SEALED BID
REQUEST FOR PROPOSAL
CONSTRUCTION MANAGEMENT SERVICES FOR
STATE HOUSE PANDEMIC MITIGATION/RENOVATION PROJECT
115 STATE STREET, MONTPELIER, VT
ISSUE DATE:
BIDDERS’ CONFERENCE:
QUESTIONS DUE BY:
.
RFP RESPONSES DUE BY:
November 13, 2026
December 9, 2026 at 11:00 AM
January 5, 2027 at 4:30 PM (EDT)
January 19, 2027 at 4:30 PM (EDT)
PLEASE BE ADVISED THAT ALL NOTIFICATIONS, RELEASES, AND ADDENDUMS ASSOCIATED
WITH THIS RFP WILL BE POSTED AT:
http://www.bgs.state.vt.us/pca/bids/bids.php
THE STATE WILL MAKE NO ATTEMPT TO CONTACT INTERESTED PARTIES WITH UPDATED
INFORMATION. IT IS THE RESPONSIBILITY OF EACH BIDDER TO PERIODICALLY CHECK THE
ABOVE WEB PAGE FOR ANY AND ALL NOTIFICATIONS, RELEASES AND ADDENDUMS
ASSOCIATED WITH THIS RFP.
STATE CONTACT: James Meyers, State Senior Purchasing Agent
E-MAIL: BGS.OPCVendorDocs@vermont.gov
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
1. OVERVIEW:
1.1. SCOPE AND BACKGROUND: Through this Request for Proposal (RFP) the Department of
Buildings and General Services (hereinafter the “State”) is seeking to establish a contract with a
construction management firm to provide Construction Management services (hereinafter the
“CM”) for the State House Pandemic Mitigation/Renovation Project. The primary objective of this
project is to create a single point of entry for security and an accessible entrance for better flow
and control of visitors to the State House.
1.2. CONTRACT PERIOD: The period of performance under this contract shall commence on
March 1, 2027 and end on January 1, 2032. See Section 5 – Project Schedule for specific
proposed dates.
1.3. SINGLE POINT OF CONTACT: All communications concerning this RFP are to be addressed
in writing to the State Contact listed on the front page of this RFP. Actual or attempted contact
with any other individual from the State concerning this RFP is strictly prohibited and may result
in disqualification.
1.4. BIDDERS’ CONFERENCE: A non-mandatory bidders’ conference will be held on-site at the
date and time indicated on the front page of this RFP. Prospective bidders shall meet at 115
State Street, Montpelier, VT at the west entrance.
1.5. QUESTION AND ANSWER PERIOD: Any bidder requiring clarification of any section of this RFP
or wishing to comment on any requirement of the RFP must submit specific questions in writing
no later than the deadline for questions indicated on the first page of this RFP. Questions may
be e-mailed to the point of contact on the front page of this RFP. Questions or comments not
raised in writing on or before the last day of the question period are thereafter waived. At the
close of the question period a copy of all questions or comments and the State's responses will
be posted on the State’s web site http://www.bgs.state.vt.us/pca/bids/bids.php. Every effort will
be made to post this information as soon as possible after the question period ends, contingent
on the number and complexity of the questions.
1.6. CHANGES TO THIS RFP: Any modifications to this RFP will be made in writing by the State
through the issuance of an Addendum to this RFP and posted online at
http://www.bgs.state.vt.us/pca/bids/bids.php . Verbal instructions or written instructions from any
other source are not to be considered.
1.7. BIDDERS ATTENTION IS DIRECTED TO:
1.7.1.Please be advised that all notifications, releases, and addendums associated with this
RFP will be posted at the website noted on the front page of this RFP. The State will
make no attempt to contact contractors with updated information. It is the
responsibility of each contractor to periodically check the posting site for any and all
notifications, releases and addendums associated with the RFP.
1.7.2.BONDING: Full bonding is required for this Project.
1.7.3.It is the Bidder’s responsibility to thoroughly read and comply with all instructions and
requirements of this bid solicitation. Your attention is directed to the special instructions
regarding the bid proposal submissions. Please follow the Instructions to Bidders carefully.
