Removal and replacement of bridge structure (SN 050-0254) which carries Water St over Indian Creek located about 0.4 miles north of US 34 in Earlville.
Item: 060
Contract: 66K64
Region/District: 2 / 3
DBE goal: Pending%
VBP goal: Pending%
Federal Project: BRXRS2(794)
Key Routes: MUN 1750
Marked Routes: WATER ST / N 4550TH RD
Sections: (050-0254)BR
State Jobs: C-93-055-24
Contract specifics:
The work includes removal of existing structures, tree removal, earth and channel excavation, concrete structures, precast prestressed concrete deck beams, hot-mix asphalt binder and surface courses, pavement removal, guardrail installation, erosion control, seeding, mobilization, traffic control, and related items as listed in the pay items.
We post new structural work opportunities in Illinois as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Illinois work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Illinois Department of Transportation (solicitation 66K64), retrieved via a public procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.