This intent of this project is to construct approximately 0.5 miles of
barbwire fence lines near Kalamazoo Campground on the Ely Ranger District. Construct two
barbwire drift fences totaling approximately 0.5 miles in length to exclude active grazing within
Kalamazoo Campground. Livestock in the campground presents a safety hazard and has resulted in
numerous complaints from the public. In addition, limiting livestock activities within the
campground will also extend protection of newly installed recreational infrastructure. This project
includes construction of approximately 2,500 feet of new barbwire fence including installation of an
estimated four 12-foot wire gates as a lump sum.
Construct two barbwire drift fences totaling approximately 0.5 miles in length to exclude active grazing within Kalamazoo Campground. This includes construction of approximately 2,500 feet of new barbwire fence including installation of an estimated four 12-foot wire gates as a lump sum. All brace and anchor posts are to be schedule-40, galvanized steel except for wood posts located at the wire gates. Fences will end at natural rock barriers; a rock crib brace may be required at the northeast end. Fence wings will tie into existing cattleguards along FS Road 427. Clearing of vegetation is allowed as needed to ensure a straight fence, however heavy equipment will not be allowed to clear the fence lines. Chainsaws are allowed for vegetation clearing. Fence runs should not deviate more than 12-inches from a straight line between braces. Clear corridor to 8 ft total width (approx. 4 ft on each side of fence centerline) and 8 ft above ground. Slash generated from clearing shall be scattered outside the corridor; do not leave in ditches or roadways. Work shall be performed in accordance with specifications and drawings in the plan sheets, followed by the 'Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24).'
We post new fencing opportunities in Nevada as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""US""89431""SPARKS""NV""USA""SUPERVISOR'S OFFICE""1200 FRANKLIN WAY""C04 SF1442 - 1240LT27Q0025 - Combined SS.pdf"411342"file"".pdf""1""2026-11-05T16:41:32.596+00:00""932d51ca4a8446d9840e8a64841779f0""public""0""public""97f064710733418595f4df51fe5e0c5e""0"14"0""C04a Schedule of Items 1240LT27Q0025.xlsx"11975"file"".xlsx""1""2026-11-05T16:41:32.596+00:00""ad87099006c1451da2e5b262f03fe0e0""public""0""public""fdbc8d21355e4e1fac126136a7cd9701""0"12"0""C04b Kalamazoo SOW rev 1240LT27Q0025.pdf"139315"file"".pdf""1""2026-11-05T16:41:32.596+00:00""ea3293e1e3ee42909b98b072d5d407ad""public""0""public""077e4feb590e433e9e3f5a589c9a2606""0"10"0""C04c Maps-Drawings - KzooFenceRevkwsigned 1240LT27Q0025.pdf"3536380"file"".pdf""1""2026-11-05T16:41:32.596+00:00""e6324ab9cb04422383e28ae2091078c1""public""0""public""1c1f862c5ec24a4fbd365ba4628df5c2""0"8"0""C04d WD NV20260067 dtd 7-30-2026 1240LT27Q0025.pdf"5052265"file"".pdf""1""2026-11-05T16:41:32.596+00:00""34ea07b9be364993b79faff8c517f696""public""0""public""7b7563187c0b4a76a762e2a9027662aa""0"4"0""C04e Experience Questionnaire 1240LT27Q0025.docx"40992"file"".docx""1""2026-11-05T16:41:32.596+00:00""bbf9fe13688347b29755e2c389975224""public""0""public""74213ed1ce07437db29db049ad1f243e""0"3"0""C04f Performance Data Sheet 1240LT27Q0025.docx"13938"file"".docx""1""2026-11-05T16:41:32.596+00:00""5cc6a03746284618a46043e4608fead5""public""0""public""b71e374131f348989a4b8ddbf0daf221""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: SAM.gov (notice 21d31a2408dd4c2892c106c12736b7f7), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.