1.8. FUNDING SOURCE: This project is being funded, in whole or in part, through the American Rescue
Plan Act (ARPA) funds and/or Vermont Capital Construction Act funds. Wages for construction
employees shall be paid no less than the Vermont Prevailing Wage and Fringe Benefit Rate
requirements (reference Instructions to Bidders, Prevailing Wage Rate Requirements). A complete
list of occupations and associated wage rates are available on the internet at:
http://www.vtlmi.info/lmipub.htm
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
2. DETAILED REQUIREMENTS/DESIRED OUTCOMES:
2.1. The CM will join the project at the during of the Design Development phase. The CM will be required
to participate in the design process in order to enhance constructability, design quality, provide cost
estimates, reduce the amount of change orders, control costs and reduce the length of the overall
construction period.
2.2. For BGS billing purposes, the CM is to provide a cost breakdown for each of the following phases:
Construction Documents, Bidding & Negotiation, and Construction Administration.
3. PROJECT DESCRIPTION: This project shall ensure a safer working environment and efficient
operation of the State House to provide a single point of entry for security, accessible entrance and
allow for better control of visitors. It creates a safer working environment and efficient operation of the
State House to mitigate the impact of any future pandemics that allows Legislative functions to continue
unimpaired and create a new space for security screening of visitors
3.1. The following shall be included in the Construction Management firm’s scope of work:
3.1.1. Construct the new entrance and great hall per the construction documents.
3.1.2.Renovate some of the interior spaces per the construction documents for additional space .
3.1.3. Refer to the Design Development design plans for the complete scope of work.
3.1.4.The anticipated project schedule is noted in Section 5 below.
4. PROJECT BUDGET: The construction estimate, which includes all pre-construction and construction
services, costs and fees, General Conditions, Cost of Work, and project contingencies, is
$19,659,500.00.
5. PROJECT SCHEDULE:
The project is anticipated to begin as soon as this Contract is awarded with a preconstruction start date of
approximately March 1, 2027, with a Preconstruction phase ending August 1, 2027, with a construction
start of June 1, 2028, to align with legislative funding and a Substantial Completion date on or before
December 1, 2031. Final project schedule, sequences and milestones will be determined by the State
Project Manager, Architect, and the Construction Manager. Construction is dependent on funding by the
Legislature and is unknown until the completion of the legislative session. The contractor shall reflect a total
of 21 months of General Conditions on the enclosed Matrix.
Construction Document Start October 29, 2026
Preconstruction Start March 1, 2027
Construction Start June 1, 2028
Construction Pause for Legislative Session January 1, 2029
Construction Start June 1, 2029
Construction Pause for Legislative Session January 1, 2030
Construction Start June 1, 2030
Substantial Completion December 1, 2030
Project Completion January 1, 2031
Contract Completion (1 Year Warranty) January 1, 2032
5.2 All construction, demobilization, final performance testing, Operations and Maintenance Manuals,
and Substantial Completion related to the scope of work performed by the CM must be completed
by December 1, 2030; however, the Project Completion date is set for January 1, 2031, to allow for
the completion of the punch list, final payments, and other administrative purposes.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
6. PROPOSAL REQUIREMENTS:
6.1 PRE-CONSTRUCTION SERVICES: The pre-construction services shall include the services
noted in the State of Vermont Standard Contract for Construction Management Services with the
following additions, clarifications, modifications, and requirements.
6.1.1 For constructability review, the CM will be required, through meetings, phone conferences,
etc., to review the project design and develop a schedule, and advise on construction costs
and schedule implications.
6.1.2 The CM shall provide budget estimates for the project based on the completed Design
Development Drawings and Construction Documents. The budget estimates are to include
all costs associated with the project: CM fees, General Conditions, Cost of the Work, fit up
costs, and construction contingency, and shall include descriptions of any assumptions,
clarifications, budgets, or allowances used in the preparation of the budget estimates. The
budget estimates will serve as the basis for evaluating the State’s budget for construction
and for determining the necessity of incorporating cost-saving measures.
6.1.3 The CM shall provide constructability reviews along with the budget estimates and will be
required to submit a tracking list to assemble all review comments in one document and to
allow for the corresponding response to each item. Any cost values associated to a
comment should also be assigned to that comment. Comments are to include a thorough
review of all MEP systems by qualified specialists. The final constructability review shall
also include verification that the documents are complete and coordinated among
disciplines.
