- South Dakota Department of Transportation - Bid Letting Information SDEBS Lettings Regional Lettings Bidding Information NEW Electronic Bidding Contractor Information Bid Letting Staff Error Message An error has occurred on the page you requested. Please contact the bid letting office at 605-773-3275 to report this error. Bid Letting Home Bid Letting Log In
- Pdf Text
- 4
DEPARTMENT OF TRANSPORTATION
NOTICE TO CONTRACTORS,
PROPOSAL, SPECIAL PROVISIONS,
CONTRACT AND CONTRACT BOND
FOR
STRUCTURE (101' STEEL GIRDER) REMOVAL
FEDERAL PROJECT NO. BRO-B 8052(78)
(PCN 09A5)
MUSEUM DRIVE
IN PENNINGTON COUNTYDecember 9, 2026
DEPARTMENT OF
TRANSPORTATION
NOTICE TO ALL BIDDERS
TO REPORT BID RIGGING ACTIVITIES, CALL: 1-800-424-9071
THE U.S. DEPARTMENT OF TRANSPORTATION (DOT) OPERATES THE ABOVE TOLL-
FREE “HOTLINE” MONDAY THROUGH FRIDAY, 8:00 A.M. TO 5:00 P.M., EASTERN TIME.
ANYONE WITH KNOWLEDGE OF POSSIBLE BID RIGGING, BIDDER COLLUSION, OR
OTHER FRAUDULENT ACTIVITIES SHOULD USE THE “HOTLINE” TO REPORT SUCH
ACTIVITIES.
THE “HOTLINE” IS PART OF THE DOT’S CONTINUING EFFORT TO IDENTIFY AND
INVESTIGATE HIGHWAY CONSTRUCTION CONTRACT FRAUD AND ABUSE AND IS
OPERATED UNDER THE DIRECTION OF THE DOT INSPECTOR GENERAL.
ALL INFORMATION WILL BE TREATED CONFIDENTIALLY, AND CALLER ANONYMITY
WILL BE RESPECTED.
* * * *
PLANS, PROPOSALS AND ADDENDA
AFTER AWARD OF CONTRACT, THE LOW BIDDER WILL RECEIVE TEN (10)
COMPLIMENTARY SETS OF PLANS, PROPOSALS, PROJECT Q & A FORUM, AND
ADDENDA FOR FIELD AND OFFICE USE. AN ELECTRONIC COPY WILL ALSO BE
PROVIDED. ANY ADDITIONAL COPIES REQUIRED WILL BE THE RESPONSIBILITY OF THE
CONTRACTOR.
* * * *
Project Number: BRO-B 8052(78) Revised 10/8/25
PCN 09A5
NOTICE TO CONTRACTORS
Bid proposals for this project will be prepared, transmitted, and received electronically by the
South Dakota Department of Transportation (SDDOT) via the South Dakota Electronic Bid
System until 10 A.M. Central time, on December 9, 2026, at which time the SDDOT will open
bids. All bids will be checked for qualifications with results posted on the SDDOT website. The
South Dakota Transportation Commission will consider all bids at a scheduled Commission
meeting.
The work for which proposals are hereby requested is to be completed within the following
requirement(s):
FIELD WORK COMPLETION: April 30, 2027
The project category is Category II
The project type is Grading
The geographic zone is Zone 3
THE DBE GOAL FOR THIS PROJECT IS: N/A
WORK TYPE FOR THIS PROJECT IS: WORK TYPE 7 OR WORK TYPE 8 OR WORK TYPE
9 OR WORK TYPE 13
Bidding package for the work may be obtained at:
http://apps.sd.gov/hc65bidletting/ebslettings1.aspx#no-back-button
The South Dakota Standard Specifications for Roads and Bridges, 10-7-26 Version, may be
obtained at https://dot.sd.gov/doing-business/contractors/standard-specifications/ .
The electronic bid proposal must be submitted by a valid bidder as designated by their
company’s https://apps.sd.gov/HC65C2C/EBS/BidAdminAuthorizationForm.pdf. A bidding
administrator will have privileges in the SDEBS to prepare bids, submit bids, and authorize
additional company employees to prepare and submit bids. Additionally, a bidding
administrator will be responsible for maintaining the list of authorized bidders for the company
and will have the ability to add employees, remove employees, and set-up bidder
identifications and passwords within the SDEBS. Bidding Administrator authorization will
remain in full force and effect until written notice of termination of this authorization is sent by
an Officer of the company and received by the Department.
