CONTRACTS AND SPECIFICATIONS BUREAU
Proposal
Proposal ID: 79-0806-518 Letting Date: December 15, 2026
Call Order: 353
Proposal Work Type: LIGHTING
DBE Goal: 0.0%
Contracting Authority: IOWA DEPARTMENT OF TRANSPORTATION
Proposal Guaranty: $6,250.00
This proposal includes the following project(s):
Project Number: IM-080-6(518)202--13-79 County: POWESHIEK
Project Work Type: LIGHTING Route: I-80
Location: W of IA 21 to E of IA 21
Road System: INTERSTATE ROAD
Federal Aid - Wages: Federal Aid - Predetermined Wages are in Effect
Project Number: ITS-080-6(550)201--25-79 County: POWESHIEK
Project Work Type: ITS INFRASTRUCTURE Route: I-80
Location: W of IA 21 to E of IA 21 (EB/WB)
Road System: INTERSTATE ROAD
Federal Aid - Wages: Non-Federal Aid - Predetermined Wages are in Effect
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Contract Time
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
Site ID Site Details Liquidated
Damages
00 Late Start Date 09/06/2027 35 WORK DAYS $1,000.00
.
(*) - Indicates Cost Plus Time Site. See Schedule of Items for Cost Per Unit
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
Notes
Notes :
There are no notes for this proposal.
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Specifications List
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
Note Description
001.2023 *** STANDARD SPECIFICATIONS -- SERIES 2023 ***
The Iowa Department of Transportation STANDARD SPECIFICATIONS FOR
HIGHWAY AND BRIDGE CONSTRUCTION, SERIES 2023, plus applicable General
Supplemental Specifications, Developmental Specifications, Supplemental
Specifications AND Special Provisions shall apply to construction work on this contract.
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Specifications List
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
Note Description
005.1107.02 *** Revisions to Article 1107.02 ***
Article 1107.02, Insurance, is amended by the following modifications and additions.
This proposal note becomes null and void January 1, 2027.
A. It shall be the Contractor's responsibility to have liability insurance covering all
of the construction operations incident to contract completion and the Contractor must
have on file with the Contracting Authority a current "Certificate of Insurance" prior to
award of contract. The certificate shall identify the insurance company firm name and
address, Contractor firm name, policy period, type of policy, limits of coverage, and
scope of work covered (single contract or statewide). This requirement shall apply with
equal force, whether the work is performed by persons employed directly by the
Contractor including a subcontractor, persons employed by a subcontractor, or by an
independent contractor.
B. In addition to the above, the Contracting Authority shall be included as an
insured party, or a separate owner's protective policy shall be filed showing the
Contracting Authority as an insured party.
C. The liability insurance shall be written by an insurance company (or
companies) qualified to do business in Iowa. For independent contractors engaged
solely in the transportation of materials, the minimum coverage provided by such
insurance shall be not less than that required by Chapter 325A, Code of Iowa, for such
truck operators or contract carriers as defined therein. For all other contractors,
subcontractors, independent contractors, and the Contracting Authority, the minimum
coverage by such insurance shall be as follows:
General Liability, Including: BODILY INJURY
Independent Contractors $500,000 Each Occurrence
Contractual Liability, $500,000 Aggregate
Products and Completed PROPERTY DAMAGE
Operations $250,000 Each Occurrence
$250,000 Aggregate
or
BODILY INJURY AND PROPERTY DAMAGE
- COMBINED SINGLE LIMIT*
$750,000 Each Occurrence
$750,000 Aggregate
*A comprehensive Catastrophe Liability Policy (Umbrella) can be used to aid in
achieving the minimum required limits.
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Specifications List
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
Note Description
*A comprehensive Catastrophe Liability Policy (Umbrella) can be used to aid in
achieving the minimum required limits.
D. Failure on the part of the Contractor to comply with the requirements of this
article will be considered sufficient cause to suspend the work, withhold estimates, and
to deny the Contractor from receiving further contract awards, as provided in Article
1103.01.
500.01 *** WINTER WORK ***
The free time allowed between November 15 and April 1 will not be permitted on this
project. The Contractor shall work during the winter on all working days as defined in
Article 1101.03 'Working Day'.
DS-23074 DEVELOPMENTAL SPECIFICATIONS FOR INTELLIGENT TRANSPORTATION
SYSTEMS
FHWA-1273.09 FHWA-1273: REQUIRED CONTRACT PROVISIONS FEDERAL-AID
CONSTRUCTION CONTRACTS -- REVISED OCTOBER 23, 2023
23 U.S.C. 133(i) requires application of Davis Bacon predetermined wages on certain
projects on roads functionally classified as a local road or a rural minor collector. This
supersedes the applicability described in FHWA-1273 Section IV.