6.1.4 Provide cost saving suggestions and value engineering throughout the pre-construction
phase.
6.1.5 An overall site logistics plan is to be developed in close coordination with BGS. This plan is
to be updated throughout the project as site conditions dictate and should address, at
minimum: Site safety, schedule management, State operational needs and limitations.
6.1.6 The CM will follow the procedures for receiving and evaluating proposals, which are
acceptable to the State. If, with the approval of the State, the CM elects to self-perform a
portion of the work, they must submit their own bid 24 hours prior to receiving a competitor’s
bid. Any work performed by the CM will include the required supervision (foreman, etc.),
separate from the proposed CM supervision. If bids are not available in time to complete
the GMP, then allowances may be used in the GMP if clearly identified. A schedule of
rates for all CM staff shall be submitted with the proposal and approved by the State.
6.1.7 The CM will submit a GMP for construction for the project prior to the commencement of
construction. Subsequent to the CM’s submittal of the GMP, the CM will work with the
State and the design team on value engineering, cost saving measures, alternative pricing,
etc., as required by the State to bring the guaranteed maximum price within the State’s
budget.
6.1.8 The CM will be required to solicit a minimum of three (3) bids on all trade contracts and
major supply items greater than $15,000 when establishing the GMP.
6.1.9 Providing the State and the CM can establish a GMP, which is acceptable to both parties,
the State and the CM will amend the State CM Agreement Form between the State and
Construction Manager. The Fixed Fee for General Conditions and the Fixed Fee for
Construction Services shall be incorporated into the final agreement for construction.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
6.2 GENERAL CONDITIONS: Based on the proposed schedule and the available design information,
provide a lump sum fixed fee for all general conditions listed on the included Project Cost Matrix,
including the following:
6.2.1 Full-time and part-time supervision, including job superintendents, and project managers.
6.2.2 All job site office record keeping and clerical functions, including all required payroll
functions and reporting.
6.2.3 Administration and execution of all safety programs and safety personnel required by the
CM’s operations and as required to comply with all applicable safety regulations.
6.2.4 Maintaining and completing As-Built drawings, record documents and approved submittals.
6.2.5 Lockable barriers at all access roads, halls, doors, walkways, etc., to prevent
unauthorized vehicular, public, and staff traffic in construction areas.
6.2.6 Storage trailers as required for the CM’s work.
6.2.7 Job site security consisting of reasonable care and diligence in preventing unauthorized
activities on the job site, and the safety and well-being of staff, State employees and the
general public at all times.
6.2.8 Layout for line and grade. CM will be responsible for providing adequate horizontal and
vertical controls.
6.2.9 Labor and equipment to install and maintain temporary heat, including fuel costs, if and
when required to maintain temperature requirements of the facility or for construction.
6.2.10 Coordinating and maintaining dumpster service for all trades. Tipping fees shall be paid by
the CM as part of the cost of the work, not as a general condition.
6.2.11 Daily and final cleaning.
6.2.12 Wages and salaries of the Construction Manager’s supervisory or administrative personnel
engaged at factories, workshops or while traveling, in expediting the production or
transportation of materials or equipment required for the Work, but only for that portion of
their time required for the Work.
6.2.13 General material handling, labor and equipment. Specific material handling equipment,
such as cranes for setting structural steel and masons lifts, may be carried as a cost of the
work with the applicable trades.
6.2.14 All required job support vehicles.
6.2.15 All costs associated with conducting weekly job meetings and the distribution of meeting
minutes.
6.2.16 Creating and revising the construction schedule. All schedules and schedule revisions are
to be posted and distributed to State, Engineer, State’s Consultants and Architect, and all
trade contractors and suppliers.
6.2.17 Assisting the State in scheduling and planning for move in and fit up.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
6.2.18 Commissioning for all systems, including functional verification at startup. This process
shall include attendance by required factory representatives, testing equipment at all
required speeds, and the completion of necessary controls to allow safe and proper start-
up of equipment, and functional performance testing. After startup, this process is to
confirm that the individual pieces work together. Tests shall be performed on any moving
part including, but not limited to, all mechanical/HVAC systems, building automation
systems and controls, electrical equipment, devices, lighting and controls, plumbing and
piping systems, water transport and treatment systems; Architectural elements including
building envelope, doors and operating/moveable items, etc. See Commissioning
Specifications and BGS Design Guidelines at http://bgs.vermont.gov/facilities/forms for
more information. The CM shall be responsible for assisting with and coordination of all
subcontractors with the Commissioning Agent for observations, inspections,
documentation, verification, testing, and reporting.
