RFP is hereby modified on 10/27/2026 to incorporate Offeror Questions and Responses.pdf
Request for Updated Proposal – SHB RF High Power Amplifiers (HPA)
The Statement of Work (SOW) and Engineering Specification document have been modified. Please review the updated documentation and submit a revised proposal that reflects the changes.
The proposal submission deadline has been extended to November 18, 2026.
This Request for Proposal (RFP) is for the procurement of two Sub-Harmonic Buncher (SHB) pulsed Radio Frequency (RF) High Power Amplifiers (HPA): one unit operating at 125 MHz and a second unit operating at 500 MHz. The proposed equipment must comply with the requirements outlined in the RFP, Sample Subcontract, updated SOW, revised Engineering Specification, and all other applicable enclosures.
The contractor will design, manufacture, test, and deliver two 25 kW pulsed solid-state RF high power amplifiers using LDMOS or GaN FET technology. The work includes completing preliminary and final design reviews, obtaining NRTL certification for both units, performing a 100-hour heat run reliability test and factory acceptance testing at the vendor's facility, packaging and shipping the units to LBNL in Berkeley, CA, providing installation and commissioning guidance on site, and conducting a site acceptance test. The contractor must also deliver complete documentation including manuals, schematics, parts lists, PLC/FPGA code, as well as certifications from a California licensed structural engineer for seismic anchoring. The contract is firm fixed price with a maximum delivery time of 18 months after receipt of order.
We post new goods & materials opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"Richland""WA""US""2345 Stevens Drive""94720""Berkeley""CA""USA""1 Cyclotron Rd""Offeror Questions and Responses.pdf"127140"file"".pdf""1""2026-10-27T22:59:15.911+00:00""bae4698668d14d19ae382a530fcbd73d""public""0""public""085a5e65d09044168f95f91d080b1df4""0"149"0""RFP-SHB pulsed RF HPA Rev. 1.pdf"323850"file"".pdf""1""2026-10-12T19:10:21.333+00:00""a7f0073a24eb4717aae361844d96a84c""public""0""public""7b6a7cfa2f05405c826cc6ef67263c72""0"148"0""Updated - SHB pulsed HPA ESD MARKUP Rev.1.pdf"524724"file"".pdf""1""2026-10-12T19:10:21.333+00:00""76a8f7994f574c7684e767c4b698c074""public""0""public""46f2fe68785d4677a26caa9a5e45a5df""0"146"0""Updated SHB pulsed HPA SOW MARKUP Rev.1.pdf"377940"file"".pdf""1""2026-10-12T19:10:21.333+00:00""fe408d4a8fe64e76a3ba2ba6761d978e""public""0""public""f2536a5284c94ab0a7b00edbd3d39651""0"144"0""Rep Cert- SHB pulsed RF HPA Rev1.docx"67675"file"".docx""1""2026-10-12T19:10:21.333+00:00""34642defea0745299ef8bd43ac7fdf74""public""0""public""fef65ec45abf4673bc08bd552a6d6c2b""0"142"0""Price Proposal Schedule Attachment B.xlsx"13513"file"".xlsx""1""2026-10-12T19:10:21.333+00:00""03e046eb08ce45dda52e0b73c7602d83""public""0""public""c720f3615de748c0a8e99622b61e5a8d""0"138"0""RFP SHB pulsed RF HPA ESD Response sheet.xlsx"12806"file"".xlsx""1""2026-10-12T19:10:21.333+00:00""5b516f886cfc4b63a07b3b36ca8eea70""public""0""public""bceba481937f414fac5395e632b83b8c""0"137"0""Sample Subcontract.pdf"261957"file"".pdf""1""2026-04-15T01:31:25.033+00:00""10f577b39a7946f094701d156693112d""public""0""public""0541072ef38941509909859443595723""0"125"0""Past Performance Reference Information Form.docx"31253"file"".docx""1""2026-04-15T01:31:25.033+00:00""1afab8b34a204207b4d9213655da7dcf""public""0""public""096ab0736ee24928b3d025177559d9eb""0"110"0""AL-1887-8780A SHB pulsed RF HPA ESD.pdf"2405474"file"".pdf""1""2026-04-15T01:31:25.033+00:00""63b184426b014d098fdda9d3d3a056fd""public""0""public""ce6f6be367434b929193c5971ce8ef69""0"107"0""AL-1887-8783A SHB pulsed RF HPA SOW.pdf"1347977"file"".pdf""1""2026-04-15T01:31:25.033+00:00""162a860920e24b229ad6e04134d59f54""public""0""public""6d8f0594de1f46c2b89f28d18a128de9""0"106"0""1 