SJSU is requesting SOQs from interested qualified contractors for a TOCA Master Enabling Agreement for various types of projects
24 September 2026
SJSU RFQ TOCA MEA
SJSU is requesting SOQs from interested qualified contractors for a TOCA Master Enabling Agreement for various
types of projects
24 September 2026
Open 9/24/2026, 3:00 PM PDT Type Request for Qualification
Close 10/23/2026, 3:00 PM PDT Number SJSU-RFQUAL-00000844-2026
Currency US Dollar
Sealed Until 10/23/2026, 3:00 PM PDT
24 September 2026
Contacts
Mel Vierra
melissa.vierra@sjsu.edu
Phone +1 408-924-1642
24 September 2026
Commodity Codes
None Added
24 September 202624 September 202624 September 2026
Description
The Board of Trustees of the California State University is requesting Statements of Qualifications (SOQ)
from interested and qualified general contractors (Respondents) to provide Collaborative (Progressive)
Design Build (CDB), and Construction Manager at Risk (CMAR) services the design,
preconstruction, construction management, and/or construction of a portfolio of projects under a master
enabling agreement.
The delivery method for this contract is Task Order-Construction Agreement for Multiple Projects— Master
Enabling Agreement (TO-CA MEA). The Trustees will issue two types of agreements under the TO-CA
MEA, a Task Order Service Agreement (TOSA) for the design and
preconstruction phase services and a Task Order Construction Agreement (TOCA) for the construction
phase.
Provide Collaborative (Progressive) Design Build and Construction Manager at Risk services for the design, preconstruction, construction management, and/or construction of a portfolio of projects under a master enabling agreement. The Trustees will issue Task Order Service Agreements for design and preconstruction phase services and Task Order Construction Agreements for construction phase work.
We post new general contractors opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most California work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: California State University (CSUBuy) (solicitation 1449962), retrieved via the CSUBuy SciQuest procurement portal. View the official posting, and always confirm requirements and deadlines with the issuing agency.