GS-23007 GENERAL SUPPLEMENTAL SPECIFICATIONS FOR HIGHWAY AND BRIDGE
CONSTRUCTION, OCTOBER 20, 2026 RELEASE
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Specifications List
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
Note Description
IA26-28.4A PREDETERMINED WAGE RATE - GENERAL DECISION NUMBER IA20260028
FOR HEAVY AND HIGHWAY CONSTRUCTION -- STATEWIDE (EXCEPT SCOTT
COUNTY)
Note: The Contractor shall review the contract documents and
is responsible for identifying which zone(s), as defined
in the Predetermined Wage Rate specification, apply to
the work on the contract.
*** Additional Requirement ***
Contracts where the Department is the Contracting Authority:
The Prime Contractor and each approved Subcontractor shall submit certified payrolls
weekly to the Project Engineer. Each Contractor shall use the AASHTOWare Project
Civil Rights and Labor (AWP CRL) software to electronically submit Certified Payroll
Reports. The Contractor shall list the craft for each employee covered by the
Predetermined Wage Rates. The Prime Contractor shall review and approve each
Subcontractor’s payroll within AWP CRL.
Contracts where the Department is not the Contracting Authority:
The Prime Contractor shall submit certified payrolls for itself and each approved
Subcontractor weekly to the Project Engineer. The Contractor may use the Iowa D.O.T.
Certified Payroll form or other approved form. The Contractor shall list the craft for
each employee covered by the Predetermined Wage Rates. The Prime Contractor
shall sign each of the Subcontractor's payrolls to acknowledge the submittal of the
Certified Payroll.
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Schedule of Items
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
SECTION: 0001
LIGHTING ITEMS - IM-080-6(518)202--13-79
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0010 2401-6745359 3.000
REMOVAL OF CONCRETE
FOUNDATIONS OF LIGHT POLES
EACH _________._____ _________._____
0020 2401-6745765 3.000
REMOVAL OF LIGHT POLES EACH _________._____ _________._____
0030 2523-0000100 3.000
LIGHTING POLES EACH _________._____ _________._____
0040 2523-0000200 740.000
ELECTRICAL CIRCUITS LF _________._____ _________._____
0050 2523-0000310 2.000
HANDHOLES AND JUNCTION BOXES EACH _________._____ _________._____
0060 2523-0000400 1.000
CONTROL CABINET EACH _________._____ _________._____
0070 2528-8445110
TRAFFIC CONTROL LUMP SUM LUMP SUM _________._____
0080 2533-4980005
MOBILIZATION LUMP SUM LUMP SUM _________._____
0090 2555-0000010
DELIVER AND STOCKPILE SALVAGED
MATERIALS
LUMP SUM LUMP SUM _________._____
0100 2599-9999005 1.000
('EACH' ITEM) REMOVE AND DISPOSE
OF POLE MOUNTED LIGHTING
CABINET
EACH _________._____ _________._____
0110 2599-9999010
('LUMP SUM' ITEM) DEMOLITION OF
ELECTRICAL CIRCUITS
LUMP SUM LUMP SUM _________._____
Section: 0001 Total: _________._____
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Schedule of Items
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
SECTION: 0002
ITS ITEMS - ITS-080-6(550)201--25-79
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0120 2518-0000010
ITS CONSTRUCTION SURVEY LUMP SUM LUMP SUM _________._____
0130 2518-0000020 1.000
ITS POWER INSTALLED
FOUNDATION, INSTALL ONLY
EACH _________._____ _________._____
0140 2518-0000030 1.000
ITS STEEL POLE, INSTALL ONLY EACH _________._____ _________._____
0150 2518-0000055 1.000
ITS DEVICE CABINET, INSTALL ONLY EACH _________._____ _________._____
0160 2518-0000090 2.000
ITS HANDHOLE, 36x24x36 EACH _________._____ _________._____
0170 2518-0000150 3.000
ITS GROUND ROD EACH _________._____ _________._____
0180 2518-0001125 773.000
ITS CONDUIT, HDPE, 1.25 INCH
BORED
LF _________._____ _________._____
0190 2518-0002125 20.000
ITS CONDUIT, HDPE, 1.25 INCH
PLOWED
LF _________._____ _________._____
0200 2518-0006006 1,342.000
XHHW COPPER WIRE, NO. 6 AWG LF _________._____ _________._____
0210 2518-0006008 671.000
XHHW COPPER WIRE, NO. 8 AWG LF _________._____ _________._____
0220 2518-0006015 608.000
ITS TRACER WIRE LF _________._____ _________._____
0230 2518-0007012 883.000
FIBER OPTIC CABLE, 12 SM
DIELECTRIC
LF _________._____ _________._____
Contracts and Specifications Bureau
11/10/2026 11:14 AM
Proposal Schedule of Items
Proposal ID: 79-0806-518 Call Order: 353 Letting Date: December 15, 2026
SECTION: 0002
ITS ITEMS - ITS-080-6(550)201--25-79
Proposal
Line
Number
Item Number
Item Description
Item Quantity
and Units