6.2.19 Punch list and training for all systems, see Specifications and BGS Design Guidelines for
more information at http://bgs.vermont.gov/facilities/forms.
6.2.20 All warranty work, including coordinating any and all warranty work required by
subcontractors.
6.2.21 Warranty Inspection one month prior to expiration of one-year warranty.
6.3 CONSTRUCTION SERVICES FEE (Construction Manager’s Fee): The fee for the construction
phase of the project shall be a lump sum fixed fee developed using the scope of work indicated
herein, as well as the proposed project budget and schedule. For this purpose, the cost of
construction will include all competitively bid portions of the work, plus the fixed fee for General
Conditions established by this proposal. Construction services for Change Orders shall be included
in the overhead and mark-up percentage, included in this proposal. The fee for the construction
phase of the project shall include the following:
6.3.1 All direct contractor overhead not included in the general conditions.
6.3.2 All estimating.
6.3.3 All home office and data processing costs.
6.3.4 All indirect contractor overhead costs.
6.3.5 All unidentified contractor overhead costs.
6.3.6 All contractor profit.
6.4 GENERAL INFORMATION AND REQUIREMENTS:
6.4.1 The form of agreement will be the STATE OF VT CM CONTRACT between the State and
Construction Manager.
6.4.2 The General Conditions for the Contract will be the STATE OF VERMONT GENERAL
CONDITIONS FORM AND GENERAL CONDITIONS FOR CONSTRUCTION
CONTRACTS.
6.4.3 The State shall receive copies of all proposals, contracts, subcontracts and material price
proposals for the proposed GMP and material price proposals for which the CM has
estimated using their own forces.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
6.4.4 All cost savings will be returned to the State and any unused portion of any contingency or
allowance carried in the GMP will revert to the State once the project is complete. The
GMP shall include assumptions and clarifications, agreed upon by the CM and State.
6.4.5 Labor rates used in establishing the cost of the work shall not include any payroll
administrative costs, clerical costs, general administrative costs, or any costs other than
the actual wages paid plus Workers’ Compensation insurance costs, unemployment
insurance costs, payroll taxes, and employee benefits.
6.4.6 Vermont State Wage Rates documentation and reporting shall apply to this project. Proper
wage documentation and reports shall be forwarded to the appropriate State Departments
as required.
6.4.7 The cost of the work shall not include any supervisory costs or administrative labor cost.
Any supervisory costs or administrative labor costs are to be included in the fixed fee for
general conditions or the fee for the contractor CM services.
6.4.8 There shall be no reimbursable costs except costs specifically identified in this RFP. All
reimbursable costs shall be at cost with no additional mark up.
6.4.9 The State and the CM will have separate contingencies. Use of the CM’s contingency (in
the GMP) will only be with the approval of the State and will include proposed scope, costs
and reason for change, and shall be maintained in a log and reflected in a change order at
the end of the project. At the end of the project, any remaining CM contingency will be
returned to the State. Use of State’s contingency (not in the GMP) will be added via change
order.
6.4.10 At any time during the pre-construction phase, the State may terminate the agreement with
the CM without prejudice. In the event the State elects to terminate the agreement with
the CM, the CM shall provide copies of all records, bids, estimates, quotations, and other
pertinent material developed by the CM during the pre-construction phase. The State shall
pay the CM for the portion of the pre-construction services performed up to the point of
termination. Upon payment for the portion of the pre-construction services performed, the
CM shall have no further claims or rights under the executed agreement. Materials
provided by the CM, and paid for by the State, shall become the property of the State.
6.4.11 All invoices including, but not limited to, invoices for materials, labor, equipment rental, and
trade contracts used in establishing the cost of the work shall reflect all discounts and
rebates of which the CM was able to take advantage. In order to take advantage of quick
payment discounts, the State may be willing to make accommodations to meet specific
terms. The CM will keep the State appraised of potential discounts and savings. The CM
will be allowed to keep savings attributed to quick pay discounts unless the State is able to
provide payment in such circumstances in the required time frame.
