The Contractor shall provide all labor, supervision, materials, equipment, and incidentals necessary to identify, manage, and remediate environmental hazards including, but not limited to, lead, asbestos, mold, and other hazardous materials in compliance with all applicable federal, state, and local regulations.
Work shall include site assessments and testing; regulatory compliance and permitting; establishment of containment measures; abatement, removal, or encapsulation of hazardous materials; proper handling and disposal of waste; air monitoring and clearance testing; emergency response services; and complete documentation and reporting.
The Contractor shall coordinate all activities with the Owner and relevant stakeholders to ensure safe execution and minimal disruption. All work shall be performed in a safe, timely, and professional manner in accordance with JOC contract requirements.
RFQ Solicitation Timetable:
A conference will be held on 11/18/2026 at 11:00 A.M., via Microsoft Teams. Pre-bid Teams Meeting information: (646) 838-1534 Conference ID: (265 241 740 225 185 6**)** Passcode: dz6kX98T. Although attendance is not mandatory; it is strongly recommended that all interested vendors attend. In order to RSVP to the Pre-Bid Conference and obtain the Teams Meeting link to view the virtual conference email
acm.procurement@nycha.nyc.gov with the RFQ number as the Subject line to confirm attendance.
https://teams.microsoft.com/meet/2652417402251856?p=1XrYLH5wcW1xZssYrq
All questions related to this RFQ are to be submitted via email to the CPD Procurement Unit at acm.procurement@nycha.nyc.gov with the RFQ number as the Subject line by no later than 12/01/2026 on 2:00 P.M. Bidders will be permitted to ask additional questions at the Bidders Conference. Responses to all submitted questions will be available for public viewing in Sourcing under the RFQ.
Bid Submission Requirements:
Vendors shall electronically upload a single .pdf containing ALL components of the bid into iSupplier by the RFQ Bid Submission Deadline. NYCHA will NOT accept hardcopy Bids or bids via e-mail, fax, or mail.
Pre-Bid Conference: November 18, 2026, 11:00 A.M.
Site Visit: November 20, 2026, 11:00 A.M.
RFQ Question Deadline: December 01, 2026, 2:00 P.M.
Question and Answer Release Date: December 10, 2026
Instructions for registering for iSupplier can be found at http://www1.nyc.gov/site/nycha/business/isupplier-vendor-registration.page. After Bidder registers for iSupplier, it typically takes 24 to 72 hours for Bidders iSupplier profile to be approved.
It is Vendors sole responsibility to complete iSupplier registration and submit its Bid before the RFQ Bid Submission Deadline. NYCHA is not responsible for delays caused by technical difficulty or caused by any other occurrence.
For assistance regarding iSupplier please email procurement@nycha.nyc.gov
Provide all labor, supervision, materials, equipment and incidentals to identify, manage and remediate lead, asbestos, mold and other hazardous materials in compliance with federal, state and local regulations, including site assessments and testing, regulatory compliance and permitting, establishment of containment measures, abatement, removal or encapsulation, proper handling and disposal of waste, air monitoring and clearance testing, emergency response services, and complete documentation and reporting with coordination to ensure safe execution and minimal disruption in accordance with JOC contract requirements.
We post new interior maintenance opportunities as agencies publish them. Get them in one email — free, and unsubscribe whenever.
Most public work asks for the two below, and the solicitation documents are where it’s stated. Apply straight through for it — or prequalify once and skip the application on both.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: NYC City Record (request 20261030019), retrieved via NYC Open Data. View the official posting, and always confirm requirements and deadlines with the issuing agency.