Bremerton right-of-way performance bonds.
Quote on review.

Work in a public right-of-way in Bremerton, Washington needs a use permit and a performance deposit of at least 150% of the estimated value of the work plus the cost to restore existing improvements. A surety bond is one accepted way to post it. A surety specialist returns your price, usually within one business day.

✓
Required by Bremerton Municipal Code § 11.02.220 for work under a right-of-way use permit
✓
Set at no less than 150% of the estimated work plus restoration of existing improvements, as the Director sets it
✓
Priced on review — the application asks for the contractor, the project address and the completion date, nothing about your credit
Underwrittenthe City sets the amount1 daytypical specialist replyNo credit reviewnot even a soft pull
Trusted by industry leaders
New York City Economic Development Corporation (NYCEDC)
Blumenfeld Development Group (BDG)
Capital Development Partners
McKinney Properties
Terra Capital
JLL (Jones Lang LaSalle)
Triple Five Group
The Georgetown Company
New York City Economic Development Corporation (NYCEDC)
Blumenfeld Development Group (BDG)
Capital Development Partners
McKinney Properties
Terra Capital
JLL (Jones Lang LaSalle)
Triple Five Group
The Georgetown Company
How it works

Built around your right-of-way permit.

Bremerton holds the performance deposit before your right-of-way work goes ahead and keeps it until the work is accepted. Here is the whole process, from quote to permit:

TODAY · ONE APPLICATION

Send us the project

Apply online with your business details, the bond amount the City set, the contractor name, the project address and the expected completion date. There is no credit section and no SSN field on this application.

WITHIN 1 BUSINESS DAY

A surety specialist prices it

The City has already sized the deposit from the approved cost estimate, so the review is about the project and the amount, not about re-estimating your work. A specialist confirms your exact premium and sends it back for approval.

ON APPROVAL

Pay, e-sign & file with Public Works

Once you accept the quote and pay, the executed bond arrives by email, ready to file with the Engineering Division of the Department of Public Works and Utilities with your right-of-way use permit. The City requires the instrument on a form acceptable to its Risk Manager, so send us the City’s form if one was issued to you.

About this bond

What it is and who needs it.

What the Bremerton right-of-way bond guarantees

Bremerton controls private use of its streets, sidewalks and other public right-of-way through Chapter 11.02 of the Bremerton Municipal Code. Section 11.02.060 makes it unlawful to make private use of any public right-of-way without first obtaining a right-of-way use permit from the City. Construction work falls under a Type B permit, which covers anything that alters the appearance of, or disturbs the surface or subsurface of, the right-of-way — boring and jacking, culverts, curb cuts and driveway approaches, curbs, gutters and sidewalks, drainage facilities, landscaping, paving, street trenching and utility installation — and the initial construction of improvements that must meet City standards.

Section 11.02.220 then requires a performance deposit to ensure the work conforms to the plans, specifications, standards, permit requirements and development guidelines. The minimum is 150% of the estimated value of the work and the estimated cost to restore existing improvements, as determined by the Director of Public Works and Utilities. The deposit may be cash, a non-revocable letter of credit, an assignment of funds, or a bond on a form acceptable to the City Risk Manager — but the City accepts a bond only for amounts over $1,000. The City’s current Design and Construction Standards restate the rule: for private development, performance and warranty deposits follow BMC 11.02.220, and the developer’s cost estimate must be prepared, stamped and itemized by an engineer licensed in Washington.

If the work is incomplete or defective, or existing improvements are damaged, the Director must give written notice stating what must be fixed and the time allowed before drawing on the deposit; if the work still is not done, the City uses the proceeds to complete it, and the issuer must pay City invoices within 45 days. It is a three-party arrangement: you (the principal), the surety, and the City of Bremerton (the obligee). It is not insurance for you — if the surety pays the City, you repay the surety. The performance deposit is released only after a separate two-year warranty deposit is posted and acceptable record drawings are filed.

Bremerton Municipal Code § 11.02.220Bremerton Municipal Code § 11.02.220 (Performance and Warranty Deposits) requires a performance deposit to ensure conformance with the plans, specifications, standards, permit requirements, development guidelines and other requirements. The minimum amount is 150 percent of the estimated value of the work and the estimated cost to restore existing improvements, as determined by the Director, and performance deposits are not released until a warranty deposit is received. The warranty deposit covers workmanship and materials of improvements in the right-of-way for two years, at a minimum of 20 percent of actual construction costs. The deposit instrument may be cash, a non-revocable letter of credit, an assignment of funds, bond or other readily accessible source of funds approved by the City Risk Manager, on a form acceptable to the City Risk Manager; any issuer must pay City invoices within 45 days, and a bond is accepted only for amounts over $1,000 or when State law requires one. Before using the proceeds, the Director must give written notice of the work required and the time allowed to complete it. Section 11.02.060 requires a right-of-way use permit for any private use of the public right-of-way, and § 11.02.230 requires $500,000 of comprehensive general liability insurance naming the City as additional insured. The City’s current Design and Construction Standards, Division 1, § 1-70, apply these deposits to private development and restate the 150% right-of-way figure; performance bonds on City public works contracts follow the individual contract instead.

