Waco concrete contractor bonds.
$100 flat.

Before the City of Waco will issue a permit for sidewalk, curb, gutter, driveway approach or other concrete work on public property, the contractor must deliver a bond payable to the City under Waco Code Sec. 22-72. The City's own bond form calls for a $5,000 penal sum. Ours is $100 flat for a term.

✓
Required by Waco Code Sec. 22-72 before any concrete work on public property in the city
✓
A $5,000 bond payable to the City of Waco, continuous in form
✓
Backs a 12-month maintenance and repair guarantee on every sidewalk, curb, gutter and drive approach you pour
$100 flattermInstantunderwriting processNo credit checkfor this bond
Trusted by industry leaders
New York City Economic Development Corporation (NYCEDC)
Blumenfeld Development Group (BDG)
Capital Development Partners
McKinney Properties
Terra Capital
JLL (Jones Lang LaSalle)
Triple Five Group
The Georgetown Company
New York City Economic Development Corporation (NYCEDC)
Blumenfeld Development Group (BDG)
Capital Development Partners
McKinney Properties
Terra Capital
JLL (Jones Lang LaSalle)
Triple Five Group
The Georgetown Company
How it works

Three steps. One sitting.

Waco's Engineering Department issues concrete permits only to bonded concrete contractors, so the bond comes before the right-of-way permit. Here is the whole process:

NOW · ONLINE

Apply for the $5,000 bond

The bond amount is already set on the application. Enter your business details and the effective date you want the bond to start. No credit check.

MINUTES, USUALLY

Pay & e-sign

The price is $100 flat for a term — the price you see is the checkout price. Pay and the bond issues right after purchase.

SAME DAY

File with the City Secretary

Your executed bond and the surety's power of attorney arrive by email. The original goes to the Waco City Secretary's Office with a same-date power of attorney attached; then apply for your right-of-way concrete permit through the Engineering Department.

About this bond

What it is and who needs it.

What the Waco concrete contractor bond covers

In Waco, concrete poured on private property is handled under a building permit, but anything that touches the public right-of-way — sidewalks, curb and gutter, driveway approaches and other flatwork on city property — is regulated by the Engineering Department. Waco Code Sec. 22-66 says no one may build, rebuild, alter, repair, remove or replace that work "without first obtaining a permit from the city engineer", and the Engineering Department issues concrete permits only to bonded concrete contractors. Sec. 22-72 is the bond itself: no person may do the work without delivering to the City "a bond payable to the city in an amount and with a surety company approved by the city attorney."

The bond is a three-party promise. You are the principal, the surety backs your obligation, and the City of Waco is the obligee. Sec. 22-72 lists the conditions: the work is done in a good and workmanlike manner; it meets the City's concrete specifications and ordinances; the City is indemnified and held harmless for injury or damage the work causes; and you maintain and repair each job for 12 months from completion at no extra cost to the owner. If you do not make a required repair, the City can have the work done and recover the cost, and the ordinance also covers cleanup costs and suits by the City or an injured party. A valid claim is paid up to the $5,000 penal sum. It is not insurance for you — you repay the surety for any claim it pays.

The City's form makes the bond continuous: it stays in force until the surety cancels it by giving 30 days' written notice to the City Secretary, and cancellation applies only to work started after that notice period ends. After a claim is paid, the City can require an additional bond so the total is again equal to the original sum. Keep one thing separate: Waco's Chapter 23 right-of-way management rules impose a different, variable-amount bond and insurance on utility and right-of-way "users". That is not this bond — the $5,000 concrete contractor's bond is the one Engineering asks for before it issues a concrete permit.