A bidder identification and password, coupled with a company identification previously
assigned by the Department, will serve as authentication that an individual is a valid bidder for
the company.
Contact information to schedule a preconstruction meeting prior to commencing with the work
on this project.
Bruce Schroeder
PO Box 431
Custer, SD 57730-0431
Phone: 605/673-4948
PROPOSAL Revised 8/10/11
SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION, STATE OF SOUTH DAKOTA:
Ladies / Gentlemen:
The following proposal is made on behalf of the undersigned and no others. It is in all respects
fair and is made without collusion on the part of any other person, firm or corporation not
appearing in the signature to this proposal.
The undersigned certifies that she / he has carefully examined the plans listed herein, the
Specifications hereinbefore referred to, the Special Provisions and the form of contract, both of
which are attached hereto. The undersigned further certifies that she / he has personally
inspected the actual location of the work, together with the local sources of supply and that she /
he understands the conditions under which the work is to be performed, or, that if she / he has
not so inspected the actual location of the work, that she / he waives all right to plea any
misunderstanding regarding the location of the work or the conditions peculiar to the same.
On the basis of the plans, Specifications, Special Provisions and form of contract proposed for
use, the undersigned proposes to furnish all necessary machinery, tools, apparatus and other
means of construction, to do all the work and furnish all the materials in the manner specified, to
finish the entire project within the contract time specified and to accept as full compensation
therefore the amount of the summation of the products of the actual quantities, as finally
determined, multiplied by the unit prices bid.
The undersigned understands that the quantities as shown in the Bid Schedule are subject to
increase or decrease, and hereby proposes to perform all quantities of work, as increased or
decreased, in accordance with the provisions of the specifications, and subject to any applicable
special provisions, and at the unit prices bid.
The undersigned understands that the "Total or Gross Amount Bid" as immediately hereinbefore
set forth is not the final amount which will be paid if this proposal is accepted and the work done,
but that such amount is computed for the purpose of comparison of the bids submitted and the
determination of the amount of the performance bond.
The undersigned further proposes to perform all extra work that may be required on the basis
provided in the specifications, and to give such work personal attention in order to see that it is
economically performed.
The undersigned further proposes to both execute the contract agreement and to furnish a
satisfactory performance bond, in accordance with the terms of the specifications, within twenty
(20) calendar days after the date of Notice of Award from the South Dakota Department of
Transportation that this proposal has been accepted.
CERTIFICATION REGARDING LOBBYING
I certify, to the best of my knowledge and belief, that: No Federal appropriated funds have
been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or
attempting to influence an officer or employee of any agency, a member of Congress, an
officer or employee of Congress, or an employee of a member of Congress in connection with
the awarding of any Federal contract, the making of any Federal grant, the making of any
Federal loan, the entering into of any cooperative agreement, and the extension, continuation,
renewal, amendment, or modification of a Federal contract, grant, loan, or cooperative
agreement. If any funds other than Federal appropriated funds have been paid or will be paid
to any of the above mentioned parties, the undersigned shall complete and submit Standard
Form LLL, “Disclosure Form to Report Lobbying,” in accordance with its instructions.
The undersigned shall require that the language of this certification be included in the award
documents for all subawards at all tiers (including subcontracts, subgrants, and contracts
under grants, loans, and cooperative agreements) and that all subrecipients shall certify and
disclose accordingly. This certification is a material representation of fact upon which reliance
was placed when this transaction was made or entered into. Submission of this certification is
a prerequisite for making or entering into this transaction imposed by section 1352, title 31,
U.S. Code. Any person who fails to file the required certification shall be subject to a civil
penalty or not less than $10,000 and not more than $100,000 for each such failure.
REV 11/2/26
INDEX OF SPECIAL PROVISIONS
PROJECT NUMBER(S): BRO-B 8052(78) PCN: 09A5
TYPE OF WORK: STRUCTURE (101' STEEL GIRDER) REMOVAL
COUNTY: PENNINGTON
The following clauses have been prepared subsequent to the Standard Specifications for Roads
and Bridges and refer only to the above described improvement, for which the following
Proposal is made.
