The construction of ± 0.25 miles of dirt to pave roadway construction, the construction of 0.25 LM of dirt road grading, including ± 340 tons of 9.5 mm Superpave, ± 0.50 LM striping, ±3,239 SY of 8" soil cement construction base course, and all appurtenances necessary for a complete job.
AB-1
ADVERTISEMENT FOR BIDS
Sealed bids will be received for the TIA 2 Band 1: Dirt to Pave at the Scotland
City Hall, 969 Main Street, Scotland, Georgia 31083 until 1:00 P.M. (Local Time), on,
October 22, 2026, at which time they will be publicly opened and read.
The work under this Contract will consist generally of the following:
The construction of ± 0.25 miles of dirt to pave roadway construction, the
construction of 0.25 LM of dirt road grading, including ± 340 tons of 9.5 mm Superpave,
± 0.50 LM striping, ±3,239 SY of 8” soil cement construction base course, and all
appurtenances necessary for a complete job.
All work on the Project must be completed within 180 consecutive calendar days
of date of notice to proceed.
Bid shall be submitted on Bid Proposal Forms furnished for that purpose, in
accordance with the Contract Documents and the Plans and Specifications, which are on
file and may be reviewed at the office of Hofstadter and Associates, Inc., Consulting
Engineers, 4571 Arkwright Road, Macon, Georgia 31210.
Copies of Bid Forms, Plans, Specifications and Contract Documents may be
obtained from Hofstadter and Associates, Inc., 4571 Arkwright Road, Macon, Georgia
31210, upon deposit of $200.00 per set. No refund will be made for returned documents.
No bid will be considered unless sealed and filed with the City of Scotland prior
to the time set forth above, and accompanied by a Bidder's Bond, payable to the City of
Scotland, for 10 percent of the amount of the bid; to be forfeited as liquidated damages in
the event that the bid be accepted and the bidder fail to enter promptly into a written
contract and furnish the required Payment Bond and Performance Bond and Insurance
Certificates. Bids arriving after the designated time will be returned unopened.
The work consists of the construction of ±0.25 miles of dirt to pave roadway construction, 0.25 LM of dirt road grading, including ±340 tons of 9.5 mm Superpave, ±0.50 LM striping, ±3,239 SY of 8-inch soil cement construction base course, and all appurtenances necessary for a complete job.
We post new asphalt opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Georgia work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-66716-NONST-2027-000000001), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.