SGR 2027 PLANT MIX - PRIMARY/SECONDARY
Virginia Department of Transportation 11/10/2026Date Printed:
Schedule of Items Page: 2
Proposal ID: CM427PMD130193 PM4D-026-27F, P401
Order No.: 419
Oversight/State Project No.:
Federal Project No.: PM04545
Contractor:
0001 REGULAR BID ITEMSSECTION:
Cat Alt Set ID: Cat Alt Mbr ID:
Bid AmountUnit Price
Approximate
Quantity and
UnitsDescription
Item ID
Proposal
Line
Number Dollars Cents Dollars Cents
Spec
No.
0010 303SD20-0001
REGULAR EXCAVATION CY
162.000
____. ____.
303
0020 305SP20-0003
AGR. BASE MAT. TY.I OR II
NO. 21A OR 21B
TON
2,520.250
____. ____.
ATTD
0030 310SD20-0001
TACK COAT GAL
52,659.000
____. ____.
310
0040 315SD20-0036
ASPH. CONC. TY. SM-12.5E
MAINT
TON
8,947.720
____. ____.
315
0050 315SD20-0043
ASPH. CONC. TY. IM-19.0D
MAINT
TON
121.000
____. ____.
315
0060 315SD20-0052
RUMBLE STRIP SINUSOIDAL
ASPHALT
LF
91,507.000
____. ____.
315
0070 315SD20-0100
ASPHALT CONCRETE BASE
COURSE BM-25.0
TON
420.000
____. ____.
315
0080 315SP20-0006
PAVEMENT SHOULDER
WEDGE PREP. CONST
LF
142,824.000
____. ____.
ATTD
0090 315SP20-0049
ASPH. CONC. BMD P+VO SM-
9.5D
TON
11,933.670
____. ____.
315
0100 315SP20-0051
ASPH. CONC.
State Project: PM4D-026-27F, P401
UPC: 130193
Federal Project: PM04545
Route: Various
County/City: Various
Engineer's estimate: $9,530,000.00
Let date: 12/16/2026
Begin: Various
Showing: No Showing
Time limit: 11/19/2027
Last date to post questions: 12/11/2026
Provide plant-mix asphalt including SM-12.5E, IM-19.0D, BM-25.0 base, BMD P+VO SM-9.5D and SM-12.5D mixes, travel lane patching, regular excavation, aggregate base material, tack coat, sinusoidal rumble strips, shoulder wedge preparation, demolition of pavement, flexible pavement planing, maintenance of traffic, flagger service, temporary and permanent Type B Class I pavement markings, inlaid markers, symbols and messages, and an alternate for select shoulder material.
We post new asphalt opportunities in Virginia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Virginia work asks for the two below, and the solicitation documents are where it’s stated. Apply straight through for it — or prequalify once and skip the application on both.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Virginia Department of Transportation (solicitation 419), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.