LBNL Electrical Equipment Build Standard V6.pdf"132499"file"".pdf""1""2026-04-15T01:31:25.033+00:00""741c6f46f1b84a59b03bee539042f15c""public""0""public""4a8d0b2e326e4e17b0b3554e729915b4""0"103"0""1a Appendix A Electrical Equipment Hazard Labeling.pdf"190555"file"".pdf""1""2026-04-15T01:31:25.033+00:00""0a234cb25fb64bb5b54bb68a238804e2""public""0""public""2803242039be450bac0c2aef2b8a9f9c""0"100"0""1b Appendix B Electrical Equipment Fabrication.pdf"590557"file"".pdf""1""2026-04-15T01:31:25.033+00:00""56215f78396b482992014ce8621305fb""public""0""public""fc76bf42427a4162842961b3613605f7""0"97"0""1c Appendix C Ground Hook Safety.pdf"23758"file"".pdf""1""2026-04-15T01:31:25.033+00:00""50b43e3bfafd4424b4ca914d95f65f8b""public""0""public""ab07373964d94f41991a345fdac8bdf5""0"94"0""1d Appendix D Rack Build Standard.pdf"310165"file"".pdf""1""2026-04-15T01:31:25.033+00:00""40b2241f335644d6a2d44193a26fe3ff""public""0""public""64d2f5378db342ddbd47c8a8555636a2""0"91"0""2 LBNL Electrical Safety Manual Revision 1.pdf"4395731"file"".pdf""1""2026-04-15T01:31:25.033+00:00""4645b0b8b268420598062d242ddbf059""public""0""public""5d7800cf5aaa448fbb886b0ce937246d""0"88"0""3 LBNL RPM on Safe Electrical Installations Policy.pdf"210509"file"".pdf""1""2026-04-15T01:31:25.033+00:00""ce777154d7244448bb488a6fcc93a20f""public""0""public""8d1f17e06aad4b47b08cd01a3049a83e""0"80"0""4 LBNL ES_H Manual (PUB-3000) Chapter 08 Electrical Safety Program.pdf"374534"file"".pdf""1""2026-04-15T01:31:25.033+00:00""16a6ca0a53664f46a6b46e3df657e6ea""public""0""public""d1e3ecccca154f159187cb4e63246f37""0"77"0""5 LBNL ES_H Manual (PUB-3000) Chapter 14 Electrical Equipment Safety Program.pdf"382420"file"".pdf""1""2026-04-15T01:31:25.033+00:00""be45f3dda3b44bb0bf68b4249d10b9c3""public""0""public""38f14e1bb4714785be5e2c01938881bc""0"74"0""6 LBNL RPM on Seismic Safety.pdf"214932"file"".pdf""1""2026-04-15T01:31:25.033+00:00""b787fb4ba2bd4035b284a71bdd6ec597""public""0""public""7b8ab1c98cb742268457c5268f1d2556""0"71"0""7 LBNL Lateral Force Design Criteria Resource Document (RD3.22) (version 18).pdf"2486485"file"".pdf""1""2026-04-15T01:31:25.033+00:00""57c77041da7a405c8bca45f537e4c818""public""0""public""2c2ba8141c7d4e42a38198ea957eaad5""0"68"0""8 LBNL RPM on Cranes Hoists and Rigging Safety.pdf"206619"file"".pdf""1""2026-04-15T01:31:25.033+00:00""a54f9578988748c9aa841dfc2478ebdd""public""0""public""a4e3a85571704b67a4e9a4b8359831ad""0"16"0""9 LBNL ES_H Manual (PUB-3000) Chapter 27 Cranes Hoists and Rigging Safety.pdf"460453"file"".pdf""1""2026-04-15T01:31:25.033+00:00""55ab3457b5a4413a93b6fefe79534b48""public""0""public""4f95b63e740248a9a0e561d2e1324d87""0"15"0""10 LBNL LBNL Facilities Master Specifications 260519.11_600 Volt Conductors and Cable.docx"22740"file"".docx""1""2026-04-15T01:31:25.033+00:00""066b89920b894e45b5b5aed2829a7ce9""public""0""public""f96d9bc0962f44839ad8dd230368f099""0"14"0""11 LBNL Facilities Master Specifications 260523_Low-Voltage Electrical Power Conductors and Cables.docx"24589"file"".docx""1""2026-04-15T01:31:25.033+00:00""d00fd3c22cbd4978bf35cd2f076947d4""public""0""public""d002d24bee3044828faa7f2e2df412f1""0"13"0""12 LBNL ES_H Manual (PUB-3000) Chapter 43 Non Ionizing Radiation.pdf"255749"file"".pdf""1""2026-04-15T01:31:25.033+00:00""9c8791dd9c8a41fab26a0e51f765515c""public""0""public""f557b13fefb1438eb5131a491ac87e71""0"11"0""13 LBNL PUB 3111 Quality Assurance Program Description.pdf"3192190"file"".pdf""1""2026-04-15T01:31:25.033+00:00""553b18dd34244312a9d2b62831432489""public""0""public""b0258e1e9d7b4950807e324a3243d521""0"4"0"Most California work asks for the two below, and the solicitation documents are where it’s stated. One prequalification covers both — on this bid and the next.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what an agency asks to see before they take your bid seriously.