A. This project consists of modifying an existing waterline and replacing a water hydrant, removing an existing wood deck and constructing a new metal deck, replacing the existing roof, abatement of lead-based paint, removing lead-based paint siding, installing new siding, and preparing and painting exterior surfaces of the New Meadows Range Barn located at the New Meadows Barracks administrative site located at 100 S Norris Ave. New Meadows, ID 83654.
B. Base work includes the following described below:
Removal of existing roofing, installation of plywood sheathing over the existing skip sheathing, installation of ice/water shield over the entire roof, and installation of new corrugated metal roofing.
Abatement of lead-based paint of rafter tails, soffit, & fascia; and painting of aforementioned surfaces.
Removal of lead-based paint siding and felt paper, installation of plywood sheathing and building wrap, installation of new siding in-kind, installation of new trim in-kind around the windows, doors, and corners and painting of all aforementioned surfaces.
Replacement of approximately 10-feet of existing 1-inch SIDR 9 HDPE waterline including moving the existing hydrant location 2-feet to the east along the side of the building and replacement of the existing hydrant with a new hydrant and drainage basin. Additionally, replacement of an existing galvanized barb fitting with a brass barb fitting is required.
C. Optional work includes the following described below:
D. Quantities associated with these options are identified in the Schedule of Items
Base work includes: (1) removal of existing roofing, installation of plywood sheathing over existing skip sheathing, installation of ice/water shield over the entire roof, and installation of new corrugated metal roofing; (2) abatement of lead-based paint on rafter tails, soffit, and fascia, and painting of those surfaces; (3) removal of lead-based paint siding and felt paper, installation of plywood sheathing and building wrap, installation of new siding in-kind, installation of new trim in-kind around windows, doors, and corners, and painting all aforementioned surfaces; (4) replacement of approximately 10-feet of existing 1-inch SIDR 9 HDPE waterline including moving the existing hydrant location 2-feet to the east, replacement of the existing hydrant with a new hydrant and drainage basin, and replacement of an existing galvanized barb fitting with a brass barb fitting. Optional work includes removal of existing wood decking and foundation piers, and fabrication and installation of new expanded metal decking with steps over a metal frame with new foundation piers.
We post new paint opportunities in Idaho as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""US""83638""MCCALL""ID""USA""PAYETTE NATIONAL FOREST""500 N. MISSION STREET BLDG 2""C04a SF-1442 1240LT27Q0027.pdf"221659"file"".pdf""1""2026-10-29T13:05:11.412+00:00""a6e0a45fb12d4ef5a83e60686efa4f55""public""0""public""8e50f04bc39945638f6e6a7e77bff395""0"7"0""C04a SF-1442 1240LT27Q0027.pdf"202137"file"".pdf""1""2026-10-28T17:44:34.339+00:00""c522bd5586e94290a78d9f186e4f3242""public""2026-10-29T13:05:11.412+00:00""1""public""eb04585617ad462db71c37a7809ed0a3""0"6"0""2026-10-29T13:05:11.412+00:00""C04b 1240LT27Q0027.pdf"493401"file"".pdf""1""2026-10-28T17:44:34.339+00:00""597112229b3d429cbe6b432645a6a55b""public""0""public""498c0afdd01d49a3960bd7e94d4ad459""0"5"0""C04c SOW 1240LT27Q0027.pdf"577542"file"".pdf""1""2026-10-28T17:44:34.339+00:00""7d21f9c4bd1a421d966025a4714163e2""public""0""public""e0ad79c9585f4cb1946ccb906bdba3c1""0"4"0""C04d Drawings 1240LT27Q0027.pdf"4996317"file"".pdf""1""2026-10-28T17:44:34.339+00:00""85ada9c638f048a7861425a803cf36b8""public""0""public""35df42727f464a0b9339abd768880b5a""0"3"0""C04e Photos 1240LT27Q0027.pdf"2829559"file"".pdf""1""2026-10-28T17:44:34.339+00:00""916a88da18ac4fe4bb5928eda9101cf3""public""0""public""ac5f50414b094d89a8604749cb05b7f2""0"2"0""C04f WD Adams County Idaho 1240LT27Q0027.pdf"64655"file"".pdf""1""2026-10-28T17:44:34.339+00:00""60f6150bece94ac198a8b77cf91353b2""public""0""public""65f9109b28b046d497f81d1134182d75""0"1"0"Most Idaho work asks for the two below, and the solicitation documents are where it’s stated. Apply straight through for it — or prequalify once and skip the application on both.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: SAM.gov (notice b08fa8ab3a6d41a3b8a58fc869b015d8), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.