Major items of work include:
Removal and replacement of the existing Clarifier No. 2 components, including but not limited to, center drive assembly with gear drive and motor with over-torque protection, center drive cage, center support column with inlet openings, feedwell, effluent weir plates, sludge collection arms with rake blades, squeegees, and suction duct, sludge collection manifold, full surface scum skimming equipment, scum baffle plates, anchor bolts and assembly fasteners, clips, supports, NPW line and sprayers, mechanical/structural/electrical equipment and all controls, piping, all required appurtenances for a complete and operational system, and all items and descriptions shown in the Construction Drawings and/or described in the specifications.
Pre-bid meeting: November 5, 2026 at 2:00 PM (Chicago) — Microsoft Teams https://teams.microsoft.com/meet/215266400825677?p=LoLy9O9GUh5YpQsVJV — Attendance at the pre-bid meeting is non-mandatory, however, bidders are encouraged to attend
Bid opening: December 1, 2026 at 2:00 PM (Chicago) — City of Richmond, City Hall, 1517 Thompson Rd., Richmond, Texas 77469 — All bids will be presented in person and opened in person at the following time and location: City of Richmond - City Hall, 1517 Thompson Rd. Richmond, Texas 77469
Questions due: November 16, 2026 at 12:00 PM (Chicago)
Questions asked: 1
Bid documents (download requires a free CivCast account):
Major items of work include: Removal and replacement of the existing Clarifier No. 2 components, including but not limited to, center drive assembly with gear drive and motor with over-torque protection, center drive cage, center support column with inlet openings, feedwell, effluent weir plates, sludge collection arms with rake blades, squeegees, and suction duct, sludge collection manifold, full surface scum skimming equipment, scum baffle plates, anchor bolts and assembly fasteners, clips, supports, NPW line and sprayers, mechanical/structural/electrical equipment and all controls, piping, all required appurtenances for a complete and operational system, and all items and descriptions shown in the Construction Drawings and/or described in the specifications.
We post new plumbing opportunities in Texas as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most Texas work asks for the two below, and the solicitation documents are where it’s stated. Apply straight through for it — or prequalify once and skip the application on both.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: CivCast (project 6aa16ea92419b8d5ec06e90e), retrieved via CivCast, the bid board Texas civil engineers advertise on. View the official posting, and always confirm requirements and deadlines with the issuing agency.