Unit Price Bid Amount
Dollars Cents Dollars Cents
0240 2518-0008355 1.000
CONNECTOR ADAPTOR PANEL, SIX
DUPLEX SC
EACH _________._____ _________._____
0250 2518-0008360 1.000
SINGLE PANEL HOUSING EACH _________._____ _________._____
0260 2518-0008365 2.000
UPC/SC FACTORY TERMINATED
FIBER CONNECTOR AND PIGTAILS
EACH _________._____ _________._____
0270 2518-0008400
FIBER OPTIC CABLE ACCEPTANCE
TESTING
LUMP SUM LUMP SUM _________._____
0280 2528-8445110
TRAFFIC CONTROL LUMP SUM LUMP SUM _________._____
0290 2533-4980005
MOBILIZATION LUMP SUM LUMP SUM _________._____
Section: 0002 Total: _________._____
Total Bid: _________._____
DS- 23074
(Replaces DS-23058)
DEVELOPMENTAL SPECIFICATIONS
FOR
INTELLIGENT TRANSPORTATION SYSTEMS
Effective Date
January 22, 2025
THE STANDARD SPECIFICATIONS, SERIES 2023, ARE AMENDED BY THE FOLLOWING
MODIFICATIONS AND ADDITIONS. THESE ARE DEVELOPMENTAL SPECIFICATIONS AND THEY
PREVAIL OVER THOSE PUBLISHED IN THE STANDARD SPECIFICATIONS.
23074.01 DESCRIPTION.
A. This section includes furnishing all work, apparatus, and materials to construct, install, and place
in operation, to the Engineer's satisfaction, a complete ITS as shown in the contract documents.
B. Definition of Abbreviations.
AC – Alternating Current
AMP - Ampere
AWG – American Wire Gauge
CSR – Combined Stress Ratio
EMT – Electric Metallic Tube
GFCI – Ground Fault Circuit Interrupter
IP – Internet Protocol
ITU-T - International Telecommunications Union – Telecommunications Standardization Sector
LED – Light Emitting Diode
MVDS - Microwave Vehicle Detection System
NOC – Network Operations Center
OSP – Outside Plant
PDF – Portable Document File
RJ – Registered Jack
RMS – Root Mean Square
SC – Subscriber Connector
SCTE - Society of Cable Telecommunications Engineers
TMC – Traffic Management Center
UPC - Ultra-Physical Contact
UV – Ultraviolet
VAC - Volts Alternating Current
XHHW - Cross-linked Polyethylene, High Heat and Water Resistant
C. Special Requirements.
DS-23074, Page 2 of 39
1. Comply with NEC, latest edition adopted by the State of Iowa.
2. Comply with TIA latest editions.
3. EIA latest editions.
4. IEEE Standards and Practices.
5. ANSI Standards and Practices.
6. NEMA Standards.
7. UL Standards.
D. Submittals.
1. Material List.
Complete and submit one electronic PDF file of the materials list to the project Engineer within
14 calendar days after award of the project contract. Include the name of the materials, supplier
and catalog number of each item listed.
2. Construction Schedule.
a. Fourteen calendar days before the preconstruction conference, submit to the Engineer one
electronic PDF file of the detailed construction schedule including dates of commencement
for each major work item, duration of each major work item and completion of each major
work item on each segment of the proposed construction.
b. Major items of work to be included on the schedule shall include, but are not limited to the
following:
• Duration of material procurement,
• Installation of conduit, handholes, building entrances, and fiber optic cable,
• Bridge attachments,
• Installation of device cabinets, foundations, and poles,
• Installation and energizing of power,
• Splicing and termination of fiber optic cables, and
• Duration of fiber testing and submission of test reports.
c. The construction schedule shall comply with Section 1108 of the Standard Specifications.
In addition to limitations of operations in Article 1108.03 of the Standard Specifications,
work shall not be performed that may result in an unplanned network disruption during an
ICN moratorium date.
d. Coordinate with the Engineer to schedule all splicing work.
e. Upon acceptance of the schedule, the Contractor will be expected to adhere to these dates
as proposed unless modified with the approval of the Engineer.
f. Submittal and approval of the proposed construction schedule by the Engineer is required
before the Contractor can commence construction activities.
g. The cost of preparing and revising the construction schedule shall be included in the bid
item for Mobilization.
3. Shop Drawings.
a. Before any items are ordered or installation is started, submit the following list of shop
drawings for approval according to Article 1105.03 of the Standard Specifications:
• Power Installed Foundation.
• Pole.
• Breakaway Transformer Base.
• Pole Mount Cabinet Mounting Assemblies.
• Cabinet Foundation.
DS-23074, Page 3 of 39
• Cabinet.
• HDPE Conduit.