You need this bond if you’re

✓
A developer or site contractor building street, curb, sidewalk or drainage improvements in the Bremerton right-of-way for a private development
✓
A utility or telecom contractor trenching, boring or installing facilities in a city street under a Type B permit
✓
A paving or concrete contractor cutting a driveway approach, curb ramp or sidewalk panel in the public right-of-way
✓
A builder or owner’s contractor whose right-of-way deposit exceeds $1,000 and would rather post a bond than tie up cash or a letter of credit
After you buy

Claims, renewal, filing, and what sets the price.

If a claim is made

A claim comes from the party the bond protects, the obligee named on the form, when the duty the bond guarantees is not met.

The surety investigates and pays a valid claim, up to the bond amount. You then repay the surety: a surety bond is a guarantee of your performance, not insurance for you.

Renewal and term

Term and renewal are set in the underwriter's quote.

Keep the bond in force for as long as the obligation behind it runs.

How to file it

Pay, e-sign & file with Public Works. Once you accept the quote and pay, the executed bond arrives by email, ready to file with the Engineering Division of the Department of Public Works and Utilities with your right-of-way use permit. The City requires the instrument on a form acceptable to its Risk Manager, so send us the City’s form if one was issued to you.

What sets the price

This bond is underwritten: the premium is quoted from the bond amount and your financial picture, so there is no flat price to show.

One application, one specialist review.

These are the actual issuing fields — your business details, the bond amount the City set, the contractor name, the project address and the completion date. There is no credit section on this bond. Submit once and a surety specialist returns your exact price, typically within one business day. Free until your bond is issued.

Start the application →
FAQ

Common questions.

What is a Washington right-of-way performance bond for the City of Bremerton?It is a surety bond posted as the performance deposit Bremerton Municipal Code § 11.02.220 requires for work under a right-of-way use permit. It guarantees that your work in a city street, sidewalk or other public right-of-way conforms to the approved plans and City standards and that damaged improvements are restored. If you do not complete or correct the work after written notice, the City can use the bond to have it done.
Who sets the bond amount?The Director of Public Works and Utilities does. The code sets the minimum at 150% of the estimated value of the work plus the estimated cost to restore existing improvements. For private development, a Washington-licensed engineer prepares an itemized, stamped cost estimate from the approved plans, and the Engineering Division reviews it. The City accepts a bond only when the deposit is more than $1,000; smaller deposits must be cash or another instrument.
How much does it cost?This bond is not on our carrier’s published rate sheet, and the penal sum is different on every project, so we quote it on review instead of showing a number checkout might not match. Submit the application with the City’s bond amount, the project address and the completion date, and a surety specialist confirms your exact premium, typically within one business day. The bond amount is the surety’s maximum liability to the City, not something you pay.
Will I need collateral?Usually not on an ordinary permit. On a large development, where 150% of the engineer’s estimate can run high, underwriting may ask for more information or, occasionally, collateral — and we tell you before you commit to anything. The bond issues the moment you pay — no credit review of any kind, not even a soft pull.
When is the bond released, and is there a second bond?The performance deposit stays in place until the City accepts the work. Under § 11.02.220 it is not released until a warranty deposit is received, and § 11.02.160 requires acceptable record drawings first. The warranty deposit is a separate obligation: at least 20% of actual construction costs, covering workmanship and materials for two years. Plan for both when you schedule the project.
Which A-rated carriers underwrite these bonds?Typically Arch Insurance Company (A.M. Best A+) or Nationwide Mutual Insurance Company (A.M. Best A). Which one writes your bond depends on the bond type and your state. The carrier's name and official signature are printed on the bond you receive.
How do I contact Light RFP about this bond?Email insurance@lightrfp.com. It reaches the bond team at Light RFP Risk Management Services LLC (NY DFS License # PC-1978982). Write to us about quotes, applications, bond forms or certificates. We will respond within 24 hours.
Related bonds

Other Washington bonds.

Requirements checked on the carrier’s application, . Page updated .

Get the Bremerton right-of-way bond off your permit checklist.

Send us the City’s bond amount, the project address and the completion date, and a surety specialist returns your price, typically within one business day. Free until issued.

PricingOn review
Apply now →