6.4.12 The State shall be responsible for paying all fees associated with attaining the local and
state permits required for the project. Trade permits shall be the responsibility of the CM
or regulated trade.
6.4.13 Electronic Submittal Procedures will be used for the submittal process, RFIs, reports,
drawings and pay applications throughout the project. This account shall be used through
the design process and continue through closeout of the project.
6.4.13.1. The electronic submittal process shall not be used for color samples, color charts,
or physical material samples.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
6.4.14. SUBMITTAL EXCHANGE®: Submittal Exchange® (www.submitalexchange.com) shall be
used to provide an on-line database and repository, which shall be used to transmit and
track project-related documents. The intent for using this service is to expedite the
construction process by reducing paperwork, improving information flow, and decreasing
submittal review turnaround time.
6.4.14.1 Project submittals (shop drawing, product data and quality assurance submittals)
shall be transmitted by the Contractor in PDF to Submittal Exchange®, where it
will be tracked and stored for retrieval for review. After the submittal is reviewed
it shall be uploaded back to Submittal Exchange® for action and use by the
Contractor and Director’s Representatives.
6.4.14.2 The service also tracks and stores documents related to the project such as
Request for Information (RFI’s), Architect's Supplemental Instructions (ASI),
Information Bulletins (IB’s), CAD Coordination, Commission, Construction
Change Directive (CCD), Contractor’s Daily Reports, Minutes, Photos, Quality
Control, Shop Drawings, Testing, Closeout Documents including As-Built
Drawings, Operations and Maintenance Manuals and other project related
documents.
6.4.14.3 Training and support during this project will be provided by Submittal Exchange
at no additional cost to the selected contractor(s).
7. GENERAL REQUIREMENTS:
7.1 PRICING: Bidders must price the terms of this solicitation at their best pricing. Any and all costs
that Bidder wishes the State to consider must be submitted for consideration. If applicable, all
equipment pricing is to include F.O.B. delivery to the ordering facility. No request for extra delivery
cost will be honored. All equipment shall be delivered assembled, serviced, and ready for
immediate use, unless otherwise requested by the State.
7.1.1 Prices and/or rates shall remain firm for the initial term of the contract. The pricing policy
submitted by Bidder must (i) be clearly structured, accountable, and auditable and (ii) cover
the full spectrum of materials and/or services required.
7.1.2 Retainage. In the discretion of the State, a contract resulting from this RFP may provide
that the State withhold a percentage of the total amount payable for some or all
deliverables, such retainage to be payable upon satisfactory completion and State
acceptance in accordance with the terms and conditions of the contract.
7.1.2.1. The State shall withhold 10% retainage for all construction related invoices. At
Substantial Completion of the entire project, retainage may be reduced as agreed
upon by State, CM and Architect. There shall be no retainage withheld on Pre-
Construction services.
7.2 WORKER CLASSIFICATION COMPLIANCE REQUIREMENTS: In accordance with Section 32 of
The Vermont Recovery and Reinvestment Act of 2009 (Act No. 54), Bidders must comply with the
following provisions and requirements.
7.2.1 Self Reporting: For bid amounts exceeding $250,000.00, Bidder shall complete the
appropriate section in the attached Certificate of Compliance for purposes of self-reporting
information relating to past violations, convictions, suspensions, and any other information
related to past performance relative to coding and classification of workers. The State is
requiring information on any violations that occurred in the previous 12 months.
7.2.2 Subcontractor Reporting: For bid amounts exceeding $250,000.00, Bidders are hereby
notified that upon award of contract, and prior to contract execution, the State shall be
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
provided with a list of all proposed subcontractors and subcontractors’ subcontractors,
together with the identity of those subcontractors’ workers compensation insurance
providers, and additional required or requested information, as applicable, in accordance
with Section 32 of The Vermont Recovery and Reinvestment Act of 2009 (Act No. 54). This
requirement does not apply to subcontractors providing supplies only and no labor to the
overall contract or project. This list MUST be updated and provided to the State as
additional subcontractors are hired. A sample form is available online at
http://bgs.vermont.gov/purchasing-contracting/forms . The subcontractor reporting
form is not required to be submitted with the bid response.
