04 Sept 2026: Amend 0001: The purpose is to add an additional definitive work item into the Specs (WORK ITEM 3: Talon Grid (Type 18-08), Inspect and Test), extend the proposal due date from 14 Sept 2026 to 28 Sept 2026, provide a s****uspense date of NLT 11AM EST, 11 Sept 2026 for technical package requests due to the additional work item, and provide the following revised documents: Attachment A - Specification CALHOUN (WMSL-759), Rev 1, dtd 03SEP2026 and Attachment B Pricing CALHOUN (WMSL-759) SOS&S, Rev 1.
This requirement is for the Contractor to provide all necessary labor, services, supplies, materials, equipment, power, accessories, personnel, and other things as necessary, except otherwise specified to perform dockside repairs to the USCGC CALHOUN (WMSL-759), a 418' National Security Cutter in accordance with the solicitation, schedule and specifications.
Reference Attachment A - Specification, Rev-0 dated 20 August 2026. The Work Items included but not limited to the following:
WORK ITEM 1: Circuit Breakers (Draw Out), Inspect and Test
WORK ITEM 2: Miscellaneous System Relief Valves, 5 Year Certification
WORK ITEM 3: Deck Covering (Slip-Resistant) Stern Deck, Renew
WORK ITEM 4: Tenting (Stern Deck), Provide
WORK ITEM 5: Deck Covering (Polymeric), Repair and Seal
WORK ITEM 6: Tanks (MP Fuel Service), Clean and Inspect
WORK ITEM 7: Tanks (MP Fuel Storage and Overflow), Clean and Inspect
WORK ITEM 8: Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect
WORK ITEM 9: Tank (Water Mist), Clean and Inspect
WORK ITEM 10: Tanks (Water Mist), Preserve (Partial)
WORK ITEM 11: Potable Water Pneumatic Tank, Clean and Inspect
WORK ITEM 12: TCTO: Dewatering Overboard Discharge Connections, Install
WORK ITEM 13: TCTO: Potable Water FWD Hose Connection, Install
WORK ITEM 14: TCTO: Dry Provision Storeroom, Modify
WORK ITEM 15: TCTO: HVAC System (Port Aft Capstan), Modify
WORK ITEM 16: TCTO: Weather Deck Scuppers, Install
WORK ITEM 17: MPAC Demister, Install
WORK ITEM 18: Temporary Services, Provide – Cutter
WORK ITEM 19: Welding, Provide (General)
WORK ITEM 20: Fire Prevention, Provide.
Please reference Attachment G - CALHOUN DS FQ2 FY27 -Provisions and Clauses. The following are identified hard dates:
NLT 26 AUG 2026, by 12PM EST - Requests for Techncial Packages are due.
NLT 03 SEPT 2026, by 12PM EST - Any /all questions related to this solicitation are due.
NLT 14 SEPT 2026, by 12PM EST - Quotes are due.
The Contractor shall furnish all necessary labor, materials, services, equipment, supplies, power, accessories, facilities, and all other items required—except as otherwise specified—to perform dockside repairs in accordance with this solicitation and all attached specifications. The scope of work includes ship repair and associated support work and may include work not currently listed as individual Work Items. The work items include: WORK ITEM 1: Circuit Breakers (Draw Out), Inspect and Test; WORK ITEM 2: Miscellaneous System Relief Valves, 5 Year Certification; WORK ITEM 3: Talon Grid (Type 18-08), Inspect and Test; WORK ITEM 4: Deck Covering (Slip-Resistant) Stern Deck, Renew; WORK ITEM 5: Tenting (Stern Deck), Provide; WORK ITEM 6: Deck Covering (Polymeric), Repair and Seal; WORK ITEM 7: Tanks (MP Fuel Service), Clean and Inspect; WORK ITEM 8: Tanks (MP Fuel Storage and Overflow), Clean and Inspect; WORK ITEM 9: Tanks (Aviation Fuel Stowage and Overflow), Clean and Inspect; WORK ITEM 10: Tank (Water Mist), Clean and Inspect; WORK ITEM 11: Tanks (Water Mist), Preserve (Partial); WORK ITEM 12: Potable Water Pneumatic Tank, Clean and Inspect; WORK ITEM 13: TCTO: Dewatering Overboard Discharge Connections, Install; WORK ITEM 14: TCTO: Potable Water FWD Hose Connection, Install; WORK ITEM 15: TCTO: Dry Provision Storeroom, Modify; WORK ITEM 16: TCTO: HVAC System (Port Aft Capstan), Modify; WORK ITEM 17: TCTO: Weather Deck Scuppers, Install; WORK ITEM 18: MPAC Demister, Install; WORK ITEM 19: Temporary Services, Provide – Cutter; WORK ITEM 20: Welding, Provide (General); WORK ITEM 21: Fire Prevention, Provide.
