Update: 10/28/2026 - Included RFIs, and Drawings
The 184 Wing is requesting the purchase of one (1) Control power Transformer and three (3) Transformer fuses to replace Building 16 indoor switchgear transformer including installation. See attached documents/ links for Specifications or Salient Characteristics - B16 Transformer and additional solicitation information.
Site Visit: Nov 10 2026 @0900 - Details in the posting links
The contractor must provide a complete and usable system including removal of the existing GE/ITI control power transformer, rigging, electrical reconnection, testing, commissioning, and disposal. The replacement transformer should preferably fit within the existing enclosure (33” W x 90” H x 54” D). The termination configuration required is the Stubs Up option. The awarded vendor will coordinate electrical shutdown and restoration with local utilities and the 184 Engineering Team. Equipment delivery timeline will be considered in evaluation.
We post new goods & materials opportunities in Kansas as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"67221-9000""MCCONNELL AFB""KS""USA""KO DODAAC FOR KSANG DO NOT DELETE""52955 JAYHAWK DR SUITE 153""Transformer Data Plate.jpg"9373532"file"".jpg""1""2026-10-28T19:54:32.37+00:00""6d44d30a204e490dbca736ace1afcdfc""public""0""public""ce13103af9f74460a96176fbbb19943c""0"5"0""LV Termination.jpg"9355921"file"".jpg""1""2026-10-28T19:54:32.37+00:00""51e79a9ee89b444590c24ba2f34f8c9b""public""0""public""1575dd69a1024a1690b2509b1b38afc9""0"4"0""HV Termination.jpg"8512749"file"".jpg""1""2026-10-28T19:54:32.37+00:00""de41baff93974229a1089303557bd5a2""public""0""public""de4184339928490bb298d4a01a00daf8""0"3"0""B16 Switchgear Transformer RFIs Current as of 28Oct26.xlsx"17785"file"".xlsx""1""2026-10-28T19:54:32.37+00:00""74008d7db6d24e8b9bfbe0892b57cb4f""public""0""public""206a77ccfcbf4784b5e4b5f73d44f361""0"2"0""B16 Transformer Drawings.pdf"127730"file"".pdf""1""2026-10-28T19:54:32.37+00:00""5d9fbeda35d5442e87d952b344c12ee4""public""0""public""5950e1061ce94bbe805f7d071eebd606""0"1"0""https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?noticeId=W50S7X27Q0001¬iceType=CombinedSynopsisSolicitation"0"link""1""2026-10-26T16:47:49.344+00:00""4939da069abe470499a53dad7b4fe847""public""0""PIEE Solicitation Module Link for W50S7X27Q0001""public""276a02676f6146a4a6caf2bf845c4490""0"4"0""https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml"0"link""1""2026-10-26T16:47:49.344+00:00""15f41a1b42044af0a2e30d0899e14f31""public""0""Web Based Training for the PIEE Solicitation Module""public""3debb3644ab9430bbb59fb643c9971d7""0"3"0""https://www.acq.osd.mil/asda/dpc/ce/cap/docs/piee/PIEE_Solicitation_Module_Vendor_Access_Instructions.pdf"0"link""1""2026-10-26T16:47:49.344+00:00""d0eff3eb43f04d98b89be4bb97c34feb""public""0""Registration Instructions for the PIEE Solicitation Module""public""810d7ad66fc648e384ee8cc0e2065a4e""0"2"0""https://toolbox-piee.eb.mil/"0"link""1""2026-10-26T16:47:49.344+00:00""a6959958cef74703a0dbfa89bb5f676f""public""0""Department of Defense Procurement Toolbox""public""62993156d30d4530829a3e8e977bc377""0"1"0"Most Kansas work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what an agency asks to see before they take your bid seriously.
Source: SAM.gov (notice 97aede81f52647ce88b6fbb8946442a6), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.