The Project is to be performed pursuant to the AIA A133-2019 Standard Form of Agreement with payment based on the Cost of Work, plus a fee and with a guaranteed maximum price. The successful proposer, the Construction Manager at Risk (CM) shall serve as the contractor and construction manager for the Project. The project might include all typical construction trades, including mechanical, electrical, plumbing, demolition, painting, other finishes, as well as ADA compliance work and local ordinance compliance work for each campus and is mainly to provide metal and masonry fence to secure the perimeter of each campus.
Campus Enclosure - Phase Two Page 1 of 12
MUSCOGEE COUNTY SCHOOL DISTRICT
REQUEST FOR PROPOSAL FOR
GENERAL CONSTRUCTION SERVICES FOR
Campus Enclosure - Phase Two
Columbus, Georgia
GENERAL
Sealed proposals for general construction services for Campus Enclosure - Phase
Two, (the “Project”), at the following schools: Brewer (Gym), Clubview Elementary
School (Gym and Playground), Dimon Elementary School (Gym), Kendrick High
School, and Midland Middle School (Gym), Reese Road Elementary School
(Gym), Richards Middle School, Waddell Elementary School (Gym), and Veterans
Memorial Middle School, will be received by the Muscogee County School District
(the “School District”), in the Office of the Director of Construction at the 5661
Lorenzo Road, Columbus, Georgia 31904, until 2 p.m., Wednesday January 6,
2027. Proposals received after this time will not be accepted. All proposals will be
opened at the time and place designated in the Request for Proposal for the Project
(the “RFP”), and no information contained in the proposals received will be
disclosed prior to the School District awarding the contract.
The Project is to be performed pursuant to the AIA A133-2019 Standard Form of
Agreement with payment based on the Cost of Work, plus a fee and with a
guaranteed maximum price. The successful proposer, the Construction Manager
at Risk (CM) shall serve as the contractor and construction manager for the
Project.
The project might include all typical construction trades, including mechanical,
electrical, plumbing, demolition, painting, other finishes, as well as ADA
compliance work and local ordinance compliance work for each campus and is
mainly to provide metal and masonry fence to secure the perimeter of each
campus.
The project is mainly to provide metal and masonry fence to secure the perimeter of each campus at the following schools: Brewer (Gym), Clubview Elementary School (Gym and Playground), Dimon Elementary School (Gym), Kendrick High School, Midland Middle School (Gym), Reese Road Elementary School (Gym), Richards Middle School, Waddell Elementary School (Gym), and Veterans Memorial Middle School. The work may include all typical construction trades, including mechanical, electrical, plumbing, demolition, painting, other finishes, as well as ADA compliance work and local ordinance compliance work for each campus. The services will consist of pre-construction and construction services which may proceed concurrently. Pre-construction services include cost estimating, constructability analysis, and scheduling and phasing of the work. The CM will assist the School District and the Project Architect in finalizing the phasing and scheduling of the work, and value engineering of the Project. Substantial Completion shall occur no later than Saturday July 24, 2027.
We post new fencing opportunities in Georgia as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: Georgia Procurement Registry (solicitation PE-55046-NONST-2027-000000030), retrieved via the Georgia Procurement Registry (DOAS). View the official posting, and always confirm requirements and deadlines with the issuing agency.