Bridge rehabilitation including partial superstructure replacement with a 30-inch steel beam on 38th Street over I-94, Kalamazoo County. This project includes a 5 year performance warranty on epoxy overlay.
Michigan Department of TransportationIssuing agency·Michigan·via a public procurement portal
Bridge rehabilitation including partial superstructure replacement with a 30-inch steel beam on 38th Street over I-94 is being procured for Kalamazoo County, Michigan.
Bids are due 2026-11-06 at 10:30 AM local time at 425 W. Ottawa St., Lansing, MI.
The solicitation was advertised on 2026-10-02.
The project includes a 5 year performance warranty on epoxy overlay.
The completion date for the work is 6/11/2027.
Required DBE participation is 0.00% and Required SBP participation is 0.00% for this project.
The net classification required for this project is 574 Fa.
Proposals and plans are available for examination online through MDOT's eProp system.
Requirement: Net Classification Required For This Project: ** 574 Fa **.
Participation goal
0.00% DBE, 0.00% SBP
Method
Invitation for Bids (IFB)
Documents
1 file
These takeaways are AI-generated and may be incomplete or wrong. Always verify every detail against the official documents before you bid.
Want to know if you can be bonded for this project? Get prequalified.One free application, soft pull — sized to your work.
Know you can be bonded before you spend a week on the bid
No scramble for a bond at the deadline — it becomes a request form
Perform bridge rehabilitation on 38th Street over I-94 in Kalamazoo County including partial superstructure replacement with a 30-inch steel beam.
Provide a 5 year performance warranty on the epoxy overlay installed.
Hold the ** 574 Fa ** prequalification classification required for this project.
Submit a bid by the 2026-11-06 10:30 AM bid opening at 425 W. Ottawa St., Lansing, MI.
Requirements
From the documents
Participation goal
0.00% DBE, 0.00% SBP
Posted Scope of Work
Description
Bridge rehabilitation including partial superstructure replacement with a 30-inch steel beam on 38th Street over I-94, Kalamazoo County. This project includes a 5 year performance warranty on epoxy overlay.
Contract details
Call number: 019
Contract ID: 39022-226314
Control section: MER 39022
Project number: 226314A
Federal project number: N/A
Prequalification: ** 574 Fa **
Required DBE participation: 0.00%
Required SBP participation: 0.00%
Completion date: 6/11/2027
Advertised: 10/2/2026
Bid opening: 2026-11-06 10:30 AM local time, 425 W. Ottawa St., Lansing, MI
The work consists of bridge rehabilitation including partial superstructure replacement with a 30-inch steel beam on 38th Street over I-94 in Kalamazoo County, with a 5 year performance warranty on the epoxy overlay installed as part of the rehabilitation.
More structural work bids in Michigan, weekly.
We post new structural work opportunities in Michigan as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Surety · through Light RFPprequal free · bid bond free · p&p 3%
Need a bond for this one? Get prequalified once.
Most Michigan work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
Prequalified contractors know they can be bonded before they write the bid — and skip the application on every one of these. The bond becomes a request form and a copy of the RFP, not a scramble at the deadline.Prequalify For Bonding →What’s a good guy letter?
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Not finding it?Describe the work in your own words and we’ll search the whole site.Search with AI →
Source: Michigan Department of Transportation (solicitation 261106-019), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.