• Schedule 80 HDPE Conduit.
• Conduit Splice Kit.
• Rigid Steel Conduit and Fittings.
• Duct Plugs.
• Duct Seal.
• Handholes.
• Test Stations.
• Fiber Markers.
• Ground Rods.
• Exothermic Welding Kit.
• Copper Cable (Power).
• Copper Cable (Ground).
• Tracer Wire.
• Tracer Wire Splice Kit.
• Fiber Optic Cable.
• NEMA 3R 240/120 1.0 kVA Transformer.
• Meter Pedestal.
• Circuit Breaker.
• OTDR Meter with Calibration Certificate from Manufacturer within last year.
• Fusion Splicer with Calibration Certificate from Manufacturer within last year.
• Fiber Optic Splice Closure.
• Fiber Optic Splice Tray.
• Module Connector Housing Splice Cassettes.
• Connector Adaptor Panel.
• Single Panel Housing.
• Fiber Connector and Pigtails.
• One Rack Unit Connector Housing.
• Four Rack Unit Connector Housing.
• Additional drawings may be required on a project specific basis in accordance with the
contract documents.
b. Submittal for power installed foundation shall include all structural calculations and be
accompanied by a shop drawing that at a minimum illustrates a schematic of the foundation
with a summary of the design criteria, material data, foundation data and orientation details.
Design calculations and shop drawing for power installed foundation shall be sealed by a
Professional Engineer licensed in the State of Iowa.
c. Submittal for poles shall include all structural calculations and be accompanied by a shop
drawing that at a minimum illustrates a schematic of the proposed pole and transformer
base with a summary of the design criteria, material data, pole data and details of
handholes, pole top, pole base and pole orientation. Design calculations for poles and
transformer bases shall be sealed by a Professional Engineer licensed in the State of Iowa.
d. The Engineer will review the shop drawings/catalog cuts for the purpose of assuring
general conformance with the project design concept and contract documents.
e. The Engineer will provide approval or rejection of shop drawings within 14 calendar days
of the Contractor’s submission. Re-submit the shop drawings for approval within 7 calendar
days of the Engineer’s rejection.
f. Provide written notice of any deviations from the requirements of the contract documents
or Special Provisions.
g. Engineer's approval of shop drawings/catalog cuts does not relieve the Contractor of
responsibility for providing satisfactory materials complying with the contract documents.
Errors not detected during review do not authorize the Contractor to proceed in error.
h. Order all materials requiring production lead time greater than 4 weeks within 7 calendar
days of receiving the approved shop drawing(s).
i. Submit to the Engineer proof of material purchase order in electronic PDF format.
DS-23074, Page 4 of 39
4. Warranty.
a. Transfer all required standard materials warranties on the date of final acceptance to the
Contracting Authority.
b. Warranty periods shall not commence prior to final acceptance of the work and shall remain
in effect until at least 1 year after the final acceptance for all cables and equipment
furnished and installed for the project.
E. As-Built Documentation.
1. General.
a. Maintain written records of daily construction progress, areas worked, and quantities
installed to aid in the completeness of as-constructed documentation.
b. Provide as-built documentation package with the following:
1) Documentation of fiber cable sequentials at building entrances, cabinets, and in/out of
handholes.
2) Master record set of plans (maintained throughout construction) documenting any
deviations from the design shown in the original contract documents.
3) Confirmation that splicing was completed as planned or redline corrections on how it
was spliced.
2. GPS Data Recording Staking Assistance.
a. Unless otherwise specified in the contract documents, the Engineer will be responsible for
collecting GPS data of all installations including, but not limited to, conduit and/or cable
routing and installation depth and handhole locations.
b. Coordinate and assist the Engineer in this effort by staking, flagging or otherwise locating
all installed features until such time that the GPS data can be collected. Mark the conduit
alignment at least every 50 feet.
c. For any segments that are bored, provide bore logs to the Engineer that include the bore
depth and location if the boring equipment is capable of producing these records.
d. The cost of GPS data recording staking assistance shall be included in the bid item for
Mobilization.
F. Aerial photography shown on the plans is for reference only and may not match existing conditions.
23074.02 MATERIALS.
A. General.
1. Provide any items, equipment, or materials not specifically addressed in the contract
documents but required to provide a complete and functional installation. The level of quality
shall be consistent with other specified items. All miscellaneous electrical equipment and
materials shall be listed for its specific application.
2. Material requirements apply to new construction, relocation, and maintenance of the Intelligent
Transportation System.
B. ITS Construction Survey.
1. General.
ITS construction survey includes equipment and supplies required for fiber optic conduit path
and ITS construction surveying and staking necessary for construction of the project as shown
in the contract documents.
2. Lath.
Provide wood lath that is approximately 3/8 inch thick by 1 1/2 inches wide by 48 inches long.