7.3 METHOD OF AWARD: Awards will be made in the best interest of the State. All other
considerations being equal, preference will be given first to resident bidders of the state and/or
to products raised or manufactured in the state, and then to bidders who have practices that
promote clean energy and address climate change, as identified in the applicable Certificate of
Compliance.
7.3.1. The CM must structure their fees as outlined in the attached Project Cost Matrix.
Any variation in how the CM structures their fees may result in a disqualified bid.
Once a contract is awarded, changes in the way the fee is apportioned may be
considered by the State.
Option 1, Scoring:
7.3.2 Evaluation Criteria: The evaluation criteria for this project are:
7.3.2.1 Strength and Experience of the Construction Management Team
7.3.2.2 Process
7.3.2.3 Fee Structure (scored separately after evaluation of other criteria)
7.3.2.3.1 Fixed Fee for Pre-Construction Services
7.3.2.3.2 Fixed Fee for Construction Services (CM Fee)
7.3.2.3.3 Fixed Fee for General Conditions based on 21 months of construction.
7.3.2.3.4 Percent Markup for Overhead and Profit for changes in the work after the
GMP has been established.
7.3.2.3.5 Mark-up for Profit on Materials Purchased by the CM.
7.3.2.3.6 Hourly Rate for the Project Manager & Superintendent.
7.3.3 Proposal Content: Proposals should respond to each criterion, in the order listed,
in a well-organized manner.
7.3.3.1 Restrict information to that requested. Unorganized or excessive and irrelevant
information will impede review of your proposal and could adversely affect the
score for one or more criteria.
7.3.3.2 Non-responsive proposals will result in disqualification.
7.3.3.3 All questions must be answered.
7.3.4 CRITERION 1: Strength and Experience of the CM Team
7.3.4.1 Has the CM had at least five (5) years of experience with Construction
Management projects of this size and complexity? Include a list of projects that are
similar in size and complexity within the last five (5) years. List project costs, dates
of construction and delivery method (Construction Management, Design/Bid/Build,
and Design Build).
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
7.3.4.2 Does the CM have experience with similar facilities? Provide a specific list of those
projects, including cost and dates of construction.
7.3.4.3 Describe how the experience of the CM team members is appropriate for this
project.
7.3.4.3.1 Provide the name and resume of the Project Manager to be assigned to
the project, include a list of projects that he/she has worked on that are
similar in size, type of construction and complexity for the last five (5)
years with references, project costs, dates of construction and delivery
method (Construction Management, Design/Bid/Build, and Design Build).
7.3.4.3.2 Provide the name and resume of Supervisory personnel to be assigned
to the project, include a list of projects that he/she has worked on that are
similar in size, type of construction and complexity for the last five (5)
years with references, project costs, dates of construction and delivery
method (Construction Management, Design/Bid/Build, and Design Build).
7.3.4.3.3 Who will represent the CM in the office and the field? Provide resumes,
experience and references for key management.
7.3.4.3.4 Has the CM team worked together before on projects that are similar in
size and complexity? If so, provide a list of the projects and indicate the
team members on those projects, and the cost and years constructed.
7.3.5 CRITERION 2: Process
7.3.5.1 Provide an overview of the CM’s proposed approach to the project; include
anticipated challenges and proposed solutions.
7.3.5.2 Describe the CM’s cost control methods for the pre-construction and construction
phases.
7.3.5.3 Describe how the CM develops cost estimates, how often they are updated and
what degree of accuracy is achieved.
7.3.5.4 Provide an evaluation of the proposed schedule. Include in the CM’s evaluation the
Date of Commencement, Substantial Completion of each phase of the work, and
any other relevant milestones. Does the schedule present a challenge? Can the
duration be shortened? Are there other considerations related to the schedule?
7.3.6 CRITERION 3: Fee Structure
7.3.6.1 The Committee will compare the fees for the Pre-Construction fee, fixed CM fee,
fixed General Conditions, the percent markup for change orders, and the hourly
rates.
7.3.6.2 For the Committee to equitably compare the Construction fees for Services and
General Conditions, the CM must structure their fees as outlined in the attached
Project Cost Matrix.
