- Scope
- This project will rehab or replace seven culverts throughout various municipalities in Putnam and Westchester counties. The replacement work will occur on the culverts that carry NY 100, US 202, NY 117, Saw Mill River Parkway, US Route 6, and NY 6N over Unknown Streams, Gregory Pond, and the Muscoot Reservoir. The rehab will occur on the culvert that carries I-684 over Unknown Stream.
- Region
- HUDSON VALLEY
- Address
- Hudson Valley Region — Putnam, Westchester County — NY
- Due Date
- May 6, 2025
- Funding
- Local
- No
- State
- Yes
- Federal
- Yes
- Mpo Text
- Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project
in New York State for which Federal funding is proposed to be used and that is
scheduled to begin during the designated three Federal fiscal year time frame.
To review the STIP Project List by Region please see the
STIP Project Report .
- Award Raw
- 05/06/2025
- Counties
- Putnam, Westchester
- Overview
- Project Overview
Project Status
- The current status of the project is Under Construction.
- The Bid Opening was on 02/27/2025.
Project Schedule
Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award** Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award**
05/06/2025
12/31/2026
12/01/2026
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion Yellow - Current Schedule Variance is > 5% and Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract* Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$13,322,365
$0
$13,322,365
On-Budget (Green)
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost Yellow - Current Construction Costs > 5% and Green - Current Construction Costs are within 5% of Contract Award Cost
Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
- Status Text
- Under Construction
- Contact Name
- Heather Pillsworth
- Contact Text
- Contact Us
If you have questions please contact:
Heather Pillsworth, PIN-8LC111
NYSDOT Region 8 Public Information Officer
4 Burnett Boulevard
Phone: 845-431-7911
- Description
- ## Project Overview
Project Status
- The current status of the project is Under Construction.
- The Bid Opening was on 02/27/2025.
Project Schedule
Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award** Award of Contract Original Contract Completion Date*
Estimated Substantial Completion Date*
Construction Schedule Variance from Contract Award**
05/06/2025
12/31/2026
12/01/2026
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion Yellow - Current Schedule Variance is > 5% and Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract* Contract Award Cost Approved Cost Changes Current Construction Contract Cost Cost Variance of Construction Contract**
$13,322,365
$0
$13,322,365
On-Budget (Green)
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost Yellow - Current Construction Costs > 5% and Green - Current Construction Costs are within 5% of Contract Award Cost
Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources:
Federal: Yes
State : Yes
Local : No
## Description
This project will rehab or replace seven culverts throughout various municipalities in Putnam and Westchester counties. The replacement work will occur on the culverts that carry NY 100, US 202, NY 117, Saw Mill River Parkway, US Route 6, and NY 6N over Unknown Streams, Gregory Pond, and the Muscoot Reservoir. The rehab will occur on the culvert that carries I-684 over Unknown Stream.
## Location
This project is located in the **Hudson Valley** region.
**Counties:** Putnam, Westchester

- Contact Email
- R8Projects@dot.state.ny.us
- Contact Phone
- 845-431-7911
- Location Text
- This project is located in the HUDSON VALLEY region and includes the following:
Counties
PUTNAM
WESTCHESTER
Villages
HARRISON
- Bid Opening Raw
- 02/27/2025
- Bid Opening Date
- Feb 27, 2025
- Legislative Text
- Legislative Districts
This project falls within the geographical boundaries of the following legislative districts:
U.S. Senators
Schumer, Charles E.
Gillibrand, Kirsten
U.S. Congressional District(s)
16th Congressional District (George Latimer)
17th Congressional District (Michael Lawler)
State Senatorial District(s)
37th Senatorial District (Shelley B. Mayer)
40th Senatorial District (Pete Harckham)
State Assembly District(s)
093rd Assembly District (Chris Burdick)
094th Assembly District (Matt Slater)
095th Assembly District (Dana Levenberg)