DS-23074, Page 5 of 39
3. Survey Equipment.
Utilize survey equipment with a level of accuracy that will result in less than 6 inches of error
horizontally.
C. Power Installed Foundation.
1. General.
a. This specification is for a power installed foundation compatible for use with, and support
of, 45 foot steel breakaway poles.
b. Foundations and baseplate should be of steel construction.
c. Ensure the foundation and baseplate are hot dip galvanized inside and out according to
ASTM A153.
d. After galvanizing, the manufacturer identification and fabrication date shall be permanently
stamped to the baseplate in minimum 1/2 inch letters.
e. The manufacturer shall utilize industry recognized written quality control for materials and
manufacturing processes.
2. Fabrication Specifications.
a. All foundations shall be designed in accordance with the AASHTO LRFD Specifications for
Structural Supports for Highway Signs, Luminaires, and Traffic Signals, First Edition.
b. Mill certifications shall be supplied as proof of compliance with the specifications. The
Fabricator shall be certified under Category I, "Conventional Steel Structures" as set forth
by the AISC Quality Certification Program. All welding shall be in accordance with Article
2408.03, B of the Standard Specifications. Tackers and welders shall be qualified in
accordance with the code. Tube longitudinal seam welds shall be free of cracks and
excessive undercut, performed with automatic processes, and be visually inspected.
Longitudinal welds suspected to contain defects shall be magnetic particle inspected. All
circumferential butt-welded pole and arm splices shall be ultrasonically or radiographically
inspected.
c. The baseplate shall be perpendicular to the shaft axis (± 1 degree) and hole and concentric
(± 0.188 inches) to shaft axis.
d. Pilot point and shaft axis to be concentric (± 0.125 FIM) and in line (± 2 degrees)
e. Preheat, tumbleblast, handgrind, and clean baseplate on all welded areas prior to
galvanizing.
f. All material is to be new, unused and mill traceable meeting the following specifications:
Baseplate: ASTM A36 (Latest Revision) Structural Steel (Conform to AASHTO Tech.
Bul. No. 270)
Shaft: ASTM 252 (Latest Revision) Grade 2, steel pipe piles.
Alternate material: ASTM A53 (Latest Revision) Type E or S, Grade B, steel
pipe
OR
ASTM A500 (Latest Revision), Grade B, structural steel tubing
Helix: ASTM A635 (Latest Revision) 1/2 inch thick hot rolled steel plate or coil.
Pilot Point: ASTM A575 (Latest Revision) 1 1/4 inch diameter hot rolled steel bar.
g. Two slots with minimum dimensions of 2.5 inches in width and 12 inches in length shall be
cut into the shaft of the foundation, perpendicular to the base plate to allow for conduit
entry during installation. The top of these conduit entryway openings shall be 12 inches
from the bottom of the base plate.
h. The baseplate shall be permanently marked to indicate the conduit entryway openings in
the shaft.
DS-23074, Page 6 of 39
i. An 8 inch diameter hole shall be constructed in the baseplate to allow access between the
shaft and pole foundation.
j. The bolt circle of the foundation shall be variable such that it will be compatible with the
bolt circle of the pole design.
k. At a minimum, the foundation base plate thickness shall match the base plate thickness of
the pole in the contract documents.
3. Design Calculations.
a. The design reference for foundations shall be AASHTO LRFD Specifications for Structural
Supports for Highway Signs, Luminaires, and Traffic Signals, First Edition, Section 13,
Foundation Design. The device loadings specified in this document shall be used in all
AASHTO design calculations. Calculations and detailed drawings shall be submitted
demonstrating compliance with the AASHTO specification.
b. Assume a soil profile of uniform cohesive soil (sand) with an angle of internal friction of 30
degrees and a unit weight of 100 pounds per cubic foot. Also, assume the water table is
at a depth that will not affect lateral capacity.
c. Using the determined loads and assumed soil profile, the size of the foundation (shaft
diameter, shaft length, base plate thickness, etc.) needed for adequate service shall be
calculated using Broms Method for Lateral Pile Support.
d. A minimum factor of safety of 2.5 shall be used when recommending an adequate
foundation.
D. Poles.
1. General
a. All poles shall be tapered steel poles, 45 feet in length (excluding the transformer base).
b. Poles shall satisfy the requirements of Article 1107.06 of the Standard Specifications.
c. The poles shall be designed to satisfy deflection requirements.
d. The poles shall be provided with two handholes with removable covers. The handhole
openings shall be reinforced with a minimum 0.432 inch wide hot rolled steel rim. The first
handhole shall be located 1.5 feet above the base plate (measured from bottom lip of
handhole) and have minimum outside dimensions of 6 inches by 10 inches. The second
handhole shall be oriented directly above the first handhole but located 40 feet above the
baseplate (measured from bottom lip of handhole) and have minimum outside dimensions
of 3 inches by 5 inches.
e. Ensure each pole has an approved grounding provision for use during installation and that
it is accessible and will function as intended after the galvanization process. Ensure the
grounding lug is readily accessible through the handhole and from the bottom of the pole
shaft.
f. Poles shall include a removable end cap at the top of the pole with a J-hook cable support
above the upper handhole.
g. Ensure the poles and base plates are hot dip galvanized inside and out according to ASTM
A123.
h. Unless otherwise noted in this specification, materials shall meet the applicable minimum
requirements of Section 4185 of the Standard Specifications.