7.3.6.2.1 Once a contract is awarded, changes in the way the fee is apportioned
may be considered by the State.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
7.3.6.3 Complete the attached “Hourly Rate Schedule”.
7.3.7 SCORING: The scoring by the Evaluation Committee members will be based on the
cumulative point score of the evaluation criteria assigned by the Evaluation Committee.
This score will be converted to an ordinal scoring system (majority rule). This contract
will be awarded to the firm receiving the majority of 1st place votes resulting from the
conversion, subject to the approval of the Commissioner of Buildings & General
Services.
7.3.8
CRITERIA WEIGHT MAXIMUM
POINTS
WEIGHTED
TOTAL
Strength and Experience of CM Team 3 10 30
Process 2 10 20
Fee Structure
Pre-Construction Fixed Fee 1 10 10
CM Fixed Fee 1 10 10
General Conditions Fixed Fee 1 10 10
Overhead & Profit on Change Orders 0.5 10 5
Mark-up for Profit on Materials Purchased
by the CM
0.5 10 5
Hourly Rate for the Project Manager &
Superintendent
1 10 10
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
PLEASE NOTE: The Project Cost Matrix must not be modified and shall be included with the Bid
Proposal.
Project Cost Matrix
Construction Management Services
State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
Description (As applicable to
project)
General Conditions
CM
Fee
Cost of
Work CommentsIncluded
in bid
To be
added at
GMP
General
Profit X
Corporate Officer's Salary &
Benefits X
Home Office Rent X
Home Office Autos & Travel X
Home Office Overhead X
Interest on Borrowed Capital X
Payroll/Bookkeeping/Clerical X
Project Management
Project Executive X
Project Manager X
Assistant Project Manager X
Project Engineer X
Estimator X
Scheduler X
Superintendent X
Assistant Superintendent X
MEP Engineer/Manager X
Field Engineers X
Accounting X
Safety Officer X
Administrative Support X
Purchasing X
Travel X
Lodging X
Temporary Housing X
Project Vehicles X
Surveying X
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
Project Cost Matrix
Construction Management Services
State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
Description (As applicable to
project)
General Conditions
CM
Fee
Cost of
Work CommentsIncluded
in bid
To be
added at
GMP
Shop Drawings X By subcontractor, processed by
CM
As-Built Drawings X By subcontractor, processed by
CM
O&M Manuals X By subcontractor, processed by
CM
Mobilization/Demobilization X
Safety Program X
Mock-ups X
Insurance/Bonding/Taxes/Permits
Builder's Risk Insurance X
General Liability Insurance X
Workers’ Compensation Insurance X Includes Management & Hourly
Workers
Performance Bond X
Payment Bond X
Warranty Bond X
Sales Tax (where applicable) X On rented equipment only
Trade Permits X
Temporary Services
Temporary Plumbing X
Temporary Power/Lighting X
Temporary Heat & Cooling
Equipment X
Temporary Fire Protection X
Temporary Fire Alarm X
Temporary Parking Area X
Dust & Noise Control X
Safety Procedures X
Temporary Heat Fuel X
Electric Power Compensation X
Winter Conditions X
Tool Rental X
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
Project Cost Matrix
Construction Management Services
State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
Description (As applicable to
project)
General Conditions
CM
Fee
Cost of
Work CommentsIncluded
in bid
To be
added at
GMP
Enclosures X
Storage Trailers X
Snow Removal X
Construction Fencing X
Staging Area/Access Roads X
Equipment Rentals X
Guardrail & Protection at Openings X
Barriers X
Watchman/Guard Services X
Police Details X
Lull X
Lifts X
Scaffolding X
Temporary Protection
General Protection & Safety -
Materials X
Protect Finished Work X
First Aid X
Fire Extinguishers X
Rubbish, Recycling & Clean-up
Trash Chutes X
Dumpsters & Tipping Fees X
Recycling Containers X
Street Cleaning X
Storm Drain Cleaning X
General Cleaning X
Final Cleaning X
Exterior Window Cleaning X
Field Office Expenses
Office Furniture & Computers X
Office Equipment X
Office Copier/Scanner/Facsimile X
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
Project Cost Matrix
Construction Management Services
State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
Description (As applicable to
project)
General Conditions
CM
Fee
Cost of
Work CommentsIncluded
in bid
To be
added at
GMP
Supplies X
Temporary Signage X
Telephone (hard wired/cellular) X
Postage, Messengers X
High Speed Wired & Wireless Data X
2-Way Radios X
Travel X
Progress Photos X
Miscellaneous General Expenses X
Sanitary Facilities X
Small Tools X
Tools & Consumables X
Office Trailer(s) – (CM, Meetings &
Subcontractors) X
Punch List X X In General Conditions unless
provided by subcontractor
Demonstration & Training X X In General Conditions unless
provided by subcontractor
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
7.4 STATEMENT OF RIGHTS: The State of Vermont reserves the right to obtain clarification or
additional information necessary to properly evaluate a proposal. Vendors may be asked to give a
verbal presentation of their proposal after submission. Failure of vendor to respond to a request for
additional information or clarification could result in rejection of that vendor's proposal. To secure a
project that is deemed to be in the best interest of the State, the State reserves the right to accept
or reject any and all bids, in whole or in part, with or without cause, and to waive technicalities in
submissions. The State also reserves the right to make purchases outside of the awarded contracts
where it is deemed in the best interest of the State.