The Contractor’s attention is directed to the need for securing from the Department of
Environment & Natural Resources, Foss Building, Pierre, South Dakota, permission to remove
water from public sources (lakes, rivers, streams, etc.). The Contractor should make his request
as early as possible after receiving his contract, and insofar as possible at least 30 days prior to
the date that the water is to be used.
Kara Palmer is the official in charge of the Hot Springs Career Center for Pennington County.
THE FOLLOWING ITEMS ARE INCLUDED IN THIS PROPOSAL FORM:
Special Provision for Contractor Staking, dated 11/6/26.
Special Provision for Fire Plan, dated 3/11/25.
Special Provision for Submission of Bid Proposals (SDEBS Lettings), dated 10/29/26. Special
Provision for Aggregates for Granular Bases and Surfacing, dated 10/26/26.
Special Provision for Acknowledgment and Certification Regarding Article 3, Section 12 of the
South Dakota Constitution, dated 8/24/23.
Fuel Adjustment Affidavit, DOT form 208 dated 11/25.
Standard Title VI Assurance, dated 3/1/16.
Special Provision for Equal Employment Opportunity Requirements for Highway Construction
Contracts, dated 10/7/26.
Special Provision for Contract Provisions for Federal-Aid Construction Contracts, Form
FHWA 1273 (Rev. June 25, 2026), dated 10/7/26.
Contract Provisions for Federal-Aid Construction Contracts, Form FHWA 1273 (Rev. 6/25/26).
Special Provision Regarding Minimum Wage on Federal-Aid Projects, dated 10/24/19.
Wage and Hour Division US Department of Labor Washington DC. - US Dept. of Labor
Decision
Number SD20260001, dated 1/30/26.
Special Provision Regarding Stormwater Discharges to Waters of the State, dated 11/5/25.
General Permit Authorizing Stormwater Discharges Associated with Construction
Activities, dated 11/1/23.
https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/stormwater/StormWater
Construction.aspx
32018166.docx 1
STATE OF SOUTH DAKOTA
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
CONTRACTOR STAKING
PROJECT BRO-B 8052(78), PCN 09A5
PENNINGTON COUNTY
NOVEMBER 6, 2026
Delete Section 5.8 of the specifications and insert the following:
SECTION 5.8
CONSTRUCTION STAKES, LINES AND GRADES
CONTRACTOR GRADE STAKING
A. DESCRIPTION
The Contractor will perform all construction staking. The staking work includes, but
is not limited to, establishing or re-establishing the project centerline; establishing
control points and benchmarks as needed; setting additional benchmarks as
needed; taking original and final cross sections of all Contractor secured borrow
sources and State designated borrow sources; taking cross sections of all topsoil
stockpiles; and staking right-of-way, easements, and fence.
The Contractor will perform all construction layout and reference staking necessary
for the accurate control and completion of all grading, paving, drainage, median
crossovers, signing, pavement marking, permanent benchmarks, detours, fence,
and all other appurtenances required for the complete construction and
acceptance of the work. The layout will include, but is not limited to, staking
easement line, staking clearing line, slope staking and slope stake reference hubs,
grade staking (blue tops), and performing the miscellaneous staking as described
in the plans and in this specification.
Horizontal and vertical control has been established as shown on the plans. Each
horizontal and vertical control point will be preserved or reset out of the work limits
and available during and after construction is complete. Prior to the Department’s
final acceptance of the project, the Contractor will replace or reset any control that
is disturbed during the construction of the project. The Contractor will provide the
Department a list of the in-place control points, including coordinates and
elevations relevant to the project control, at the end of the project.
32018166.docx 2
The Contractor will perform the staking work in accordance with the Department’s
Survey Manual, except as modified by this specification.
B. MATERIALS
The Contractor will furnish all staking materials of adequate quality for the purpose
intended including all stakes, stake chasers, paint, field note books, and all other
materials and equipment necessary to perform the required work.
C. CONSTRUCTION REQUIREMENTS
1. General: The Contractor will perform all staking work under the supervision of
a qualified surveyor or engineer who is experienced and competent in road and
bridge construction surveying and staking. The surveyor or engineer will be
available to review work, resolve problems, and make decisions in a timely
manner. A crew chief, competent to perform all required surveying duties, will
supervise the staking in the absence of the surveyor or engineer from the
project. The Contractor will submit the qualifications and work experience
history of the surveyor or engineer who will supervise the construction survey
work to the Engineer for review at least 14 calendar days prior to beginning the
staking work.
