runs continuously until released and cannot have an expiration or cancellation date. Release follows completion of the work, including permanent stabilization, and final inspection and approval by the county. On a subdivision, the bond is released early when the county accepts a final-plat performance bond that covers stabilization along with the other unfinished work.
Which A-rated carriers underwrite these bonds?Typically Arch Insurance Company (A.M. Best A+) or Nationwide Mutual Insurance Company (A.M. Best A). Which one writes your bond depends on the bond type and your state. The carrier's name and official signature are printed on the bond you receive.
How do I contact Light RFP about this bond?Email insurance@lightrfp.com. It reaches the bond team at Light RFP Risk Management Services LLC (NY DFS License # PC-1978982). Write to us about quotes, applications, bond forms or certificates. We will respond within 24 hours.
Related bonds

Other Washington bonds.

Requirements checked on the carrier’s application, . Page updated .

Get the Kitsap County erosion control bond off your SDAP checklist.

Send us the bond amount, the permit number and the development details, and a surety specialist returns your price, typically within one business day. Free until issued.

PricingOn review