removal and replacement of sliding plate expansion joint
Parish: Terrebonne
Estimated Construction Cost: $50,000 to $100,000
OJT Goal: Trainees
Specbook: 2026
Letting: 10/15/2026 New Orleans — electronic bids via www.bidx.com, downloaded 10:00 a.m.
Schedule of items (6 pay items, quantities for information only):
0001 · 202-02-04560 · Removal of Bridge Joint Removal of Existing Sliding Plate Bridge Joint · LNFT · 36
0002 · 713-01-00100 · Temporary Signs and Barricades · LUMP · 1
0003 · 727-01-00100 · Mobilization · LUMP · 1
0004 · 740-01-00100 · Construction Layout · LUMP · 1
0005 · NS-713-00009 · Portable Changeable Message Sign (with communications) · EACH · 2
0006 · NS-830-01100 · Bridge Deck Joint Repair (Both Sides of Joint) Sliding Plate Joint Repair · LNFT · 36
The work includes removal of the existing sliding plate bridge joint (36 linear feet), installation of temporary signs and barricades, mobilization, construction layout setup, installation of two portable changeable message signs with communications equipment, and repair of the bridge deck joint on both sides of the joint (36 linear feet) using a sliding plate joint system.
We post new metalwork opportunities in Louisiana as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Louisiana work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Louisiana Department of Transportation and Development (solicitation H.017039.6), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.