Read the notice and its 8 attached documents and pull out the scope, the deadlines and what you have to submit.
The boiler maintenance will provide all management, tools, supplies, equipment and labor necessary to perform all the work in maintaining 94 existing boilers/water heaters located in 71 facilities across Minot AFB, ND. The Contractor must assume maintenance of any new boilers installed for the duration of the boilers warranty (1) year from date of completed installation. Contractors will also be required to remove and dispose of existing boilers as well as install new boilers, up to 12 per year, not to exceed two every 30 days.
****AMENDMENT 004 This amendment adds additional questions and answers in the attached Q&A document.
***** AMENDMENT 003**** This amendment is to answer questions asked at the site visit on 11 August. See attachment " Questions answered from site visit FY27 Boiler Maintenance"
*AMENDMENT 002 This amendment fixes the date the RFQ closes to 4 September instead of 1 September.
AMENDMENT 001* This amendment uploads an amended combo solicitation to incorporate the new solicitation closing date of 4 September, updates the question and answer period and provides a site visit date of Tuesday, 11 August at 9:30am CST. Changes in the combo are highlighted in yellow and are included in the attachments of this solicitation.
List of attachments:
Performance Work Statement
Price Schedule
Provisions and Clauses
Wage Determinations
Financial Questionnaire
Combined Synposis/Solicitation
Questions answered from Site Visit FY27 Boiler Maintenance
We post new hvac opportunities in North Dakota as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"58705""MINOT AFB""ND""USA""CP 701 723 2889""165 MISSILE AVE""Amendment 4 Q and A.docx"18368"file"".docx""1""2026-08-17T15:53:57.953+00:00""9f9f3f2d72374f01bfbcf776e208647e""public""0""public""2880d0f0fdf74dbc967109174447fdc4""0"9"0""Questions answered from site visit FY27 Boiler Maintenance.docx"17125"file"".docx""1""2026-08-17T14:12:37.733+00:00""16ed1c17c4364a7ca2a10b38ded3b10b""public""0""public""a5354d34e4b34172a48a1bcadae454d2""0"8"0""Amendment 1 Combo Boiler Maintenance.pdf"198766"file"".pdf""1""2026-08-03T19:28:20.979+00:00""946dfad0e1e0480bbce22d9806385552""public""0""public""e86ffbde5617443bac519b757f97acdb""0"7"0""Financial Questionnaire Sheet.pdf"156118"file"".pdf""1""2026-07-20T14:52:47.978+00:00""4ad8bbb5ddcc48998ce58577f27096a6""public""0""public""5693efbc60cc4c089a90ed2cdc691554""0"5"0""Sam WD.pdf"73377"file"".pdf""1""2026-07-20T14:52:47.978+00:00""47ee4fb8c61745709bc8b128bb90ce98""public""0""public""7ba650e55d0b4198886d8ed95818cac0""0"4"0""Provisions and Clauses.pdf"133134"file"".pdf""1""2026-07-20T14:52:47.978+00:00""1824285d393a4b7f87334e2b62132238""public""0""public""c57ab8b2537a4f99ba418645a4c8f920""0"3"0""Boiler Maintenance Price Schedule.xlsx"22803"file"".xlsx""1""2026-07-20T14:52:47.978+00:00""1ffef2d4b1a34ec3befa2e8640601182""public""0""public""7b3f231ee0334063a14a6b4b3a22677f""0"2"0""Boiler MX PWS - Final.pdf"504799"file"".pdf""1""2026-07-20T14:52:47.978+00:00""ac5dead02c104fadaf7cfd55d4f31536""public""0""public""e4458f2dfaf34e4e87b362afad3fc8be""0"1"0"Most North Dakota work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: SAM.gov (notice e29bd8eea97f4e3d8e37d64c7d69eb2e), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.