The purpose of this amendment is the following:
submittal dates of 11/23/2026.
2.Consolidated questions and answers (C06_Questions and Clarifications)
repairs
This project involves the repair and resurfacing of three parking lots on the Arapaho and Roosevelt National Forest and Pawnee National Grassland including crack sealing, pavement patching, seal coating and re-striping.
NAICS code 237310 - Highway, Street, and bridge Construction as a 100% SB Set Aside.
Size standard $45 Million.
PSC Code Y1LB - CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES,
Questions Due: November 6th, 2026 at 14:00 Eastern Standard Time(EST).
Quotes Due:November 23rd, 2026 at 14:00 Eastern standard Time (EST).
All questions and quotes relating to this Solicitation shall be submitted to
Contract Specialist, Jordan Carlsen at Jordan.Carlsen@usda.gov by the deadlines
stated above. Late quotes will be rejected.
The contractor cleans all parking lot surfaces, fills cracks, removes and replaces damaged areas by infrared machine patching, seal coats the entire surface with slow-setting asphalt emulsion sealcoat, and restripes. Quantities are Boulder: 2,000 LF crack sealing, 37,300 SF sealcoat, 6 patches; Fort Collins: 2,500 LF crack sealing, 54,800 SF sealcoat, 8 patches; Clear Creek: 2,000 LF crack sealing, 27,350 SF sealcoat, 6 patches, each plus mobilization and striping. Work is performed at occupied sites with phased closures, one week per site, with weekly progress reports and asphalt product submittals under Forest Service Supplemental Specifications and FP-24.
"US""US""844012310""Ogden""UT""USA""324 25th ST""Attachment 6 C06 Wage Determination C0202600002.pdf"2020560"file"".pdf""1""2026-11-17T19:38:16.009+00:00""4a316c00a59146f98e008da6ea97f157""public""0""public""48c6593b6a124d5997281e207c8dea11""0"10"0""C06_Questions and Clarifications R.docx"225989"file"".docx""1""2026-11-17T19:38:16.009+00:00""0233d9dfbbe14067a9d0f8296aba41e1""public""0""public""9726cf68807047d09bd139cb017e6d56""0"9"0""Attachment 5 C06 416 Specifications Administrative parking lot repairs.pdf"212919"file"".pdf""1""2026-11-17T19:38:16.009+00:00""870053a250df42c9a79442cd3fca4a9c""public""0""public""61a3ffde9c164c3e9fa4a90d40c942d2""0"8"0""1240LT27Q0019.pdf"89463"file"".pdf""1""2026-11-17T19:38:16.009+00:00""0df50b281e0141319f655deb2385335e""public""0""public""8b23295c9b48413da059a798683c006b""0"7"0""Attachment 1 - C05 Schedule of Items.xlsx"13890"file"".xlsx""1""2026-10-22T13:04:57.159+00:00""fb54d4ddbaf54a4f91ee6a9dda8536f9""public""0""public""a0e30fc9970d477ab9ad741dcd38d296""0"6"0""C05 1240LT27Q0019.pdf"383962"file"".pdf""1""2026-10-21T18:33:01.735+00:00""8c6c36fe77014da08981816e4ba42b5f""public""0""public""db6b3e3a899645d4a836e749113c7f8f""0"5"0""Attachment 3 - C05 Site Maps.pdf"3047698"file"".pdf""1""2026-10-21T18:33:01.735+00:00""d8f4ab627bca444993d90261cc5bb96c""public""0""public""965d6ff0b2a4407c88a722b42ed97fb1""0"4"0""Attachment 2 - C05 FSSS.pdf"521511"file"".pdf""1""2026-10-21T18:33:01.735+00:00""116b8417292647768a9c27fb2520c379""public""0""public""f59be847c4c24789b637467f70df900e""0"2"0""Attachment 4 - C05 Statement of Work.pdf"181888"file"".pdf""1""2026-10-21T18:33:01.735+00:00""ac12e045c74344e2bf6de083df21045e""public""0""public""0c4a82b5daa447848efb8c00919940d1""0"1"0"Read from this solicitation’s own documents — each row shows the exact quote it was matched to. Confirm final amounts and forms with the issuing agency before you submit.
A surety’s written statement that it expects to bond you up to a stated amount, subject to final underwriting. It’s what a GC or agency asks to see before they take your bid seriously.
Source: SAM.gov (notice 07bd2045bcb54b8cafd5f2339ee61440), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.