Ashe Plantation Lift Station 2

Open — see notice·Electrical, Plumbing, Demolition / Abatement, ElevatorView official posting ↗
Issuing agency
City of Charlotte
Category
Construction
PIN
2027-Q2(Apr-Jun)-CW-19822
Location
Charlotte, NC
Posted
Jul 9, 2026
Takeaways by LightRFP AI
  • The City of Charlotte is soliciting bids for the construction of a 250,000 gallon-per-day duplex lift station and demolition of an existing wastewater treatment package plant.
  • The project includes an emergency containment basin, upsizing of a gravity sewer, installation of an 8-inch force main, and a new wet well.
  • The estimated total project value is between $5,000,000 and $9,999,999.
  • The anticipated posting date is 2027-05-01.
  • The City plans to require a Bid Bond, Payment Bond, and Performance Bond.
  • The City anticipates setting subcontractor utilization goals for MBE and WBE.
  • Requirement: Bid Bond - City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.
  • Requirement: Payment Bond - City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.
  • Requirement: Performance Bond - City required Bond to ensure satisfactory completion of a project by the vendor.

AI-generated, verify all details against the official documents.

Description

This contract will be for the construction of a 250,000 gallon-per-day duplex lift station and demolition of the existing wastewater treatment package plant. Included will be the construction of an emergency containment basin, upsizing of an existing gravity sewer, installation of a portion of an 8″ force main, new wet well. Owner plans to procure pumps and standby generator for the project.

Anticipated posting date: 2027-05-01

Requirements

Insurance Requirements
The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:Automobile-For automobile operations liabilityConstructions Bonds-For bidding, payment, completion of construction projectsGeneral Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injuryWorkers Compensation-For lost wages and medical expenses of injured workers

Bonding Requirements
The City plans to require the following bond(s) for this solicitation:Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor.

Estimated Total Value
The total project value is anticipated to be:$5,000,000 - 9,999,999

Utilization
The City anticipates setting goals for the following types of subcontractor utilization:MBE-Minority Business EnterpriseWBE-Women Owned Business Enterprise

Contract Term
The term of the project is anticipated to be:Through Project Completion

Contact

Name
Abby Dolan
Address
Charlotte, NC
Full source recordfrom City of Charlotte
Dept
CW
Slug
Ashe-Plantation-Lift-Station-2
Title
Ashe Plantation Lift Station 2
Detail
Text
Skip to main content English is your current preferred language. MENU Open Search Search Home / Growth and Development/ Doing Business with the City / Contract Opportunities / Ashe Plantation Lift Station 2 Ashe Plantation Lift Station 2 Anticipated Posting Date: 2027-05-01 Reference number2027-Q2(Apr-Jun)-CW-19822 StatusUpcoming SummaryThis contract will be for the construction of a 250,000 gallon-per-day duplex lift station and demolition of the existing wastewater treatment package plant. Included will be the construction of an emergency containment basin, upsizing of an existing gravity sewer, installation of a portion of an 8″ force main, new wet well. Owner plans to procure pumps and standby generator for the project. Requirements Insurance Requirements Bonding Requirements Estimated Total Value Utilization Contract Term Print Page Contact details Abby Dolan adolan@charlottenc.gov Bid Details Department: Charlotte Water - Construction Commodity Code(s): 91200, 91359, 91389 Related Information Facebook X Back to top Accessibility Policy ADA Accommodations Sitemap Public Records Privacy & Legal Notices Contact Us Subscribe/Notify Me CharMeck Alerts CATS Riders Alerts Social Facebook LinkedIn Twitter Instagram © 2026 City of Charlotte | Powered by Granicus
Contact
Name
Abby Dolan
Email
adolan@charlottenc.gov
Requirements
**Insurance Requirements** The City requires the awarded vendor(s) to obtain and maintain the following insurance coverage types:Automobile-For automobile operations liabilityConstructions Bonds-For bidding, payment, completion of construction projectsGeneral Liability-For bodily injury or property damage, arising from products, premises, completed work, personal & advertising injuryWorkers Compensation-For lost wages and medical expenses of injured workers **Bonding Requirements** The City plans to require the following bond(s) for this solicitation:Bid Bond-City required Bond to ensure that vendors do not retract bids from the time they submit a bit until the contract has been executed.Payment Bond-City required Bond to ensure that subcontractors and/or suppliers are paid for any work performed.Performance Bond-City required Bond to ensure satisfactory completion of a project by the vendor. **Estimated Total Value** The total project value is anticipated to be:$5,000,000 - 9,999,999 **Utilization** The City anticipates setting goals for the following types of subcontractor utilization:MBE-Minority Business EnterpriseWBE-Women Owned Business Enterprise **Contract Term** The term of the project is anticipated to be:Through Project Completion
Status
Upcoming
Reference
2027-Q2(Apr-Jun)-CW-19822
Anticipated
May 1, 2027
Description
This contract will be for the construction of a 250,000 gallon-per-day duplex lift station and demolition of the existing wastewater treatment package plant. Included will be the construction of an emergency containment basin, upsizing of an existing gravity sewer, installation of a portion of an 8″ force main, new wet well. Owner plans to procure pumps and standby generator for the project.