The Contractor will also submit the proposed starting date of the staking and
the anticipated surveying work schedule.
The Contractor will furnish, set, and properly reference all stakes, references,
lines, grades, and batter boards required. Minimum reference notations will be
for type, location, and alignment (when there are multiple alignments in the
same area). The Contractor will perform the survey and staking work in a
manner consistent with standard engineering practices and approved by the
Engineer.
The Contractor is solely responsible for the accuracy of the survey and staking
work. The Contractor will notify the Engineer of any errors and discrepancies
found in previous surveys, plans, specifications, or special provisions prior to
proceeding with the survey work.
The Contractor will be responsible for the supervision of the construction
staking personnel. The Contractor will correct any deficient survey or staking
work that results in construction errors at no additional cost to the Department.
The Contractor will keep field notes in conventional handwritten notebooks or
in a computerized form acceptable to the Engineer in a clear, orderly, and neat
manner. The notebooks will become the property of the Department upon
completion of the project. The notebooks will provide enough information such
32018166.docx 3
that quantity measurements are verifiable by the Department. Field notes are
subject to inspection by the Engineer at any time.
The Contractor is required to submit any remaining required quantity
calculations and notes to the Engineer no later than 60 calendar days after
completion of the survey and staking work.
The Department will set reference control points. The Contractor is responsible
for the preservation of ties and references to all control points necessary for the
accurate re-establishment of all base lines and centerlines shown in the plans,
whether established by the Contractor or found on or adjacent to the project.
The Department will also establish benchmark elevations. It is the responsibility
of the Contractor to verify the accuracy of the benchmark elevations prior to
use on the project.
The Contractor will furnish stakes and wooden hubs or steel pins of sufficient
length to provide a solid set in the ground. The Contractor will place half-length
lath stakes or stake chasers or an alternate, acceptable to the Engineer,
adjacent to or on the blue top hubs for guards. Stakes set not meeting these
requirements will be reset at the Contractors expense. The Contractor will
replace stakes damaged, destroyed, illegible, or made unusable at no
additional expense to the Department.
The Engineer may check the accuracy and control of the Contractor's survey
and staking work at any time. The checks performed by the Engineer will not
relieve the Contractor of the responsibility for the accuracy of the survey layout
or the construction work. If the random checks show the grade is out of
tolerance, the Engineer may require the Contractor to set additional stakes at
the discretion of the Engineer, at no additional cost to the Department. If the
Engineer orders additional stakes, the Contractor will perform the additional
staking until the Contractor can show the staking operations achieve the
specified grade tolerances.
Prior to any project staking, the Contractor will run a level circuit to check the
plan benchmarks the full length of the project.
2. Slope Staking: The Contractor will set slope stakes at the catch points. The
slope stake reference hubs will be offset behind the slope stake. The Contractor
will place slope stake reference hubs behind the slope stakes at the right-of-
way line, easement line, or other locations as approved by the Engineer.
The slope stakes will be set at 200-foot intervals on tangents and at 50-foot
intervals in horizontal curves. The horizontal tolerance is 0.2 foot and the
vertical tolerance is 0.1 foot. The Contractor will reference the subgrade
shoulders with slope stake reference hubs set with a horizontal tolerance of
0.2 foot and a vertical tolerance of 0.05 foot.
32018166.docx 4
The Contractor will retain the slope stakes and hub references until the final
cross sections are completed and accepted by the Department.
The Department will not provide slope stake notes. The Contractor is
responsible to generate the slope staking notes using the cross sections and
the existing field conditions.
3. Grade Staking: The Contractor will set grade finishing stakes (blue tops) for
grade elevations and horizontal alignment on the roadway centerline and at
each shoulder at the top of the subgrade. Where additional lanes or turnouts
are to be constructed, the Contractor will set blue tops at centerline, the normal
shoulder distance, and the extended shoulder distance or outside the additional
lane edge.
The transverse distance between blue tops will not exceed 20 feet. The
Contractor will be required to set intermediate blue tops when the transverse
distance is greater than 20 feet. When intermediate blue tops are required, the
Contractor will set the intermediate blue tops at locations approved by the
Engineer.
