*** Amendment 0001 has been issued.
The purpose of this Amendment 0001 is to:
Incorporate revised Performance Work Statement (PWS) dated 20 August 2026.
Incorporate Attachment titled: Referenced Conceptual Drawings.
Provide updated answers to all questions.
Extend the quote due date to 3 September 2026, no later then 11:00 AM Pacific Time.
No other changes made or implied.***
The Questions and Answers, and the site visit sign-in sheet are posted
A site visit will be conducted on** August 13, 2026 at 11:00 AM PDT. **Interested offerors shall meet at 2713 Hogan Dam Road, Valley Springs, CA 95252. Point of Contact for Site Visit is Leah Peterson. The purpose of the site visit is to familiarize offerors with the locations and conditions affecting contract performance. Offerors are responsible for all costs associated with attending the site visit. Failure to attend the site visit will not relieve the Contractor from performing all requirements of the contract.
All questions for this solicitation must be submitted in writing, via e-mail, to the pont of contacts listed below.
All questions must be submitted no later then Friday, August 14, 2026, at 11:00AM PDT**, **No additional questions will be accepted after this date.
Quotes must be submitted via e-mail, to Antonina Beal at antonina.beal@usace.army.mil.
The contractor shall demolish the existing restroom and remove all debris to an offsite location; prepare a prefabricated concrete pad (approximately 27x33 feet) after removing the entire existing slab and foundation; purchase and deliver one new prefabricated concrete cast waterborne restroom with a 26x30 footprint, including four unisex restroom/shower combos, a utility chase not exceeding 104 square feet, and features such as stainless steel fixtures, LED lighting, skylights, and ADA-compliant components; and place and connect the restroom to existing water, electrical, and sewer utilities. The work is to be performed at Acorn Campground, New Hogan Lake, Valley Springs, CA, with the campground remaining open during construction. The contractor is responsible for all delivery, crane work, and installation, and must coordinate with the COR. The period of performance is 365 days from award, with work to be performed within normal business hours (0800-1630, Monday through Friday) unless otherwise coordinated.
We post new general contractors opportunities in California as agencies publish them. Get them in one email — free, and unsubscribe whenever.
"95814-2922""SACRAMENTO""CA""USA""KO CONTRACTING DIVISION""1325 J STREET""Additional Q and A - KO Approved.pdf"127386"file"".pdf""1""2026-08-20T22:52:12.8+00:00""9c2e622bdcdb4f2f866fd1375532f79b""public""0""public""5cc1d435f3884d8a910940068a19e6d7""0"9"0""Amendment W9123826QA0310001 SF 30.pdf"4117121"file"".pdf""1""2026-08-20T22:52:12.8+00:00""9bd3320621b24ebb9395be540a8189ed""public""0""public""61c605c6c52741b7bbe538356e836b0c""0"8"0""Referenced Conceptual Drawing.pdf"377521"file"".pdf""1""2026-08-20T22:52:12.8+00:00""5cebd85d729843e6847cfe1903ddd81f""public""0""public""4af3f4a787ff43a3985029542bfd735a""0"7"0""PWS Revised - 20 Aug 2026 KO Approved.pdf"223529"file"".pdf""1""2026-08-20T22:52:12.8+00:00""10e2ba273a894f41836fa652c8114983""public""0""public""e03e8349094541668cccccd18c2e808e""0"6"0""Site Visit Sign-in Sheet - 20260813.pdf"129419"file"".pdf""1""2026-08-14T21:08:27.367+00:00""087a1599ab60457a9929a4023098fe6e""public""0""public""03e5007cc1f5473ab54ca6e1f28cb09c""0"5"0""Questions and Answers KO Approved.pdf"108526"file"".pdf""1""2026-08-14T21:08:27.367+00:00""324230f0e0344dfc8c4570e6a60f089d""public""2026-08-20T22:52:12.8+00:00""1""public""eeac1955822e4992ac60b1fbeb9b30bb""0"4"0""2026-08-20T22:52:12.8+00:00""Solicitation - W9123826QA031.pdf"3226710"file"".pdf""1""2026-07-31T16:20:42.787+00:00""b60a8d9cb27d4a1d9a2f281168f46586""public""0""public""3ec5f9bf399840c8aecae47c61da8868""0"3"0""PWS - 7.29.26.pdf"219159"file"".pdf""1""2026-07-31T16:20:42.787+00:00""837d5baaf909436d902091065120c8f5""public""2026-08-20T22:52:12.8+00:00""1""public""a9ee8b7338c247418d0df3fed67b9168""0"2"0""2026-08-20T22:52:12.8+00:00""WAGE DETERMINATIONS - 05.13.2026.pdf"77493"file"".pdf""1""2026-07-31T16:20:42.787+00:00""558564ddb649411bacabfe8bb12052d9""public""0""public""5af16e175fd2496d80a4c289296688d9""0"1"0"Most California work asks for the two below, and the solicitation documents are where it’s stated. Here’s what each costs through Light RFP if you need one.
Source: SAM.gov (notice b61164f8b3214d1b9d08306d73b35b92), retrieved via the SAM.gov Get Opportunities API. View the official posting, and always confirm requirements and deadlines with the issuing agency.