The DeKalb County Department of Watershed Management is requesting qualified firms to submit proposals to provide design and engineering services during the construction of Phase 3E facilities at the Snapfinger Advanced Wastewater Treatment Facility (SFAWTF). The Project is Phase 3E of the ongoing expansion at the SFAWTF as part of the County's $4.27 billion Capital Improvement Projects Program. The Project's anticipated work includes:
for the following Project elements: (1) adding a primary clarification unit process and (2) replacing dewatering centrifuges.
The selected firm will provide design and engineering services during construction of Phase 3E at the Snapfinger AWTF, including evaluation of alternatives, design, permitting, engineering services during construction, and post-construction services for adding a primary clarification unit process and replacing dewatering centrifuges.
We post new architecture and design opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Georgia work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-64400-NONST-2027-000000290), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.