The full scope of services for this design and construction support contract can be found within the RFP. Generally, the scope of services for the project includes the following:
Project Overview
This contract provides design, environmental, permitting, financing, public outreach, documentation, and construction support services for major infrastructure improvements at the Fairbairn Water Treatment Plant (FWTP), Sacramento River Water Treatment Plant (SRWTP), associated groundwater wells, and the North B Street transmission main.
Environmental and Regulatory Support
Preparation and coordination of environmental documentation under CEQA and NEPA, Section 214 permitting support, and environmental compliance activities related to facility upgrades, groundwater well development, transmission main replacement, levee access, and federally funded project elements.
Engineering and Technical Studies
Includes solar feasibility studies, hydraulic modeling, structural assessments, drainage evaluations, pilot testing, and treatment process optimization involving ozone implementation, sodium hypochlorite conversion, and biologically activated filtration.
Design and Construction Documents
Advances preliminary designs and develops plans and specifications through 30%, 60%, 90%, and 100% milestones, including phased expansion planning, constructability reviews, value engineering, control strategies, and operational procedures.
Permitting and Agency Coordination
Coordinates with utilities, regulatory agencies, and stakeholders to obtain approvals and support implementation of project improvements.
Financial and Real Estate Services
Provides optional assistance with grants, WIFIA and SRF funding programs, financing strategies, property acquisition, easements, demolition permits, and parcel consolidations.
Public Outreach and Records Management
Supports stakeholder engagement, public meetings, communications, document management, scanning, filing, and maintenance of project records.
Construction Support
Provides as-built documentation updates, asset management integration, submittal and RFI review, operator training, equipment startup assistance, and ongoing technical support during construction.
Overall Objective
Deliver comprehensive planning, design, permitting, funding, outreach, and construction support services necessary to implement major resiliency, capacity, and infrastructure improvements at Sacramento water treatment facilities and related transmission infrastructure
Additional Details
Department: DOU - Utilities Department
License Required: CA Licensed Civil Engineer or CA Certified Hydrogeologist
Pre-Bid Meeting: December 9, 2026 at 9:00 AM (mandatory)
Q&A Deadline: January 14, 2027 at 2:00 PM
Required Submittals: Cost File, Response File
The project provides design, environmental, permitting, financing, public outreach, documentation, and construction support for improvements at the Fairbairn Water Treatment Plant, Sacramento River Water Treatment Plant, associated groundwater wells, and the North B Street transmission main. Work includes CEQA and NEPA documentation, Section 214 permitting support, solar feasibility studies, hydraulic modeling, structural assessments, drainage evaluations, pilot testing, ozone implementation, sodium hypochlorite conversion, biologically activated filtration, plans and specifications through 30%, 60%, 90% and 100% milestones, phased expansion planning, constructability reviews, value engineering, agency coordination, optional WIFIA and SRF funding assistance, property acquisition and easements, stakeholder engagement and records management, and construction support including as-built updates, submittal and RFI review, operator training and equipment startup.
We post new architecture and design opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most California work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Contact names and phone numbers are on the official posting.
Source: City of Sacramento (bid 148005), retrieved via the City of Sacramento PlanetBids portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.