7.5. CONFLICTS OF INTEREST:
7.5.1.Organizational Conflict of Interest (OCOI): An OCOI arises when a bidder as a business
entity has interests (for example, customers, partners, contracts) that could undermine, or
reasonably be perceived to undermine, its faithful and unbiased performance of a contract
with the State that may result from this solicitation.
7.5.2.Personal Conflict of Interest (PCOI): A PCOI arises when an interest held by an
individual, agent or employee of a bidder could undermine, or reasonably be perceived to
undermine, its faithful and unbiased performance of a contract with the State that may result
from this solicitation.
7.5.3.Requirements: The State does not seek to contract with any individual or business entity
having a conflict of interest which cannot be mitigated to the State’s satisfaction. To ensure
the State’s awareness of actual, potential, or reasonably perceived PCOIs and OCOIs,
bidders shall:
a) Prior to submitting a proposal, conduct an internal review of its current affiliations and
activities and identify actual, potential, or reasonably perceived PCOIs or OCOIs relative
to a contract with the State that may result from this solicitation.
b) Disclose in your proposal any actual or potential PCOI or OCOI or the existence of any
facts that may cause a reasonably prudent person to perceive a PCOI or OCOI with
respect to a contract with the State that may result from this solicitation. Disclose, also,
any actions proposed to mitigate the PCOI or OCOI.
7.5.4.The State shall have sole discretion to determine whether a PCOI or OCOI can be mitigated
to the State’s satisfaction and may discuss the conflict with the bidder if and to the extent
the State deems discussion necessary to its determination. The State reserves the right to
(a) reject from further consideration any proposal having a PCOI or OCIO that cannot be
mitigated to the State’s full satisfaction and (b) terminate a contract upon discovery that a
contractor failed to disclose facts pertaining to a PCOI or OCOI in its proposal, or otherwise
misrepresented relevant information to the State.
7.6 CONTRACT TERMS: The selected bidder(s) will be expected to sign a contract with the State,
including the Standard Contract Form and Attachment C as attached to this RFP for reference. The
contract will obligate the bidder to provide the services and/or products identified in its bid, at the
prices listed.
7.6.1 Business Registration: To be awarded a contract by the State of Vermont a vendor
(except an individual doing business in his/her own name) must be registered with the
Vermont Secretary of State’s office Vermont Secretary of State - Business Services
Division and must obtain a Contractor’s Business Account Number issued by the
Vermont Department of Taxes http://tax.vermont.gov/ .
7.6.2 The contract will obligate the bidder to provide the services and/or products identified in its
bid, at the prices listed.
CM Services: State House Pandemic Mitigation/Renovation Project
115 State Street, Montpelier, VT
RFP – CONSTRUCTION MANAGEMENT REV: 02/13/2026
7.6.3 Payment Terms: All invoices are to be rendered by the Contractor on the vendor's
standard billhead and forwarded directly to the institution or agency ordering materials or
services and shall specify the address to which payments will be sent. Payment terms are
Net 30 days from receipt of an error-free invoice with all applicable supporting
documentation. Percentage discounts may be offered for prompt payments of invoices;
however, such discounts must be in effect for a period of 30 days or more in order to be
considered in making awards.
7.6.4 Quality: If applicable, all p