The University of South Carolina is seeking quotes for removal and replacement of existing wall panels and sealant installation at 8000 Valley Falls Rd., Spartanburg, SC.
Quotes are due by October 20, 2026 at 3:00 PM, with an estimated construction cost range of $45,000.00 - $65,000.00.
The project is classified as Minor Construction ($10K-$100K) and quotes must be emailed to mbriscoe@mailbox.sc.edu.
The contact person is Marvin Briscoe, telephone 803-777-4115.
The solicitation requires a Prime Contractor License with Special Standard of Responsibility: BD1, NR1.
Requirement: Prime Contractor License (Special Standard of Responsibility): BD1, NR1.
Licence
Prime Contractor License (Special Standard of…
Est. value
$45,000.00 -…
Documents
1 file
These takeaways are AI-generated and may be incomplete or wrong. Always verify every detail against the official documents before you bid.
Want to know if you can be bonded for this project? Get prequalified.Estimated at $65K — that’s Propeller’s credit tier (up to $3M). One free application, soft pull.
Know you can be bonded before you spend a week on the bid
No scramble for a bond at the deadline — it becomes a request form
Remove and replace existing wall panels as indicated on the drawings.
Install sealant in laps of new wall panels and where they overlap onto existing wall panels.
Perform all associated detail work for walls.
Email quotes to mbriscoe@mailbox.sc.edu.
Requirements
From the documents
Licence
Prime Contractor License (Special Standard of Responsibility): BD1, NR1
Estimated value
$45,000.00 - $65,000.00
Posted Scope of Work
The University of South Carolina is seeking quotes from a qualified contractor to perform scope of work at the elevation includes removal and replacement of the existing wall panels indicated on the drawings. Sealant to be installed in laps of new wall panels and where they overlap onto existing wall panels. All associated detail work for walls included. Please email quotes to: mbriscoe@mailbox.sc.edu
The scope of work includes removal and replacement of existing wall panels as indicated on the drawings, installation of sealant in laps of new wall panels and where they overlap onto existing wall panels, and all associated detail work for walls.
More exterior maintenance bids in South Carolina, weekly.
We post new exterior maintenance opportunities in South Carolina as agencies publish them. Get them in one email — free, and unsubscribe whenever.
The University of South Carolina is seeking quotes from a qualified contractor to perform scope of work at the elevation includes removal and replacement of the existing wall panels indicated on the drawings. Sealant to be installed in laps of new wall panels and where they overlap onto existing wall panels. All associated detail work for walls included. Please email quotes to: mbriscoe@mailbox.sc.edu
Surety · through Light RFPprequal free · bid bond free · p&p 3%
Need a bond for this one? Get prequalified once.
Most South Carolina work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
Prequalified contractors know they can be bonded before they write the bid — and skip the application on every one of these. The bond becomes a request form and a copy of the RFP, not a scramble at the deadline.Prequalify For Bonding →What’s a good guy letter?
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Not finding it?Describe the work in your own words and we’ll search the whole site.Search with AI →
Source: University of South Carolina (solicitation H34-9599-50003678-7), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.