The blue top grade stakes will be set at 100-foot intervals on tangents and 50-
foot intervals on horizontal curves. The horizontal tolerance for blue tops is ±0.2
foot and the vertical tolerance is ±0.02 foot.
The Contractor will retain the shoulder blue tops and guards through placement
of the granular material.
The Department will not provide grade stake notes. The Contractor is
responsible to generate the grade staking notes using the typical sections and
the existing field conditions.
4. Miscellaneous Staking: Miscellaneous staking includes the following work:
a. Easement line for items including, but not limited to, setting temporary
fence, utility relocation, and landowner reference and property use;
b. Clearing line for items identified by the clearing contract unit item when
provided in the plans;
c. Approach road staking and all tie-in checks. The Contractor will submit
profiles and elevations of all approach roads and other tie-ins throughout
the project to the Engineer at least 3 business days prior to staking;
d. Topsoil measurement and computation of quantities;
e. Special ditch staking;
f. Staking of signs, delineators, pavement markings, rumble strips/stripes,
guardrail, curb & gutter, light poles, conduit, mailboxes, junction boxes, and
32018166.docx 5
related items (Staking is for all aspects, i.e. detours, temporary and
permanent);
g. Right-of-way staking including fence post panels;
h. Pipe and storm sewer staking including drop inlets, manholes, cattle
passes, and related items. If additional pipe, storm sewer, drop inlets,
manholes, or cattle passes are required which are not shown on the plans,
the staking will be paid for at the contract unit price per hour for Engineer
Directed Surveying/Staking;
i. Mark limits of removal items (trees, foundations, curb & gutter, sidewalk,
etc.);
j. Detours, roadway diversions, and crossovers. (This work includes all design
and staking notes required to design and stake the detour, roadway
diversion, or crossover in accordance with the plan requirements. The
Contractor will submit the completed design including profile and alignment
and staking notes to the Engineer at least 3 business days prior to staking.);
k. Final and original cross sections of Contractor and State furnished borrow
pits and computations. The Contractor will perform earthwork computations
by the average end area method, surface-to-surface method, or alternate
computation method approved by the Engineer;
l. Resetting horizontal and vertical control, if disturbed;
m. Approach slab and sleeper slab staking;
n. Staking of sidewalks and curb ramps; and,
o. Staking of steps and wheel chair ramps.
The Contractor will perform the pipe staking so the pipe will fit the field
conditions. The plans show only approximate pipe locations and grades. The
Contractor will not install pipe prior to gaining the Engineer’s approval of minor
location and grade adjustments necessary for proper staking of the pipe.
The Contractor will stake the slope catch points to determine the inlet and outlet
locations, set reference stakes for the inlet and outlet locations, and stake
ditches and special inlet and outlet grades to ensure proper drainage. The
staking of manholes and drop inlets will be included in pipe and storm sewer
staking. The Contractor will stake precast cattle passes similar to drainage
pipes.
The horizontal tolerance for the pipe and storm sewer staking is 0.05 foot and
the vertical tolerance is 0.03 foot.
The Contractor will keep pipe staking notes on a DOT Form 214.
5. Engineer Directed Surveying/Staking: The use of the engineer directed
surveying/staking contract item is intended for surveying/staking not included
in the plan notes and this special provision. The Contractor may use a survey
crew to perform additional survey/staking work caused or required by the
Department. The Engineer will use a written order to authorize the hourly
32018166.docx 6
engineer directed surveying/staking item and describe the surveying/staking
work required of the Contractor.
D. METHOD OF MEASUREMENT
Refer to the Table of Contractor Staking in the plans for more detail on how
quantities were calculated.
1. Slope Staking: The Department will not measure slope staking. The
Department will pay the plan quantity as the final quantity unless the Engineer
orders additional slope staking in writing.
The Department will consider all combinations of roadway widths as one set of
slope stakes. On projects with ramps, the Department will consider ramps as
roadway and include the ramps in the slope staking quantity. All additional
slope staking for intersections will be incidental to the contract unit price for
slope staking.
2. Grade Staking: The Department will not measure grade staking. The
Department will pay the plan quantity as the final quantity unless the Engineer
orders additional grade staking in writing.
The Department will consider a two-lane roadway as one set of grade stakes.