2. Pole Design Calculations and Fabrication Specifications
a. All poles shall be designed in accordance with the AASHTO LRFD Specifications for
Structural Supports for Highway Signs, Luminaires and Traffic Signals, First Edition.
b. The device loadings specified in this document shall be used in all AASHTO design
calculations and pole deflection evaluations and the poles shall be capable of withstanding
winds up to 90 mph with a 1.14 gust factor without failure. Calculations and detailed
drawings shall be submitted demonstrating compliance with the AASHTO specification.
c. Mill certifications shall be supplied as proof of compliance with the specifications. The
Fabricator shall be certified under Category I, "Conventional Steel Structures" as set forth
by the American Institute of Steel Construction Quality Certification Program. Proof of this
DS-23074, Page 7 of 39
certification will be required to ensure that the fabricator has the personnel, organization,
experience, procedures, knowledge, equipment, capability and commitment to fabricate
quality pole structures. All welding shall be in accordance with Article 2408.03, B, of the
Standard Specifications. Tackers and welders shall be qualified in accordance with the
code. Tube longitudinal seam welds shall be free of cracks and excessive undercut,
performed with automatic processes, and be visually inspected. Longitudinal welds
suspected to contain defects shall be magnetic particle inspected. All circumferential butt-
welded pole and arm splices shall be ultrasonically or radiographically inspected.
d. All poles shall be designed to support the specified camera, sensor and device cabinet and
shall be stiffened or otherwise manufactured to meet allowable deflection criteria contained
herein. Pole design shall assume the following loadings. All mounting heights are
measured from the base of foundation to bottom of equipment.
Radio Communication Equipment and Mounting Bracket
Weight: 10 pounds
Surface Area: 2 square feet
Mounting Height: 45 feet
Camera and Mounting Bracket
Weight: 9 pounds
Surface Area: 1 square feet
Mounting Height: 40 feet
Roadway Sensor
Weight: 6 pounds
Surface Area: 1 square feet
Mounting Height: 17 to 25 feet
Device Cabinet
Weight: 95 pounds
Surface Area: 6 square feet
Mounting Height: maximum 6 feet
e. The pole top deflection shall not exceed 1 inch in a 30 mph (non-gust) wind. Close
consideration must be given to the effective projected area of the equipment along with the
weight when designing the pole to meet the specified deflection performance criteria. The
calculations shall include a pole, base plate, and anchor bolt analysis. The pole calculations
shall be analyzed at the pole base, at 5 foot pole intervals/segments and at any other
critical pole section. At each of these locations, the following information shall be given:
• The pole's diameter, thickness, section modulus, moment of inertia, and cross
sectional area.
• The centroid, weight, projected area, drag coefficient, velocity pressure, and wind force
of each pole segment.
• The axial force, shear force, primary moment, total moment, axial stress, bending
stress, allowable axial stress, allowable bending stress, and combined stress ratio
(CSR).
• The pole's angular and linear deflection.
f. All pole shafts shall have a minimum yield strength of 55 ksi and conform to ASTM A595
Grade A or ASTM A572 Grade 55. The shaft shall have a constant linear taper and contain
only one longitudinal seam weld. Circumferential welded tube butt splices and laminated
tubes are not permitted. Longitudinal seam welds within 6 inches of base plate welds shall
be complete penetration welds.
g. Base plates shall conform to ASTM A36. Plates shall be integrally welded to the tubes with
a telescopic welded joint or a full penetration butt weld with backup bar.
h. Anchor bolts shall conform to the requirements in Article 4185.02, B, 2 of the Standard
Specifications.
DS-23074, Page 8 of 39
3. Breakaway Transformer Base.
a. Transformer base shall be designed for installation with each ITS pole as specified above
and is subsidiary to the pole.
b. Transformer base shall conform to breakaway criteria of AASHTO LRFD Specifications for
Structural Support for Highway Signs, Luminaires and Traffic Signals, First Edition and in
accordance with the guidelines of NCHRP Report 350.
c. The aluminum transformer base material shall conform to ASTM Designation B108 Alloy
356.0 T6.
d. Connecting hardware shall be finished to ASTM: B695 Class 50. All structural fasteners
shall be galvanized high strength carbon steel. All non-structural fasteners shall be
galvanized or zinc-plated carbon steel or stainless steel.
e. Height of transformer base shall be 17 inches.
f. Top plate bolt circle shall be 12.75 inch in diameter (+/- 0.75 inch) and accommodate bolts
a maximum of one inch diameter. Top plate shall be 13.12 inch by 13.12 inch by 0.750
inch.
g. Bottom plate bolt circle shall be 14.5 inch in diameter (+/- 0.5 inch) and accommodate bolts
a maximum of 1.25 inch diameter. Bottom plate shall be 14.5 inch by 14.5 inch by 0.625
inch.
h. Transformer base shall include one aluminum access door of 11 inches by 8.56 inches (at
top) by 8.94 inches (at bottom).
