Amendment 0001 corrects Section L Site Visit date to October 6, 2026
Request for Quote (RFQ) 140G0126Q0288
Site Visit October 6, 2026 at 9 AM local time at USGS/EROS Science Center, 47914 252nd Street, Sioux Falls SD 57198
(1)Point of contact. Kimberly Schneider, Department of Interior, Reston Science Acquisition Branch, Kimberly_Schneider@ios.doi.gov
(2) Set-asides. Total small business set-aside
(3) Codes for services or supplies. NAICS 238220; PSC Z2DB
(4) Description.
(i) The Department of Interior, USGS/Earth Resources Observation and Science (EROS) Center, Sioux Falls, South Dakota is seeking professional firms to provide construction to remove and replace chilled water piping and condenser water piping which serves the 1996 building addition at EROS. Location is the USGS/EROS Science Center, 47914 252nd Street, Sioux Falls SD 57198. A design to upgrade the system was completed as a result on 6/12/2020 titled Earth Resources Observation and Science Center Phase 1: EROS Fluid Coolers Design Services (Attachment 2). The 6/12/2020 as built drawings are included in Attachment 3 along with the mechanical system design criteria (Attachment 4). Due to cost constraints, the design, drawings and mechanical design attachments are provided for reference and basis of design only. Removal and replacement of cooling towers have been completed. The third chiller will not be completed under this contract. Design reference documents to illustrate prior design intent and existing conditions. Only the requirements specifically identified in the Statement of Work constitute the contractually binding scope.
(ii) Procedures in accordance with FAR 12.201-1 Simplified procedures. The anticipated award date is November 4, 2027.
(iii) N/A
(iv) Technical data will be furnished as attachments to this solicitation.
(v)Award of a construction contract to a small business is anticipated. Federal Acquisition Regulation (FAR) 36.101-4 requires agencies to provide a description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
(vi) All responsible sources may submit a quotation, bid, or proposal, as appropriate, which will be considered by the agency.
(vii) N/A
(viii) The offeror must represent, within SAM, that it qualifies as a small business under the applicable NAICS-based size standards. This shall be done through the System for Award Management (SAM.gov), where the offeror must self-certify their small business status by claiming the appropriate NAICS code and affirming size eligibility.
The contractor shall remove and replace chilled water piping, condenser water piping, and heating water piping, and update controls. The work includes installing new water piping networks from the mechanical room to supply mechanical equipment, removing existing piping, constructing systems to utilize pumps and VFDs, providing taps for future systems, and replacing pneumatic controls with electric actuators. The project must keep facility offices and computer rooms operational and be completed in phases with minimal impact. The specifications and drawings provided as attachments are for reference and basis of design only; only the requirements in the Statement of Work are contractually binding.
We post new plumbing opportunities in Virginia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""20192""RESTON""VA""USA""12201 SUNRISE VALLEY DRIVE""Sol_140G0126Q0288_Amd_0001.pdf"207200"file"".pdf""1""2026-09-23T19:54:25.301+00:00""b18fd6bbff0d4770b69e2fc2d31eb42d""public""0""public""cbf75c4e510c4d3faa23715195d9141a""0"15"0""Sol_140G0126Q0288.pdf"509212"file"".pdf""1""2026-09-21T17:40:59.425+00:00""e107e34f4afe46468c0aa4dd50171863""public""0""public""8ea2fd923c7147e5b3cd88c6c85c8608""0"14"0""B08_Attachment_5_Bid_Schedule.xlsx"24125"file"".xlsx""1""2026-09-21T17:40:59.425+00:00""2708351abfea4a2c8ecceb872cbdf767""public""0""public""fa41609b10be4be8866a2f6ff8bf7921""0"13"0""B08_Attachment_4_2020-06-12_USGS_EROS_Mech_Narrative_Bid_Documents.pdf"90294"file"".pdf""1""2026-09-21T17:40:59.425+00:00""ae27724de7c049d8af81f5323e826aba""public""0""public""3dd1437985aa4e52b016baa9c774a5da""0"12"0""B08_Attachment_6_Wage_Determination_SD20260026_dtd_18_May_2026.pdf"150455"file"".pdf""1""2026-09-21T17:40:59.425+00:00""ce7b7d4bee9d4cc1a5d96dbe70d257af""public""0""public""dcef91a32249405f810af9b8e9dc5c82""0"11"0""B08_Attachment_7_Payment_Bond_SF25A-23a_upon_award.pdf"716931"file"".pdf""1""2026-09-21T17:40:59.425+00:00""f82dd3078b4a4db48053d04dfaf8af85""public""0""public""2316bc35044b4b3babbb482c9209d3bc""0"10"0""B08_Attachment_8_Performance_Bond_SF25-23a_upon_award.pdf"726819"file"".pdf""1""2026-09-21T17:40:59.425+00:00""d69a8a6dde0144f1be9bf48ce7bab2f5""public""0""public""d25ce96acc934fbca2cc3fb43a893a1b""0"9"0""B08_Attachment_9_Subcontractor_Ack_SF1413-23a_upon_award.pdf"703768"file"".pdf""1""2026-09-21T17:40:59.425+00:00""e3dde8308f4e4c9ea60708057b781552""public""0""public""1249c246b9724ee4a4cf489b359623ed""0"8"0""B08_Attachment_10_Payroll_WH-347.pdf"304738"file"".pdf""1""2026-09-21T17:40:59.425+00:00""69d495bb7e5b4ce4b148a6139cbdf8ad""public""0""public""4dc0e53c4e324b56a9e079245af1f127""0"7"0""B08_Attachment_11_Form_DI-137_Release_of_Claims.pdf"36675"file"".pdf""1""2026-09-21T17:40:59.425+00:00""3f8520b9784c4261bd645619e58d994e""public""0""public""48c0e4684ea74ead93cc031eed1761d5""0"6"0""B08_Attachment_12_SF24-23a_Bid_Bond.pdf"720305"file"".pdf""1""2026-09-21T17:40:59.425+00:00""61c3dc5fb8db48dabcc20154ac0131e9""public""0""public""7f9f7eeb8647452592305b4a8b959e63""0"5"0""B08_Attachment_13_Past_Performance_Questionnaire_PPQ.pdf"49410"file"".pdf""1""2026-09-21T17:40:59.425+00:00""4bc8ea133e5c4083b425dce6ac624119""public""0""public""4be5d96bd0514812893124278f7bd570""0"4"0""B08_Attachment_2_2020-06-12_USGS_EROS_Specifications_Bid_Documents_Rev_1.pdf"7549088"file"".pdf""1""2026-09-21T17:40:59.425+00:00""c0629b1fbe1f4b48a8690f69ec0933be""public""0""public""c66523a8dba9428ab581f60e889912dd""0"3"0""B08_Attachment_3_20260317_USGS_EROS_Drawings_Bid_Documents_JLB.pdf"12458095"file"".pdf""1""2026-09-21T17:40:59.425+00:00""572bf56ee03444ac8ee85c7458ffd88e""public""0""public""726f23b7a05f4d20897163d8ba8290e8""0"2"0""B08_Attachment_1_SOW_EROS_Chilled_and_Condenser_Water_Piping.pdf"219119"file"".pdf""1""2026-09-21T17:40:59.425+00:00""b95344415b3f4c9ab94a5c25c884d839""public""0""public""b7fd89f9415443d2aaaf5bb47f58bda3""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: SAM.gov (notice d3b68a81275a4472a92a2dc7149929c8), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.