The Department will proportionately increase the plan quantity for multi-lane
roadways in excess to two-lanes as shown in the table of construction staking
(lane factor). For example, a three-lane roadway is equivalent to 1.5 times the
quantity for a two-lane roadway. On projects requiring grade staking on ramps,
the Department will consider ramps as a two-lane roadway for measurement
as shown in the table of construction staking. The Department will not consider
Acceleration/deceleration lanes and turning lanes for intersecting roads, and
median crossovers as an additional roadway.
3. Miscellaneous Staking: The Department will not measure miscellaneous
staking. The Department will pay the plan quantity as the final quantity.
4. Engineer Directed Surveying/Staking: The Department will measure
engineer directed surveying/staking to the nearest 0.1 hour with the following
restrictions:
The use of engineer directed surveying/staking will be for the work ordered by
the Engineer. The measured quantity will be the actual time the survey crew is
working on the project, physically performing the field survey/staking work and
office time dedicated to the work specific to engineer directed
surveying/staking. The Department will not include travel time for the survey
crew in the measurement.
32018166.docx 7
The Contractor will provide the Engineer documentation, such as an invoice,
showing the actual days/hours worked.
E. BASIS OF PAYMENT
Payment for all of the survey items will be considered full compensation for
furnishing all necessary personnel, vehicles, surveying equipment, supplies,
materials, recording fees, transportation, and incidentals to accurately and
satisfactory complete the work.
The Department reserves the right to omit any of these bid items without providing
compensation to the contractor if the Department deems the bid prices are
unreasonable.
1. Slope Staking: The Department will pay slope staking at the contract unit price
per mile.
2. Grade Staking: The Department will pay grade staking at the contract unit
price per mile. All cost for additional grade staking for acceleration/deceleration
lanes, turning lanes, intersecting roads, grade adjustments, and median
crossovers will be incidental to the contract unit price for grade staking. All
additional grade staking for intersections and medians will be incidental to the
roadway grade staking. Any additional staking the Contractor feels necessary
to complete the grade staking work is the responsibility of the contractor and
will be incidental to the contract unit price for grade staking.
3. Miscellaneous Staking: The Department will pay miscellaneous staking at the
contract unit price per mile.
The Department will make partial payment as follows:
a. Upon submission of the name, experience, and qualifications of the
surveyor or engineer who will supervise the staking, the proposed starting
date, and the staking schedule, the Department will pay the Contractor 25
percent of the plan quantity for the miscellaneous staking.
b. The Department will make intermediate payments based on the amount of
the staking work completed.
c. The Department will make full payment at the plan quantity for
miscellaneous staking upon completion of all surveying and staking and
when the Contractor has furnished all field notebooks and records to the
Engineer.
The Department will not adjust the contract unit price or plan quantity for
miscellaneous staking due to overruns or under runs in the other contract items.
32018166.docx 8
4. Engineer Directed Surveying/Staking: The Department will pay engineer
directed surveying/staking on an hourly basis as per the Price Schedule for
Miscellaneous Items. The value listed in the Price Schedule for Miscellaneous
Items includes salaries, travel time, equipment, staking supplies, payroll
additive, and all incidental expenses related to providing the survey crew.
* * * * *
Revised March 11, 2025 2
TABLE OF CONTENTS
I. Responsibilities....................................................................................................................... 3
A. Contractor ........................................................................................................................ 3
B. Forest Service District Ranger or Delegated Fire Staff ..................................................... 3
II. Tools and Equipment ............................................................................................................. 4
A. Required Tools.................................................................................................................. 4
B. Available Equipment ........................................................................................................ 4
III. Personnel ............................................................................................................................. 4
IV. General Provisions .............................................................................................................. 4
A. Fire Prevention ................................................................................................................. 4
B. Fire Suppression ............................................................................................................... 6
C. Payment ........................................................................................................................... 7
D. Black Hills Fire Protection District .................................................................................... 7
1. PROHIBITIONS:.............................................................................................................. 7
2. EXEMPTIONS:................................................................................................................ 8
E. Stage 2 Fire Restrictions ................................................................................................... 8
1. PROHIBITIONS:.............................................................................................................. 8
2. EXEMPTIONS:................................................................................................................ 8
F. Duration of this Plan ............................................................................................................ 9
V. Exhibits
A. Exhibit A……………………………………………………………………………………………………………………….10
B. Exhibit B……………………………………………………………………………………………………………………….11
Revised March 11, 2025 3
BLACK HILLS NATIONAL FOREST
This plan outlines the channels of responsibility for fire prevention and suppression activities
and sets up an attack procedure in the event of a fire within the Project Area. The Project Area
is defined as that area within the National Forest and within ½ mile of the project right-of-way
work areas and all roads used for construction purposes.