E. Cabinet Foundations.
1. All concrete shall meet the requirements of Article 2403.02 of the Standard Specifications.
2. Use Class C concrete with 28 day compressive strength of 4000 PSI for cabinet foundations
and all other non-paving concrete construction.
3. All reinforcement shall be epoxy coated and meet the requirements of Article 4151.03 of the
Standard Specifications. All reinforcing steel shall be Grade 60.
F. Device Cabinets.
1. General.
a. Cabinets shall be dimensioned as identified in the contract documents.
b. Cabinets shall be corrosion resistant, NEMA Type 3R compliant, constructed of welded
sheet aluminum with a minimum nominal thickness of 1/8 inch.
c. Cabinets shall be complete with all required internal components, fully wired back panel,
side mount DIN rails, terminal strips, and stainless steel hardware.
d. Cabinets shall meet the requirements of ASTM B-209 for 5052 H-32 aluminum sheet. The
aluminum shall be smooth and the exterior shall be left in its unpainted natural color.
e. The cabinet shall be effectively sealed to prevent the entry of rain, dust, and dirt.
f. All exterior seams for cabinet and doors shall be continuously welded.
g. Edges, seams, fittings, and hardware shall be finished free from burrs and sharp edges.
h. Use Type 316 stainless steel for all mounting hardware.
i. Use 3/4 inch wide and 0.03 inch thick banding for pole mounted cabinets.
2. Cabinet Doors.
a. The cabinet door shall be sturdy, torsionally rigid, and attached by a continuous heavy duty
stainless steel butt hinge. The door shall substantially cover the full area of the front of the
cabinet and have a stainless steel, pad-lockable handle.
b. The cabinet door shall be provided with a door stop catch mechanism to hold the door open
at three positions; 90 degrees, 120 degrees and 180 degrees. Both the door and door stop
mechanism shall be of sufficient strength to withstand a wind load of 5 pounds per square
foot of door area applied to both inside and outside surfaces.
DS-23074, Page 9 of 39
c. A closed-cell neoprene gasket shall be provided to act as a permanent and weather
resistant seal at the cabinet door facing. The gasket material shall be of a non-absorbent
material and shall maintain its resiliency after long-term exposure to the outdoor
environment. The gasket shall have a minimum thickness of 1/3 inch. The gasket shall be
located in a channel provided for this purpose either on the cabinet or on the door. An “L”
bracket is acceptable in lieu of this channel if the gasket is fitted snugly against the bracket
to insure a uniformly dust and weather resistant seal around the entire door facing.
d. LED cabinet light shall be provided and operated by door switch.
e. Each cabinet door shall be provided with a high quality, heavy duty tumbler-type lock. Two,
No. 2 keys for each tumbler lock shall be provided for each cabinet. All locks for the project
shall be keyed identically to key pattern 9R46142 or as otherwise identified by the
Engineer. Keys shall be given to the Engineer. Do not attach keys to the exterior of the
cabinet at any time during storage or installation.
f. A heavy-duty clear plastic envelope shall be provided, securely attached to the inside wall
of the cabinet or cabinet door, for stowing cabinet wiring diagrams and equipment manuals.
Minimum dimensions shall be 9 inches wide by 12 inches deep.
3. Electrical Components, Connecting Cables and Wiring.
a. Provide cabinets equipped and configured with internal power components as shown in
the contract documents.
b. One four position service entrance terminal block with tin plated aluminum connectors,
nickel plated steel screws, and a current rating up to 70 Amps.
c. One 20 Amp single pole breaker (Main).
d. One 15 Amp single pole breaker (Equipment).
e. One 15 Amp single pole breaker (Auxiliary).
f. One 120/240 VAC surge protector with surge current at minimum of 100 KA, nanosecond
response time, and an operating temperature of -40°F to +185°F.
g. One auxiliary four-terminal electrical block rated for a maximum 250 VAC RMS maximum
voltage and 20 Amps current.
h. One 15 Amp GFCI receptacle in Ivory color.
i. One 15 Amp Duplex receptacle in Ivory color.
j. One ten outlet, remotely resettable, Power Distribution Unit with eight individually switched
circuits and two unswitched (always on) outlets. Built in surge suppressor, lithium-ion
battery, resettable circuit breaker, minimum cord length of 6 feet, and a 10/100
autosensing, Static IP, RJ-45 Ethernet Interface.
k. One seven tapped Ground Bar.
l. One seven tapped Neutral Bar.
m. All miscellaneous wiring, harnesses connectors and attachment hardware.
n. All conductors used on the cabinet wiring shall be No. 14 AWG or larger with a minimum
of 19 strands. Conductors shall conform to NEC.
