The Work required by this Contract includes, but is not limited to, the following: Construction of infrastructure and underground utilities and installation of electrical equipment to support zero emissions charging equipment and charge management systems at various Port facilities. Refer to Section 01 11 00, Summary of Work in the Technical Specifications.
Additional Details
Department: Program Management
Estimated Value: $14,900,000
Pre-Bid Meeting: October 20, 2026 at 9:00 AM (mandatory)
Q&A Deadline: November 10, 2026 at 5:00 PM
Bid Bond: 10%
Payment Bond: 100%
Performance Bond: 100%
Required Submittals: Line Items, Form BP - Bidder's Proposal, Form ND - Noncollusion Declaration, Form BS - Bidder's Security, Form ICA - Iran Contracting Act Compliance Affidavit, Form TSCA - Trade Sanctions Compliance Affidavit, Form CR1 - Bidder's Responsibility Questionnaire, Form CR2 - Experience Requirements, Form SBE-2C - SBE/VSBE Commitment Plan for Construction Contracts, Subcontractor
Construction of infrastructure and underground utilities and installation of electrical equipment to support zero emissions charging equipment and charge management systems at various Port facilities, as detailed in Section 01 11 00, Summary of Work in the Technical Specifications.
We post new electrical opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s notice text — each row shows the sentence it came from. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Contact names and phone numbers are on the official posting.
Source: Port of Long Beach (solicitation 146674), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.