CONTINUATION OF SF 30 BLOCK 14 AMENDMENT DESCRIPTION 0001 AGAINST SOLICITATION NO. 36C24227R0008
This amendment posts the sign in sheet for the site visit that occurred on Monday, November 9th, 2026. See attached document.
This amendment answers the following question vendor question:
Could you confirm the intended local Eastern time for the November 9 site visit, November 16 questions deadline, and December 2 proposal deadline? The narrative says EDT, while SF1442 and SAM list EST for proposals.
Answer: Any reference to Eastern Daylight Time (EDT) in the solicitation should read as Eastern Standard Time (EST).
All other terms and conditions remain the same.
The contractor demolishes two existing boiler exhaust stacks, one generator steam relief stack, the concrete and masonry chimney, incinerator in the penthouse mechanical room and associated piping, performs asbestos-containing materials abatement and hazardous materials removal per drawings, constructs a new concrete foundation and footing and steel support structure, routes three new exhaust stacks through the building wall, installs two insulated boiler vents and one generator exhaust to terminations above the roof curb, re-roofs and seals all penetrations to match existing EPDM roofing, maintains clinic operations during phased work, and provides submittals, safety management, testing, and one-year workmanship warranty.
"US""12208""ALBANY""NY""USA""113 HOLLAND AVE""Site visit sign-in sheet.pdf"5686710"file"".pdf""1""2026-11-16T21:19:47.417+00:00""9248edbc1865423192bb7979353a00b1""public""0""public""1034581f32b941a0a338ac276abb775d""0"9"0""36C24227R0008 0001.docx"19921"file"".docx""1""2026-11-16T21:19:47.417+00:00""d619dadd5d264a2ea5fed45618cc7294""public""0""public""d425563ef77a4f25966bb21d36a3a15e""0"8"0""52.225-9 Buy American Certificate.pdf"129844"file"".pdf""1""2026-11-02T21:11:08.352+00:00""ca19a8926d2e433d9141e6e852dc2f0d""public""0""public""c5beefc9b17342df8a9e87dd4b312bab""0"7"0""WD Oneida 5-18-2026.docx"22633"file"".docx""1""2026-11-02T21:11:08.352+00:00""08c1da26919a47af9d63397f89084a5e""public""0""public""0db7ed802bc84463aac619ca8d5d8be2""0"6"0""boilerspec 1.pdf"1672689"file"".pdf""1""2026-11-02T21:11:08.352+00:00""f9e3cb33357b42e2af971d9fc029016c""public""0""public""e94751e595234014911398a0c72ac32b""0"5"0""Final_Specification of Repair Boiler Stack 528A7-18-707.pdf"2789824"file"".pdf""1""2026-11-02T21:11:08.352+00:00""c14d9099b5de45118dede6037e992939""public""0""public""d955a6c6f1ea4095b30ec640cc956b0b""0"4"0""528A7-18-707_Perforated Screen Drawing.pdf"62779"file"".pdf""1""2026-11-02T21:11:08.352+00:00""589512dc6a05491f9c971fc6bb1c147f""public""0""public""fd1d2c7b5a9e428d9e9d20b7d7fb459c""0"3"0""528A7-18-707_Final Bid Drawings.pdf"4646557"file"".pdf""1""2026-11-02T21:11:08.352+00:00""8936e50cbab7478e90f573b5ee3d21c7""public""0""public""8bfd7fabe5604083a4354b398715fea7""0"2"0""36C24227R0008_2.docx"275956"file"".docx""1""2026-11-02T21:11:08.352+00:00""1253382414b14272a7a53f7b323e5fdb""public""0""public""d324cdf2b5964950a45534544d8bc844""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.