The Princeton Plasmas Physics Laboratory is seeking a qualified contractor to replace roofing on two existing roofs. The (C40 RF Building & C41 CS Building) which are past their useful life requiring costly maintenance to upkeep. Severe water infiltration occurs regularly at failing joints, punctures, and flashing. Portions of existing metal coping have pulled away during storm events causing large sections of membrane to separate from the substrate. A catastrophic failure to one of these roofs would negatively impact the ability to conduct the top priority experimental operations in the Laboratory.
The Subcontractor shall provide all materials, labor, supervision, equipment, and expertise required to replace the noted roofs and specified components per the associated contractdesign documents. Construction scope includes the following:
Remove and replace existing built-up roofs at PPPL. Buildings include:
a. C40 – RF Building
b. C41 – CS Building
All work shall be perfomed IAW SOW titled: C40 & C41 RF ROOF REPLACEMENT CONSTRUCTION dated 28 Aug 2026
Only some of the solicitation documents have been posted. The remaining documents will be released to offerors (on an as requested basis) when we receive the following information and documents
(1) An e-mail confirmation of your intent to participate in the site visit/pre-bid meeting scheduled for 11/17/26
(2) A signed solicitation acknowledgement form
(3) Identification of your lead proposal manager for this solictation via e-mail
(4) A written request for project drawings (see attached form)
The Subcontractor shall provide all materials, labor, supervision, equipment, and expertise required to remove and replace existing built-up roofs on C40 - RF Building and C41 - CS Building and specified components per the SOW titled C40 and C41 RF Roof Replacement Construction dated 28 Aug 2026 and the Michael Graves RF Roof Replacement Specification.
"Richland""WA""US""2345 Stevens Drive""08540""Princeton""NJ""USA""100 Stellarator Rd.""RFP 26-081JR Request for Project Drawings.pdf"76905"file"".pdf""1""2026-11-02T14:48:28.685+00:00""f480a483e00e45ff9b000ec98ead1917""public""0""public""7ccd9c6e800c41c59c0ad5cacec0cb48""0"12"0""RFP 27-005JR Offeror Information and Pricing Form.pdf"100647"file"".pdf""1""2026-10-30T22:42:25.337+00:00""2661e4ef979e4b71a7504887607328f4""public""0""public""5bc588141140400dabf19bf134abeac7""0"11"0""RFP 27-005JR Invitation Cover Letter.pdf"191561"file"".pdf""1""2026-10-30T22:42:25.337+00:00""894cd07d2b224b2895c26fcaefc1e8eb""public""0""public""7cbbec13992d47ef86eadfb22c35a543""0"10"0""RFP 27-005JR Instructions for Proposal Preparation.pdf"216653"file"".pdf""1""2026-10-30T22:42:25.337+00:00""9d74191b17f2442c8ae9b79a4492000a""public""0""public""81dbfe34390f46d3a4cbc4da830c7092""0"9"0""RFP 27-005JR Evaluation and Basis for Award.pdf.pdf"191879"file"".pdf""1""2026-10-30T22:42:25.337+00:00""3a1d7c7324e54f64b2bf59a144f7b72c""public""0""public""aa4a172ca8be459580f7e2672d9da1ed""0"8"0""RFP 27-005JR E-Verify Certification Document.pdf"111242"file"".pdf""1""2026-10-30T22:42:25.337+00:00""8599dee529a340b7ba5450cd4b39a181""public""0""public""32b6115f34fb4aa9b2d77d81bb072f26""0"7"0""Payment Bond SF25A-23a.pdf"716931"file"".pdf""1""2026-10-30T22:42:25.337+00:00""4cb2f91d1cec4aa3a71d11691a55d4ea""public""0""public""cf275921bf914f88bd73746e34d89461""0"6"0""RFP 27-005JR Acknowledgment Form.pdf"89164"file"".pdf""1""2026-10-30T22:42:25.337+00:00""633cd1bca7184fdc9f174af34bfadd09""public""0""public""3bce348bc0bf4f00bfb7ee023b993f13""0"5"0""Performance Bond SF25.pdf"726819"file"".pdf""1""2026-10-30T22:42:25.337+00:00""e0659125da154aba86c325fd5f839b13""public""0""public""8b17fbcfedae4386aaad6431e785fde9""0"4"0""7. PPPL PQA Supplier Quality Survey R2 Construction.pdf"1089287"file"".pdf""1""2026-10-30T22:42:25.337+00:00""4fac3cd5c8e848a0b4defe782a4ce30f""public""0""public""6cf231a2d9bb47de83f88391ebbaf8a4""0"3"0""PPPL-PD-G Provisions and Conditions for FP Construction Subcontracts_ Rev 8_ 052022.pdf"260300"file"".pdf""1""2026-10-30T22:42:25.337+00:00""6c8a1ba42ee24bafa3a38bc5c20199c7""public""0""public""2b7f762f423f42808070a1476fcad2a5""0"2"0""PPPL-PD-T Provisions For Work Performed On The PPPL Site-Rev 6_Oct2026.pdf"207448"file"".pdf""1""2026-10-30T22:42:25.337+00:00""d004c4afce654e3483b085ac0adbb9f5""public""0""public""cfafb64257104af38d83f21083b05bf7""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: SAM.gov (notice 53c3998384b44325bf74a8d58fc322b9), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.