Issuing Procurement Unit: State of Utah Division of Purchasing
Conducting Procurement Unit: State of Utah Division of Oil, Gas and Mining
The purpose of this IFB is to enter into a contract to provide:coal refuse waste excavation and haul, channel construction, site grading and earthwork, runoff control, revegetation of disturbed areas, and road realignment and resurfacing at an abandoned coal refuse pile in Carbon County, Utah.
Engineer's Estimate: $6,522,959.00
Mandatory Site Visit: REQUIRED ATTENDANCE TO BID ON PROJECT:
Date/Time: Friday, November 13, 2026 at 10:00 AM
Location: Meet at the Price Field Office of the Division of Oil, Gas and Mining at 319 North
Carbonville, Road, Price, UT 84501. Bidders will then travel to other sites. (Vendors will meet in the front door waiting area, before being escorted back to a conference room.)
The meeting is expected to last approximately 4 hours. High-clearance four-wheel-drive vehicles are recommended. Due to the lack of parking space in Hardscrabble Canyon, carpooling is recommended.
This meeting is mandatory. Attendance is required to bid. Abandoned mine reclamation work is different from standard residential or commercial construction. It requires specialized work in unusual conditions and unique circumstances. Because of the special nature of this reclamation work, biddersare required to attend the pre-bid meeting. Bids from firms not on record as attending the entire meeting will be considered nonresponsive. Bidders should supplement the pre-bid meeting by examining the project on their own time.
It is anticipated that this IFB will result in a single contract award to the lowest cost responsive and responsible vendor who meets specifications and mandatory minimum requirements within the solicitation.
Length of Contract: The WORK under this CONTRACT shall be commenced upon notice to proceed and shall be completed within 84 calendar days after the date of email delivery, date of hand delivery, or date marked on registered mail receipt of said Notice to Proceed and no later than August 27th, 2027. WORK delays caused by weather may, at the discretion of
the OWNER, extend the completion date. CONTRACTOR also agrees to the liquidated damages provisions of Article 12.
Vendor must guarantee its pricing for the completion of the project.
We post new waste & recycling collection opportunities in Utah as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Utah work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what an agency asks to see before they take your bid seriously.
Source: State of Utah (Bonfire) (solicitation 261402), retrieved via the Utah Bonfire procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.