We post new fuel & energy opportunities in South Carolina as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"US""94501""ALAMEDA""CA""USA""COAST GUARD ISLAND, BLDG 50-7""Amend 00001 to Solicitation 70Z08526QLREP0025_04SEPT2026.pdf"615495"file"".pdf""1""2026-09-04T12:09:27.853+00:00""b663434893024498888325b4d94e9dcc""public""0""public""6a2c97baa3964dce8e3f3a7a175afaa8""0"11"0""Attach B - Pricing Schedule_CALHOUN (WMSL 759) DS FQ2 FY27_SOSandS R1.xlsx"20936"file"".xlsx""1""2026-09-04T12:09:27.853+00:00""aeed5028053a4f989caad414c7d3f10a""public""0""public""ddd2a071679946fd89cf02c595bc9167""0"10"0""Attach A_ Specification CALHOUN (WMSL 759) DS FQ2 FY27R1.pdf"3433261"file"".pdf""1""2026-09-04T12:09:27.853+00:00""beeb5e12e81c4ffaab7ab7eeabab2756""public""0""public""f191a5117cbd432798228d652f2fc5dd""0"9"0""Attachment G- CALHOUN DS FQ2 FY27 - Provisions and Clauses.pdf"754973"file"".pdf""1""2026-08-20T18:04:29.311+00:00""838c924c69d54d1a96a8b78b697dc663""public""0""public""20184dbcfde542098dc5cdcf574503f5""0"8"0""Attachment F- Non-Disclosure Agreement.pdf"3565430"file"".pdf""1""2026-08-20T18:04:29.311+00:00""a6d9d018575c40a0b4f6e75917635cd0""public""0""public""6f2eaf8e290d45689cc837f85d44edc3""0"7"0""Attachment E- FLETC Base Access and Pier Laydown.pdf"728287"file"".pdf""1""2026-08-20T18:04:29.311+00:00""43c2aafe44484030bd4c2628d816148e""public""0""public""e30c9426aeda462094d4a4b541807c70""0"6"0""Attachment D - Past Performance Questionnaire (PPQ) USCGC CALHOUN (WMSL-759) (003).docx"28800"file"".docx""1""2026-08-20T18:04:29.311+00:00""38b4593b882245c9b6b019541878841e""public""0""public""737261f515104b9b80a91f394c736f69""0"5"0""Attachment C - Request for Clarification USCGC CALHOUN (WMSL-759).docx"21767"file"".docx""1""2026-08-20T18:04:29.311+00:00""a68d2a6acfd8456880b5699f50ad2c96""public""0""public""4baa2e96f1cb41d8917bd9a7a9095c1e""0"4"0""Attachment B- Pricing Schedule CALHOUN (WMSL-759).xlsx"19315"file"".xlsx""1""2026-08-20T18:04:29.311+00:00""95b078a5ca6c49a591a1e7b5cf1fa40e""public""0""public""28da8fef3db54a16a644dfaf46da7a66""0"3"0""Attachment A- Specification CALHOUN (WMSL-759) REV0.pdf"3903940"file"".pdf""1""2026-08-20T18:04:29.311+00:00""51d58624627541a181f3f74c95089c63""public""0""public""35383c2e93394121ab2d60c6c9af0a99""0"2"0""70Z08526QLREP0025 CALHOUN DS FQ2 FY27.pdf"187517"file"".pdf""1""2026-08-20T18:04:29.311+00:00""d8493d9462774046bbd408fa31e4ba82""public""0""public""7f1ff2ce04804d4382907e31785c5b49""0"1"0"Most South Carolina work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: SAM.gov (notice e17526361ea540188826730ae7d980dc), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.