Waco Code of Ordinances Sec. 22-72City of Waco, Texas Code of Ordinances, Chapter 22 (Streets, Sidewalks and Certain Other Public Places), Article III (Sidewalks, Curbs, Gutters, Driveways), Sec. 22-72 "Contractors required to file bond" (Ord. No. 2008-606): no person shall construct, reconstruct or repair any sidewalk, curb or gutter or other concrete work on public property in the city without delivering a bond payable to the city in an amount and with a surety approved by the city attorney. Sec. 22-66 requires a permit from the city engineer for the same work. The amount is set on the City's Concrete Contractor's Bond form, published by the Engineering Department, which names a $5,000 penal sum payable to the City of Waco. File the original, with a same-date power of attorney, at the City Secretary's Office.

You need this bond if you’re

✓
A concrete contractor pouring sidewalks, curbs or gutters on City of Waco property
✓
A driveway or flatwork crew tying a new drive approach into a Waco street
✓
A home builder or GC whose job includes sidewalk or curb work in the right-of-way
✓
An out-of-town contractor pulling a Waco right-of-way concrete permit for the first time
After you buy

Claims, renewal, filing, and what sets the price.

If a claim is made

A claim comes from the party the bond protects, the obligee named on the form, when the duty the bond guarantees is not met.

The surety investigates and pays a valid claim, up to the $5,000 bond amount. You then repay the surety: a surety bond is a guarantee of your performance, not insurance for you.

Renewal and term

The term is set on the carrier’s application; the premium covers the period shown there.

Renew before the expiry date to keep the bond in force: the license, permit or contract it backs expects continuous coverage.

How to file it

File with the City Secretary. Your executed bond and the surety's power of attorney arrive by email. The original goes to the Waco City Secretary's Office with a same-date power of attorney attached; then apply for your right-of-way concrete permit through the Engineering Department.

What sets the price

The premium is fixed at $100 at the $5,000 amount for every applicant: the carrier’s rate book prices this bond by the form, not by your credit or your business profile.

No credit check.

One application, issued instantly.

These are the actual issuing fields — your business details and the effective date, with the $5,000 bond amount already set. No credit check. $100 flat for a term. Free until your bond is issued.

Start the application →
FAQ

Common questions.

What is a Texas concrete contractor bond for the City of Waco?It is the surety bond Waco Code Sec. 22-72 requires of anyone who builds or repairs sidewalks, curbs, gutters or other concrete work on public property in the city. The City's form sets the penal sum at $5,000, names the City of Waco as obligee, and guarantees good workmanship, compliance with City specifications, indemnity for damage, and a 12-month repair obligation on each job.
Who sets the bond amount?The City does. Sec. 22-72 leaves the amount to the city attorney's approval, and the City's Concrete Contractor's Bond form names a $5,000 penal sum, which is preset on our application. If a claim is paid, the City can require an additional bond to bring the total back up to the original sum.
How much does it cost?The premium is $100 flat for a term — set by our carrier's rate book for this bond, not a percentage formula, so there is no quote process. The $5,000 is the surety's maximum liability to the City, not something you pay, and the City's permit and inspection fees are separate.
Is there a credit check?No credit check: the application collects no credit information. Most applications approve instantly.
Does the bond expire, and where do I file it?The City's form makes the bond continuous, so there is no fixed expiration date; it runs until the surety cancels on 30 days' written notice to the City Secretary, and each job stays covered for its 12-month maintenance period. The signed original goes to the Waco City Secretary's Office with a power of attorney dated the same day, and the Engineering Department then issues right-of-way concrete permits to you as a bonded contractor.
Which A-rated carriers underwrite these bonds?Typically Arch Insurance Company (A.M. Best A+) or Nationwide Mutual Insurance Company (A.M. Best A). Which one writes your bond depends on the bond type and your state. The carrier's name and official signature are printed on the bond you receive.
How do I contact Light RFP about this bond?Email insurance@lightrfp.com. It reaches the bond team at Light RFP Risk Management Services LLC (NY DFS License # PC-1978982). Write to us about quotes, applications, bond forms or certificates. We will respond within 24 hours.
Related bonds

Other Texas bonds.

Been told you need a different amount?

Price and requirements checked on the carrier’s application, .

Get bonded before you pour in Waco.