I. Responsibilities
1. Contractor
1. Will cooperate with the District Ranger and/or Fire Management Officer in
preparation of a fire plan, by furnishing necessary information on personnel,
equipment and organization.
2. Is responsible for and will direct all fire suppression activities within the project area
until relieved by a Forest Service Representative or a South Dakota Wildland Fire
Division Representative.
3. Will make certain that prevention and suppression actions are in accord with
contract requirements, including the fire plan.
4. Will immediately notify authorities if a fire occurs. The following telephone numbers
will be used.
911
Great Plains Dispatch Center – 605-399-3160
5. Will delegate the second person in authority on the job to be responsible for the
above activities when he or she is not on the project.
2. Forest Service District Ranger or Delegated Fire Staff
1. Is responsible for all fire prevention & suppression activities on the Ranger District in
which the project is located.
2. Will review the standard fire plan for adequacy and after discussing any need for
changes with the Area Engineer, will add any specific provisions needed for the
project.
3. At least once on each project will accompany the Area Engineer on an inspection of
compliance with the project fire requirements. The Area Engineer will notify the
Revised March 11, 2025 4
Contractor of corrective measures which must be taken when fire requirements are
not being observed.
II. Tools and Equipment
1. Required Tools
1. The Contractor will furnish and maintain in a serviceable condition; one shovel,
McLeod, or Pulaski for each of his employees; to be used only for suppressing
wildland fires. These tools will be kept in sealed boxes and available within the
immediate working area.
2. The Contractor will furnish one shovel and one fully charged fire extinguisher UL rate
at 4 B:C or more on each truck, personal vehicle, tractor, grader, or other heavy
equipment. For each welder he/she will furnish one shovel and one backpack five-
gallon water-filled tank with pump; for each gasoline power tool, including but not
limited to chain saws, soil augers, rock drills, etc. one shovel or one chemical
pressurized fire extinguisher, fully charged. The required fire tools shall, at no time,
be farther than 25 feet from the point of operation of the power tool. Contractor
will also furnish any other equipment called for elsewhere in the contract.
a. Shovels will be size “O” or larger and will be not less than 35 inches in length.
All fire tools and equipment required to be furnished by the Contractor will always
be in good working condition.
2. Available Equipment
1. Prior to the beginning of the contract, the Contractor will furnish a list of equipment
used on the project to the District Ranger. The established list will be attached to and
become a part of the fire plan.
III. Personnel
The Contractor will furnish a list of supervisory personnel, and amount of workers available
on the project to the District Ranger or Delegated Fire Staff. Such a list will be attached to
and become a part of the fire plan. Changes in supervisory personnel and amount of
personnel will be reflected in amendment to the list.
IV. General Provisions
1. Fire Prevention
Revised March 11, 2025 5
1. The “Current Fire Danger” links are posted on the Great Plains Interagency
Dispatch Center website:
https://gacc.nifc.gov/rmcc/dispatch_centers/r2gpc/fuels.htm.
The Department of Transportation and/or Contractor will monitor the Fire Danger
as appropriate. When the Fire Danger Rating is “Very High” or “Extreme”, the
following actions will be taken:
If the Fire Danger Rating reaches “Very High,” the following conditions will prevail:
a. Falling of dead trees or snags will be discontinued.
b. No open burning will be permitted; fires will be extinguished.
c. Welding will discontinue except in an enclosed building or within an area
cleared of flammable material for a radius of 15 feet.
d. Blasting will be discontinued.
e. Smoking will be permitted only in automobiles and cabs of trucks equipped
with an ashtray or in cleared areas immediately surrounded by a fire break,
unless prohibited by other authority.
f. Vehicular travel will be restricted to cleared areas except in case of
emergency.
If the Fire Danger Rating reaches “Extreme,” the following precautions will be
taken in addition to the conditions specified above:
a. Work of a nature which could start a fire will require that properly equipped
fire guards be assigned to such an operation for the duration of the work and
patrol the area of construction while work is being done and for at least one-
half hour after shutdown of the work.
b. Smoking will be permitted only in automobiles and truck cabs equipped with
an ashtray, unless prohibited by other authority.
