The Project includes improvements at the City of Wharton Wastewater Treatment Plant No. 1, the Alabama Road Lift Station, and the Park Lane Lift Station.
Work generally consists of rehabilitation, replacement, and installation of wastewater treatment process equipment, lift station upgrades, piping and valves, chemical systems, solids handling equipment, electrical and control systems, and associated site improvements, while maintaining continuous operation of existing facilities.
The Work will require coordination with Owner operations and include temporary bypass pumping and phased construction.
This project is funded in part by the Texas General Land Office (GLO) Community Development Block Grant (CDBG) program and is subject to all applicable federal requirements. Bidders must comply with all applicable federal labor standards, including Davis-Bacon Act and applicable Section 3 requirements.
Type of work: Wastewater treatment plant and lift station improvements
Pre-bid meeting: October 6, 2026 at 9:00 AM (Chicago) — City of Wharton City Hall, 120 East Caney Street, Wharton, Texas 77488 — Non-mandatory. Bidders may attend in person at City Hall or virtually via MS Teams. A coordinated non-mandatory site visit will be held immediately following the pre-bid conference, anticipated to begin at approximately 9:30 AM.
Bid opening: October 22, 2026 at 2:00 PM (Chicago) — City of Wharton City Hall, 120 East Caney Street, Wharton, Texas 77488 — Sealed bids must be received by the City Secretary at City Hall no later than 2:00 PM. Bids will be publicly opened and read at that time. The bid opening may also be attended virtually via MS Teams.
Questions due: October 13, 2026 at 5:00 PM (Chicago)
Questions asked: 4
Bid documents (download requires a free CivCast account):
Work generally consists of rehabilitation, replacement, and installation of wastewater treatment process equipment, lift station upgrades, piping and valves, chemical systems, solids handling equipment, electrical and control systems, and associated site improvements, while maintaining continuous operation of existing facilities. The Work will require coordination with Owner operations and include temporary bypass pumping and phased construction.
We post new electrical opportunities in Texas as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Texas work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: CivCast (project 6ab389b8b2086ae4111c4bb6), retrieved via CivCast, the bid board Texas civil engineers advertise on. View the official posting, and always confirm requirements and deadlines with the issuing agency.