4. Ventilation.
a. Vents.
1) Furnish cabinets containing a suitably designed rain tight vent or vents that:
a) Are equipped with suitable screens or dust filters, and
b) Allow the release of excessive heat and/or any explosive gases which may enter
the cabinet.
2) Ensure when filters are utilized, positive retainment is provided on all sides to prevent
warpage and entry of foreign matter around the edges.
3) The filters shall be dry type, easily removed and replaced, and standard dimensions
commercially available.
b. Vent Fan.
1) A thermostatically controlled vent fan is furnished to provide air circulation within the
cabinet.
2) The thermostat controlling the fan is manually adjustable to turn on between 90°F and
150°F with a differential of not more than 10°F between automatic turn on and turn off.
DS-23074, Page 10 of 39
3) The fan is located with respect to the vent holes to direct the bulk of the air flow over
the internal components within the cabinet.
4) Ventilation fan shall be fused separately and wired after the main AC+ circuit breaker.
5. Grounding.
a. The cabinet internal ground shall consist of one or more ground bus-bars permanently
affixed to the cabinet and connected to the grounding electrode.
b. Use bare stranded No. 6 AWG copper wire between bus-bars and between the bus-bar
and grounding electrode.
c. Each copper ground bus-bar shall have a minimum of 20 connector points. Each connector
point shall be capable of securing at least one No. 6 AWG conductor.
d. AC neutral and equipment ground wiring shall return to bus-bars.
6. Pedestal.
a. Clean-cut in design and appearance to match cabinet.
b. Dimensioned as identified in the contract documents.
c. Corrosion resistant, NEMA Type 3R compliant, constructed of welded sheet aluminum with
a minimum nominal thickness of 1/8 inch.
d. Complete with all stainless steel hardware.
e. Meet the requirements of ASTM B-209 for 5052 H-32 aluminum sheet. The aluminum shall
be smooth and the exterior shall be left in its unpainted natural color.
f. Effectively sealed to prevent the entry of rain, dust, and dirt.
g. All exterior seams shall be continuously welded.
h. Edges, seams, fittings, and hardware shall be finished free from burrs and sharp edges.
G. Conduit.
1. High Density Polyethylene Conduit.
a. HDPE conduit shall be smooth wall and orange in color for communications.
b. HDPE conduit shall be smooth wall and orange, red, or black with red stripe in color for
power. Verify conduit color requirements with local electrical utilities.
c. Comply with ASTM F 2160 (conduit) and ASTM D 3350 (HDPE material), minimum SDR
13.5 or 11 as specified in the contract documents.
d. Sequential foot markings printed on HDPE.
e. Continuous reel or straight pieces to minimize splicing.
f. For dissimilar conduit connections provide an adhesive compatible with both materials.
2. Rigid Steel Conduit
Comply with Article 4185.09 of the Standard Specifications.
3. Electric Metallic Tube Conduit
a. Listed and labeled in accordance with NEC.
b. EMT conduit shall be steel.
c. Comply with UL 797 and UL Category Control Number FJMX.
d. Zinc alternate corrosion-resistant coating exterior.
e. Zinc with organic top coating interior coating.
f. EMT fittings shall comply with UL 514B and UL Category Control Number FKAV.
g. EMT fittings shall be steel die cast.
h. Coupling shall use compression coupling or raintight compression coupling with
distinctive color gland nut setscrew coupling. Setscrew couplings with only a single screw
per conduit is unacceptable.
H. Handholes.
1. General.
a. Constructed of epoxy or polyester resin mortar with woven glass fiber reinforcement.
DS-23074, Page 11 of 39
b. Handhole materials shall not support combustion when tested in accordance with ASTM D
635.
c. Water absorption shall not exceed 2% of the original weight of material under test
conditions per ASTM D 570.
d. Functional without failure throughout a temperature range of -50°F to +170°F.
e. Walls shall not deflect more than 0.24 inches per foot of length of box when installed and
subject to an ASTM C 857 TIER 22 load.
f. Meet or exceed ANSI/SCTE 77 requirements.
g. Li
- Package Files
- Name
- 15DEC353\Plan\79-0806-518\79-0806-518_C.pdf
- Bytes
- 1896532
- Name
- 15DEC353\Plan\79-0806-550\79-0806-550_C.pdf
- Bytes
- 15945532
- Name
- 15DEC353\Prop\DS-23074.pdf
- Bytes