2. Burning, blasting, or welding. Advance approval in writing will be required and will
contain special stipulations pertinent to the particular job. The District Ranger
may give, in writing, seasonal approval with stipulations for blasting and/or
welding. Permission to blast with fuse or caps will require special written
permission. Use of detonating cord will not be allowed in clearing operations.
Explosives will be stored in a locked box marked “EXPLOSIVES” at all times. All
federal, State, and local laws concerning the use and storage of explosives will be
complied with. All flammable material will be cleared for a distance of 15 feet
around any welding operation.
3. Spark arrestors. All gasoline and diesel-powered equipment used in the
performance of the work will be equipped with a spark arrester qualified and rated
under the USDA Forest Service unless it is:
Revised March 11, 2025 6
a. Equipped with a turbine-driven exhaust supercharger, such as the
turbocharger. There will be no exhaust bypass.
b. A passenger carrying vehicle or light truck, or medium truck up to 40,000
GVW, used only on roads and equipped with a factory designed muffler
complete with baffles and an exhaust system in good working condition.
c. A truck or a piece of highway surfacing equipment used only on roads and
equipped with a factory designed muffler having a vertical stack exhaust
system extending above the equipment.
The exhaust equipment described above, including spark arrestors and
mufflers, will be properly installed and constantly maintained in serviceable
condition.
4. Power saws. Each gasoline power saw will be provided with a spark screen and a
muffler in good condition. Spill-proof metal safety cans will be used for refueling.
5. Storage and parking areas. Batch plant areas, equipment service areas, parking
areas, gas and oil drum storage areas, and explosive storage areas will be cleared
of all inflammable material for a distance of 50 feet. Small stationary engine sites
will be cleared of all flammable material for a distance of 15 feet. Flammable and
explosive storage areas will be labeled as such, and “No Smoking” signs erected.
6. Oil filters, cartridges, oil rags. Used and discarded oil filters, cartridges, and oil rags
or waste will be removed from the project and disposed of in accordance will all
applicable Federal, State and Local laws.
2. Fire Suppression
1. Contractor shall, both independently and in cooperation with the Forest Service
and/or the SD Division of Wildland Fire, take all reasonable and practicable action
to prevent and suppress fires resulting from Contractor operations and to suppress
any wildfire in the project area.
2. In line with this agreement personnel will be supplied from project crews to fight
fires on the project area up to the total number of personnel employed by the
Contractor and/or his subcontractors as they are needed by the incident
commander. The Forest Service will make every effort to avoid calling on the
Contractor for action on fires outside the project area except for emergencies.
The Incident Commander may call out all needed available help to control fires on
the project area.
Revised March 11, 2025 7
3. Payment
1. South Dakota Department of Transportation
Will require its contractors to be responsible for suppression costs together with
damages for all fires started as a result of the project operations or contractors on
the project or employees of said contractor.
2. The Forest Service
Will pay Contractor personnel firefighting and equipment as well as equipment
operator’s wages used for fire suppressions work on fires not a result of the
project operation or its personnel at Forest Service Equipment Use Rates as
established annually or other use rates may be negotiated in advance as required.
3. Contractor
Will pay for all costs of fires resulting from the project operations.
4. Black Hills Fire Protection District
The Black Hills National Forest has a very volatile wildfire profile due to the ponderosa pine
fuel type and unique weather phenomena thus fire prevention is of upmost importance.
Illegal fires are often built by individuals and then attended by large groups. Upon finding
illegal fire attended by large groups officers have difficulty finding the person(s) who started
the illegal fire. Having the ability to hold everyone attending the fire accountable allows
officers to effectively deal with the illegal fire. Further, this regulation will also allow Forest
Officers to enforce fire prevention regulations established by the State of South Dakota.
The Forest Order pertaining to the Black Hills Fire Protection District in essence, places
Stage I Fire Restrictions year-round. To ensure the p
- Enriched
- Yes
- Pdf Pages
- 70
- Work Desc
- Structure Removal
- Work Type
- Work Type 7 or Work Type 8 or Work Type 9 or Work Type 13
- Addendums
- 0
- Project No
- BRO-B 8052(78)
- Questions
- 0
- List Url Hint
- hc65bidletting/ebslettings1.aspx
- Letting Label
- December 9, 2026
- Categorized By
- llm